Board of Managers of the Courtyards at the Woodlands Condominium Ass'n v. Iko Chicago, Inc.

697 N.E.2d 727, 183 Ill. 2d 66, 231 Ill. Dec. 942, 1998 Ill. LEXIS 914
CourtIllinois Supreme Court
DecidedJune 18, 1998
Docket83578
StatusPublished
Cited by54 cases

This text of 697 N.E.2d 727 (Board of Managers of the Courtyards at the Woodlands Condominium Ass'n v. Iko Chicago, Inc.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Managers of the Courtyards at the Woodlands Condominium Ass'n v. Iko Chicago, Inc., 697 N.E.2d 727, 183 Ill. 2d 66, 231 Ill. Dec. 942, 1998 Ill. LEXIS 914 (Ill. 1998).

Opinions

CHIEF JUSTICE FREEMAN

delivered the opinion of the court:

Plaintiff, Board of Managers of the Courtyards at the Woodlands Condominium Association, filed a complaint against the developers of the condominium, Zale Groves, Inc., Zale Group, Inc., Zale Enterprises, Inc., and Zale Construction Company (collectively, the Zale defendants), for alleged defects in the design and construction of the development’s roofs. The Zale defendants filed a third-amended third-party complaint against Johnston Associates, Inc. (Johnston), and certain other entities which contracted with the Zale defendants to build the roofs. At issue in this case is the contract between Zale Construction Company and Johnston in which Johnston agreed to furnish architectural and design services for the buildings. The contract also included an arbitration clause. Based upon this clause, Johnston filed a written demand for arbitration with the American Arbitration Association. Johnston also filed a motion to compel arbitration and stay the third-party claims against it pursuant to section 2(a) of the Illinois Uniform Arbitration Act (710 ILCS 5/2(a) (West 1994)). Relying on J.F. Inc. v. Vicik, 99 Ill. App. 3d 815 (1981), the trial court denied Johnston’s motion, finding that the issues and parties were so “intertwined” and “interconnected” that “they could not be resolved without all the parties being a part of this litigation.” Johnston appealed to the appellate court, which affirmed the trial court’s decision. See 288 Ill. App. 3d 801, 807. We granted Johnston’s petition for leave to appeal (166 Ill. 2d R. 315) and now reverse the decision of the appellate court.

BACKGROUND

The detailed facts of the case are fully set forth in the appellate court opinion. 288 Ill. App. 3d 801. We will provide the relevant background necessary to dispose of the issue presented.

The plaintiff maintains the common elements of a 128-building condominium development in Buffalo Grove, Illinois. In 1994, plaintiff filed a complaint against the Zale defendants seeking damages for alleged defects in the design and construction of the condominium’s roofs. On March 1, 1996, the Zale defendants filed their third-amended third-party complaint against IKO Chicago, Inc., WA. Anderson Construction Company, Lenny Szarek, Inc., Prate Roofing, Inc., S.J. Nitch/Roof Brokers, Inc., All American Roofing, Inc., and Johnston. The Zale defendants premised their third-party action solely on theories of conditional contribution or indemnification. The Zale defendants did not allege any independent causes of action against any third-party defendant.

In count VII of the third-amended third-party complaint, the Zale defendants alleged that they entered into a written contract with Johnston in which Johnston agreed to furnish architectural and design services for the buildings. The Zale defendants further alleged that “the actions of which plaintiff complains in its fifth amended complaint are services furnished in part by-third party defendant [Johnston].”

The contract between Johnston and Zale Construction Company included the following provision:

“Either party may demand in writing arbitration of all claims, disputes or questions of this Contract or breach thereof in accordance with the prevailing rules of the American Arbitration Association, within reasonable time before the date legal proceedings would be barred by applicable statute of limitations, and judgment upon the award rendered by the arbitrators shall be final and may be entered in any court having jurisdiction thereof.”

Based on this arbitration clause, Johnston filed and served a written demand for arbitration with the American Arbitration Association on April 4, 1996. On that same day, Johnston filed a motion to compel arbitration and stay the third-party claims against it pursuant to section 2(a) of the Illinois Uniform Arbitration Act (the Act) (710 ILCS 5/2(a) (West 1994)).

Plaintiff, the Zale defendants, and W.A. Anderson Construction Company opposed Johnston’s motion, relying on the decision in Vicik. The Vicik court held that the policy favoring arbitration may give way to competing policies favoring joinder of claims in light of the following factors: decreased delay, complexity and costs, resolution of common issues in a single forum, desirability of consistent results, and prejudicing or affecting parties who did not execute an arbitration agreement. 288 Ill. App. 3d at 806. The Zale defendants argued that Johnston’s motion should be denied because the “issues in this case are inextricably intertwined, intermingled and dependent upon each other such that the issues raised in count VII cannot be severed.”

Johnston responded by stating that since there was no dispute as to the agreement to arbitrate, its motion should be granted. Johnston argued that the trial court should not apply the Vicik analysis because Vicik has been criticized by Illinois courts. Johnston further argued that the public policy considerations enumerated in Vicik were insufficient to override the general rule in Illinois that arbitration agreements in multiparty proceedings should be enforced.

On June 11, 1996, the trial court denied Johnston’s motion based on the reasoning in Vicik. While recognizing the validity of the arbitration agreement, the trial court nonetheless found that the “problems would be enormous” if it were to allow arbitration to proceed either before or during litigation of the underlying action. The court stated that inconsistent results “might prejudice various other parties in this litigation. And prejudice is one of the factors that the court is considering here in relying on its ruling.” On appeal, the appellate court affirmed the trial court. The court applied the Vicik factors and concluded that prejudices and inequities might result if the court compelled arbitration in this case. 288 Ill. App. 3d at 806-07.

ANALYSIS

Johnston argues that the trial court erred in denying arbitration once the court found that a valid arbitration agreement existed. Johnston bases this argument upon section 2(a) of the Act, which provides:

“On application of a party showing an [arbitration] agreement ***, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration, but if the opposing party denies the existence of the agreement to arbitrate, the court shall proceed summarily to the determination of the issue so raised and shall order arbitration if found for the moving party, otherwise, the application shall be denied.” 710 ILCS 5/2(a) (West 1994).

Based on the plain language of the statute, Johnston is correct that at a hearing to stay a judicial proceeding and to compel arbitration, the trial court should concern itself solely with whether an agreement exists to arbitrate the dispute in question. See J&K Cement Construction, Inc. v. Montalbano Builders, Inc., 119 Ill. App. 3d 663, 669 (1983).

Here, the parties do not deny the existence of the arbitration clause in the contract between Johnston and Zale Construction Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bricker v. Heinz
2025 IL App (4th) 250264-U (Appellate Court of Illinois, 2025)
Barron v. City of Chicago
2025 IL App (1st) 240066 (Appellate Court of Illinois, 2025)
Xiang Zhao v. State Farm Fire & Casualty Co.
2025 IL App (2d) 240723 (Appellate Court of Illinois, 2025)
Kalmin v. Weinberg
2022 IL App (1st) 211651-U (Appellate Court of Illinois, 2022)
American Economy Insurance Company v. Accelerated Rehabilitation Centers, Ltd
2022 IL App (1st) 211410-U (Appellate Court of Illinois, 2022)
CSC Partners Management, LLC v. ADM Investor Services, Inc.
2021 IL App (1st) 210136 (Appellate Court of Illinois, 2021)
Messmore v. Silvis Operations, LLC
2018 IL App (3d) 170708 (Appellate Court of Illinois, 2018)
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Ass'n
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Association
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Koehler v. The Packer Group, Inc.
2016 IL App (1st) 142767 (Appellate Court of Illinois, 2016)
GPS USA, Inc. v. Performance Powdercoating
2015 IL App (2d) 131190 (Appellate Court of Illinois, 2015)
City of Chicago v. Chicago Loop Parking LLC
2014 IL App (1st) 133020 (Appellate Court of Illinois, 2015)
The City of Chicago v. Chicago Loop Parking LLC
2014 IL App (1st) 133020 (Appellate Court of Illinois, 2014)
Johnson v. Orkin, LLC
928 F. Supp. 2d 989 (N.D. Illinois, 2013)
Carter v. SSC Odin Operating Company
2012 IL 113204 (Illinois Supreme Court, 2012)
FAHLSTROM v. Jones
952 N.E.2d 1227 (Appellate Court of Illinois, 2011)
QuickClick Loans, LLC v. Russell
943 N.E.2d 166 (Appellate Court of Illinois, 2011)
Quickclick Loans v. Russell
Appellate Court of Illinois, 2011

Cite This Page — Counsel Stack

Bluebook (online)
697 N.E.2d 727, 183 Ill. 2d 66, 231 Ill. Dec. 942, 1998 Ill. LEXIS 914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-managers-of-the-courtyards-at-the-woodlands-condominium-assn-v-ill-1998.