Southtown Plumbing, Inc. v. Har-Ned Lumber Co.

493 N.W.2d 137, 1992 Minn. App. LEXIS 1173, 1992 WL 358275
CourtCourt of Appeals of Minnesota
DecidedDecember 8, 1992
DocketC7-92-177
StatusPublished
Cited by62 cases

This text of 493 N.W.2d 137 (Southtown Plumbing, Inc. v. Har-Ned Lumber Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southtown Plumbing, Inc. v. Har-Ned Lumber Co., 493 N.W.2d 137, 1992 Minn. App. LEXIS 1173, 1992 WL 358275 (Mich. Ct. App. 1992).

Opinion

OPINION

CRIPPEN, Judge.

Appellants were subcontractors on a residential construction project. Respondents financed the project. The owner/contractor failed to pay appellants for their labor, claiming that respondents had wrongfully refused to furnish the final payments of funding for the project. Appellants brought suit against respondents, claiming unjust enrichment. Following appellants’ ease in chief, the trial court granted respondents’ motion for directed verdict and dismissed the claim with prejudice and on the merits. We affirm.

FACTS

Appellants, five subcontractors, provided labor and materials on a residential construction project. Respondents, Har-Ned Lumber Company and Home Lumber Company, provided financing and lumber materials. John Van Abel, not a party to this action, was the owner of the property, the mortgagor to Home, and the general contractor on the project.

In April 1988, Van Abel and respondent Home entered into an agreement that Van Abel would build a house and Home would provide the construction financing on the project. The agreement was reduced to writing in the form of a construction loan *139 agreement, a mortgage, a first mortgage note, and a guaranty. These documents contain numerous terms and conditions, including the following:

(1) The amount of the loan was to be $240,000.
(2) Van Abel was required to insure the property.
(3) Van Abel was required to pay all persons who furnished labor or materials in connection with the construction.
(4) Van Abel was not permitted to be in default of any of the terms and conditions.
(5) Home was permitted to discontinue making advance payments if Van Abel was in default and Home could then foreclose its mortgage.
(6) No other person had any rights or remedies, under the financial agreement.
(7) There were no third-party rights under the agreement.
(8) Home was not to have any obligation or liability to any claimant for labor performed or materials furnished.
(9) Van Abel promised to repay on or before January 1, 1989, all funds loaned.

Van Abel was not an employee or agent of Home, nor was Van Abel authorized to request or enter into contracts on behalf of Home. In addition, Van Abel was not authorized to assign any rights under the contract to a third-party, such as the subcontractors in this case.

Each appellant is a subcontractor who contracted with Van Abel to construct the house. Van Abel selected each of these companies, negotiated each of their contracts, entered into each contract, supervised the work, accepted pay requests, made draw requests from Home, and paid the subcontractors directly. Van Abel also approved all change orders and work performed. Van Abel understood it was his obligation to pay the subcontractors. Each of the subcontractors in turn signed a contract with Van Abel which demonstrated he was responsible for their payments. Home never negotiated with any of the contractors about the project. Home did not require that the contractors give up any mechanic’s lien rights nor any rights to pursue actions against Van Abel. Finally, Home did not supervise or inspect the work of the subcontractors.

Between April and December 1988, the construction of the house progressed. Pursuant to the financing documents, Van Abel periodically submitted draw requests to Home. Home then disbursed a portion of the loan proceeds directly to Van Abel, and Van Abel issued checks directly to the appellants. Appellants, respondents, and Van Abel all were familiar with this process.

In December 1988, near the completion of the project, appellants submitted their bills to Van Abel. The subcontractors’ uncompensated work totaled approximately $50,000. Van Abel submitted his final draw request to Home on December 21, 1988. The note with Home was due in ten days, on January 1, 1989. A dispute arose between Van Abel and Home. First, Van Abel had failed to provide the required insurance on the project and property. Failure to provide insurance constituted a breach of the agreement. Second, the final draw request was several thousand dollars in excess of the remaining loan funds. Third, the final draw request did not include any provision for amounts owing to Home for lumber supplied on the project. For these reasons, Home refused to grant the draw request. Van Abel, in turn, failed to pay the appellants.

In 1989, Van Abel defaulted on his note with Home. Home foreclosed on the mortgage and resold the house at a $50,000 loss. Appellants filed for mechanics’ liens but failed to enforce them. Instead, appellants voluntarily relinquished their legal remedies based on the mechanics’ lien statutes and entered into an agreement with Van Abel whereby they would collaborate in this lawsuit. Van Abel signed an agreement purporting to assign all of his contract rights against Home to the appellants. This agreement contradicted the contract that Van Abel had signed with Home. Appellants subsequently brought this suit against Home claiming unjust enrichment.

*140 Appellants were given an opportunity to present all of their evidence before a jury. 1 At trial, Van Abel testified that he had two lines of credit totaling $45,000 available in December 1988 for any purpose. After appellants had presented their evidence, respondents were granted a directed verdict.

ISSUE

In an action for unjust enrichment, did the trial court err in directing a verdict in favor of respondents, where the appellants failed to seek their statutory remedy under mechanics’ lien statutes.

ANALYSIS

We must make an independent judgment about the appropriateness of the directed verdict, and must accept as true all evidence favorable to the appellants and all reasonable inferences that can be drawn from the evidence. Chemlease Worldwide, Inc. v. Brace, Inc., 338 N.W.2d 428, 432 (Minn.1983) (citing Walton v. Jones, 286 N.W.2d 710, 714 (Minn.1979)).

To establish an unjust enrichment claim it must be shown that a party has knowingly received something of value, not being entitled to the benefit, and under circumstances that would make it unjust to permit its retention. In re Stevenson Assocs., Inc., 777 F.2d 415, 421 (8th Cir.1985); Ylijarvi v. Brockphaler, 213 Minn. 385, 393, 7 N.W.2d 314, 319 (1942). The right of recovery for unjust enrichment is equitable. Lundstrom Constr. Co. v. Dygert, 254 Minn. 224, 231, 94 N.W.2d 527, 533 (1959); see also Hommerding v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
493 N.W.2d 137, 1992 Minn. App. LEXIS 1173, 1992 WL 358275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southtown-plumbing-inc-v-har-ned-lumber-co-minnctapp-1992.