Park Construction Co. v. Independent School District No. 32

11 N.W.2d 649, 216 Minn. 27, 1943 Minn. LEXIS 433
CourtSupreme Court of Minnesota
DecidedOctober 29, 1943
DocketNo. 33,403.
StatusPublished
Cited by24 cases

This text of 11 N.W.2d 649 (Park Construction Co. v. Independent School District No. 32) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Park Construction Co. v. Independent School District No. 32, 11 N.W.2d 649, 216 Minn. 27, 1943 Minn. LEXIS 433 (Mich. 1943).

Opinion

Peterson, Justice.

On the prior appeal, Park Const. Co. v. Independent School Dist. 209 Minn. 182, 296 N. W. 475, 135 A. L. R. 59, this court held that the complaint stated a cause of action upon an award rendered in a common-law arbitration under a general submission. After our decision, defendant interposed an answer setting up numerous defenses, only one of which was litigated, viz., that upon the face of the proceedings before the arbitrators the award was so erroneous as to compel a finding that the arbitrators acted with prejudice and bias and not in the exercise of a fair and impartial judgment.

The case was submitted below upon the record before the arbitrators, which contained a stenographic report of all the proceedings had and of all the evidence and exhibits received in the arbitration proceedings.

The dispute arose out of plaintiff’s claim for the balance due for work done under a contract with defendant dated December 21, 1938, let upon competitive bidding, to construct a high school athletic field according to plans and specifications prepared by defendant’s architect. The contract price was $5,168.36, from which the parties by supplemental agreement deducted $889.87 for certain omitted work and allowances, reducing it to $4,278.49. During the progress of the work defendant allowed and paid $755.55 and $1,978.20, the amounts of two estimates less 10 percent retained. The balance claimed by plaintiff Avas $1,116.89 plus the retained percentage.

The field was to be constructed by excavating earth from the upper portion of a hill and filling an embankment on the loAver portion thereof and by grading the excavated and filled areas to a common level. The area surrounding the cut in the hill was to *29 be a sort of amphitheater; that surrounding the playing field was to be sloped and graded to the adjacent lands.

The plans showed a total excavation of 10,448 cubic yards and a filled embankment of approximately 15,000 cubic yards. It was obvious, therefore, that the work could not be done according to the plans, because, as plaintiff’s engineer stated, “you cannot build some 15,000 yards of fill and embankment with 10,000 yards of excavation.” The discrepancy was discovered before the contract was signed. Plaintiff’s evidence, which was contradicted by defendant’s, was to the effect that the parties agreed that, in order to get additional excavation for filling, the level of the field should be lowered six-tenths of a foot andPpart of the dirt excavated in building an addition to the school should be used for filling. One of defendant’s officers testified that plaintiff orally agreed to haul dirt from the outside to complete the fill. This plaintiff claims it, was unwilling to do unless it was paid extra compensation. It is undisputed that the members of defendant’s board informed plaintiff’s representatives that it would not pay any additional compensation for dirt hauled from the outside for filling. Notwithstanding their full knowledge of the facts relating to the miscalculation of the amount of filling required and that the embankment could not be adequately filled with the dirt excavated from the cut, the contract was executed and plaintiff entered upon its performance.

There was a sharp dispute as to whether plaintiff was obligated under the contract to procure the filling from the outside. Defendant claimed that plaintiff was required to do so under a provision in the specifications to the effect that the contractor shall furnish all materials and perform all work shown on the plans and described in the specifications. Plaintiff claimed that this provision related to the things the parties contemplated the contractor should supply, such as cinders for the running track (which provision was later eliminated), oil, gasoline, and similar items, but not dirt in place, which was not to be supplied but was to be excavated, moved, and graded. In support of its view, plaintiff contended (1) that providing filling was impliedly excluded from its contractual obli *30 gation by provisions under two separate headings in the specifications, “Rough and Finish Grading” and “Removal and Securing Additional Soil,” requiring the contractor to provide all additional topsoil necessary to complete the work, and the absence of any provision requiring it to provide additional filling; and (2) that, since according to the undisputed testimony of an engineer of large experience in such matters the term “materials” had a well-known meaning which did not include dirt filling under such a contract, the term was to be so construed under a provision of the specifications that words describing materials “shall be construed in accordance with such well-known meaning recognized by architects, engineers and the trade.” *

Likewise, there was a sharp dispute as to whether defendant agreed that the level of the field should be lowered six-tenths of a foot. It denied such an agreement. Although its records showed consent to other changes, they did not show it with respect to this one. For lack of such record, defendant contended that the change was not binding upon it, since the specifications provided that changes could be authorized only “upon proper action by its governing body.” The specifications provided that every part of the work should be executed under the direction and supervision of its architect and that the architect should set the stakes for the rough and, where required for accurate finish grading, finish grading levels. The architect did not direct and supervise the work to any substantial extent or set any grading level stakes. According to the specifications, the rough grading level was to be six inches below that of the finish grade. Because of the omission of defendant’s architect to do so, plaintiff set the stakes for the rough grading. An assistant architect was present at the time and made no objection to the change. With knowledge of the change, he certified that the “entire field has been laid out according to the plans.” During the progress of the work he certified that an estimate on a PWA form, dated December 31, 1938, for $839.50 (less 10 percent retained percentage), filed by plaintiff for rough grading done, according to the level as changed and lowered, was in full *31 accord with the terms and conditions of the “contract documents,” of which the specifications were a part, and “authorized changes thereto.” On April 29, 1939, another assistant architect made a similar certificate for the balance of the rough grading, amounting to $2,198 (less 10 percent retained percentage). Defendant allowed and paid both estimates.

After the estimate of April 29, 1939, was allowed and paid, plaintiff demanded that the architect set the finish grade stakes. Because the architect failed to comply, plaintiff had the stakes set by its own engineer and completed the job, except for some embankment filling, for which no dirt was available on the premises. The testimony tended to show that the excavation of the hill, the filling of the embankment, and the construction of the playing field were according to the plans and specifications, with the exceptions presently to be mentioned. In the corners outside the playing field the embankment was about four feet lower than the plans showed. This was due to lack of filling. In performing the work, plaintiff excavated and moved 14,552 cubic yards of dirt, 4,104 cubic yards more than was shown on the plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seagate Technology, LLC v. Western Digital Corp.
834 N.W.2d 555 (Court of Appeals of Minnesota, 2013)
Abd Alla v. Mourssi
680 N.W.2d 569 (Court of Appeals of Minnesota, 2004)
Vaubel Farms, Inc. v. Shelby Farmers Mutual
679 N.W.2d 407 (Court of Appeals of Minnesota, 2004)
Independent School District No. 279 v. Winkelman Building Corp.
530 N.W.2d 583 (Court of Appeals of Minnesota, 1995)
Kersting v. Royal-Milbank Insurance
456 N.W.2d 270 (Court of Appeals of Minnesota, 1990)
Johnson v. Consolidated Freightways, Inc.
420 N.W.2d 608 (Supreme Court of Minnesota, 1988)
Western Casualty & Surety Co. v. Gridley
362 N.W.2d 100 (South Dakota Supreme Court, 1985)
Taylor v. FITZ COAL CO. INC.
618 S.W.2d 432 (Kentucky Supreme Court, 1981)
Eric A. Carlstrom Construction Co. v. Independent School District No. 77
256 N.W.2d 479 (Supreme Court of Minnesota, 1977)
Snowberger v. Young
536 P.2d 1069 (Court of Appeals of Arizona, 1975)
Nizinski v. Golden Valley Electric Ass'n, Inc.
509 P.2d 280 (Alaska Supreme Court, 1973)
Dehnart v. Waukesha Brewing Co.
124 N.W.2d 664 (Wisconsin Supreme Court, 1963)
Layne-Minnesota Co. v. Regents of the University of Minnesota
123 N.W.2d 371 (Supreme Court of Minnesota, 1963)
Anderson v. Twin City Rapid Transit Co.
84 N.W.2d 593 (Supreme Court of Minnesota, 1957)
Cournoyer v. American Television & Radio Co.
83 N.W.2d 409 (Supreme Court of Minnesota, 1957)
Local 63, Textile Workers Union of America v. Cheney Bros.
141 Conn. 606 (Supreme Court of Connecticut, 1954)
Zelle v. Chicago & North Western Railway Co.
65 N.W.2d 583 (Supreme Court of Minnesota, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
11 N.W.2d 649, 216 Minn. 27, 1943 Minn. LEXIS 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/park-construction-co-v-independent-school-district-no-32-minn-1943.