Ylijarvi v. Brockphaler

7 N.W.2d 314, 213 Minn. 385, 1942 Minn. LEXIS 535
CourtSupreme Court of Minnesota
DecidedDecember 18, 1942
DocketNo. 33,090.
StatusPublished
Cited by27 cases

This text of 7 N.W.2d 314 (Ylijarvi v. Brockphaler) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ylijarvi v. Brockphaler, 7 N.W.2d 314, 213 Minn. 385, 1942 Minn. LEXIS 535 (Mich. 1942).

Opinion

Peterson, Justice.

This is an action to foreclose a mechanic’s lien claimed by plaintiff for labor and material performed and furnished in drilling a well on defendant’s farm pursuant to express contract modified during performance.

The complaint, so far as here material, alleged in substance that the parties made an oral contract by the terms of which plaintiff undertook to dig a well on defendant’s farm and defendant promised to pay him for such work “after the completion of said job” at the rate of $1.65 per lineal foot and to furnish board and lodging to plaintiff and his crew while the work was being done; that plaintiff performed the contract by drilling a well 204 feet deep; and that he was entitled to recover the contract price, which defendant had not paid, and to a mechanic’s lien for the amount of the recovery and foreclosure of the lien.

The answer admitted the contract and further alleged that the parties agreed that a 4-inch casing should be sunk; that plaintiff agreed that the well should furnish a sufficient supply of usable water; and that plaintiff should not be entitled to any pay until after the well was completed and was producing sufficient usable water.

Although no reply is necessary in actions to foreclose mechanic’s liens (see Minn. St. 1941, § 514.11 [Mason St. 1927, § 8500], and Bruce v. Lennon, 52 Minn. 547, 54 N. W. 739), plaintiff interposed a reply alleging that no size of casing was specified; that, although he struck water at a depth of 216 feet (sic), it was not usable; that plaintiff sought usable water at a lower depth; that while engaged in such work defendant so interfered as to make *387 further performance impossible; and that thereupon work was discontinued.

While the pleadings allege that the contract was to “sink” a well, it is apparent from the methods employed and the testimony as a whole that the parties meant that the well should be drilled or bored.

At the trial plaintiff did not stand on the allegations in his pleadings, but claimed that when the well had been drilled to a depth of 204 feet the contract was modified so as to substitute 2%-inch for 4-inch casing. It is not clear whether he also claimed that the contract did not bind him to drill a well that would produce an adequate supply of usable water.

We have examined the evidence with painstaking care. The testimony of defendant and his witnesses, of whom there were four, all related to him, supports the view that the contract was as claimed by him. Plaintiff’s testimony and admissions in the pleadings and briefs amply support defendant’s claims. In effect there was no substantial conflict that the contract as originally made was as defendant claims it was.

The real conflict was whether the contract was modified as claimed by plaintiff. Plaintiff’s evidence is that when the well had been drilled to a depth of 204 feet the contract was modified so as to permit him to use 2%-inch instead of 4-inch casing. As stated above, it is not clear from his testimony whether he also claimed that by the modification he was relieved from the requirement that the well should produce a sufficient supply of usable water.

Defendant’s testimony, which is supported by that of his witnesses, was explicit that there was no agreement to modify the contract as originally made; that when plaintiff had sunk the well to a depth of 204 feet plaintiff obtained one Cichy to assist with the work, using the latter’s equipment; that Cichy brought along some 2%-inch casing; that plaintiff procured some casing of the same size; that, when plaintiff commenced to use the 2%-inch *388 casing to drill the well below the 204 feet to which it was already bored with 4-inch casing, defendant protested and informed him that he would not pay for the well unless 4-inch casing were used; that plaintiff claimed that he had a legal right to reduce the size of the casing from 4 inches to 2y2 inches; that acting under such claim of right plaintiff continued to use the 214-inch casing; that meanwhile defendant consulted a lawyer, who advised him that he would not have to pay unless the contract was performed according to its terms; that by that time plaintiff had sunk the well to a depth of 283 feet, using 2%-inch casing the last 79 feet; that he advised plaintiff that he had consulted counsel and of his insistence that 4-inch casing be used throughout and that he would not pay unless it was used; that some argument between the parties ensued; and that thereupon plaintiff discontinued the work, pulled up the 214-inch casing sunk by him, and removed his equipment from defendant’s premises. The 204 feet of 4-inch casing was allowed to remain in the ground. There was no evidence that the casing which remained in the ground was of any benefit to defendant. It produced no water. It was not shown that it could be used for that purpose, and the inference is that it could not.

Below,. plaintiff claimed the right to recover upon the ground that he performed the contract as originally made until it was modified, and that after the modification he performed it as modified until defendant’s insistence on performance according to the terms of the contract as originally made and his warning not to pay if 214-inch instead of 4-inch casing were used below the depth of 204 feet, which plaintiff claims amounted to a wrongful interference by defendant, making further performance impossible.

The court below found that the contract was as claimed by defendant; that, although plaintiff asked defendant to modify the contract in the respects claimed, defendant refused to consent to the modification; that plaintiff had not performed the contract; and that thereafter plaintiff ceased work and removed his equipment from defendant’s premises. The court concluded that plain *389 tiff was entitled to no relief, and judgment was entered accordingly. Plaintiff appeals.

On the appeal, while asserting the claims made below, plaintiff has shifted his ground somewhat by claiming that when he had drilled the well to a depth of 145 to 150 feet he considered abandoning the job, but continued to perform upon the advice of defendant’s son, who told him that there was nothing else for him to do. This he contends amounts to an abandonment of the contract and the making of a new contract to continue with the work on a quantum meruit basis.

The contract was entire, because by its terms it was to be performed as a whole and the compensation for performance was to be paid as a whole. Uldrickson v. Samdahl, 92 Minn. 297, 100 N. W. 5 (contract to build a house); Blackburn v. Texarkana G. & E. Co. 102 Ark. 152, 143 S. W. 588 (contract to drill a well). The fact that the contract price to be paid by defendant was to be at a stipulated amount per unit of performance such as the price per foot is of no importance. Bentley v. Edwards, 125 Minn. 179, 146 N. W. 347 (contract to sell a tract of land at a stipulated price per acre); Blackburn v. Texarkana G. & E. Co. supra, (contract to drill well at stipulated price per foot).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Helland
2025 ND 63 (North Dakota Supreme Court, 2025)
Southtown Plumbing, Inc. v. Har-Ned Lumber Co.
493 N.W.2d 137 (Court of Appeals of Minnesota, 1992)
Apache Plaza, Ltd. v. Midwest Savings Ass'n
456 N.W.2d 729 (Court of Appeals of Minnesota, 1990)
Levin v. C.O.M.B. Co.
441 N.W.2d 801 (Supreme Court of Minnesota, 1989)
Steffl v. Roediger
406 N.W.2d 535 (Court of Appeals of Minnesota, 1987)
Voight v. Jones
404 N.W.2d 830 (Court of Appeals of Minnesota, 1987)
Paving Plus, Inc. v. Professional Investment, Inc.
382 N.W.2d 912 (Court of Appeals of Minnesota, 1986)
Material Movers, Inc. v. Hill
316 N.W.2d 13 (Supreme Court of Minnesota, 1982)
Morris v. Perkins
603 S.W.2d 711 (Missouri Court of Appeals, 1980)
Gess v. Sill
251 N.W.2d 650 (Supreme Court of Minnesota, 1977)
Larson Bros. Tiling v. Melton
235 N.W.2d 844 (Supreme Court of Minnesota, 1975)
Seegers v. Sprague
236 N.W.2d 227 (Wisconsin Supreme Court, 1975)
Henningson, Durham & Richardson v. Prochnow
477 P.2d 285 (Court of Appeals of Arizona, 1970)
Industrial Rubber Applicators, Inc. v. Eaton Metal Products Co.
171 N.W.2d 728 (Supreme Court of Minnesota, 1969)
Breza v. Thaldorf
149 N.W.2d 276 (Supreme Court of Minnesota, 1967)
Tomlinson Lumber Sales, Inc. v. J. D. Harrold Co.
117 N.W.2d 203 (Supreme Court of Minnesota, 1962)
Tynan v. KSTP, INC.
77 N.W.2d 200 (Supreme Court of Minnesota, 1956)
Bowline v. Gries
218 P.2d 806 (California Court of Appeal, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
7 N.W.2d 314, 213 Minn. 385, 1942 Minn. LEXIS 535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ylijarvi-v-brockphaler-minn-1942.