Steffl v. Roediger

406 N.W.2d 535
CourtCourt of Appeals of Minnesota
DecidedMay 19, 1987
DocketC7-86-2230
StatusPublished

This text of 406 N.W.2d 535 (Steffl v. Roediger) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steffl v. Roediger, 406 N.W.2d 535 (Mich. Ct. App. 1987).

Opinion

OPINION

HUSPENI, Judge.

Paul and Phyllis Roediger appeal from a judgment enforcing and foreclosing a mechanic’s lien in favor of Michael Steffi. The Roedigers argue that the trial court erred in entering judgment for Steffi because he had not substantially performed the contract and in enforcing a mechanic’s lien because the statutory notice requirements for creating such a lien had not been met. We affirm in part, reverse in part and remand.

FACTS

Paul Roediger and Michael Steffi met on August 14, 1985, to discuss drilling a well on the Roedigers’ property to service a planned minnow hatchery operation. Roe-diger showed Steffi the location of an existing 60 foot deep well which, although not tested, Roediger believed provided water with a relatively low iron content. Two other deeper wells on the property produced water with high iron levels. He explained to Steffi that water with a high iron content is not suitable for hatchery use. Roediger wanted a well drilled in the same location as the existing well with a low iron level, and he wanted it drilled to the depth of 60 feet in order to tap the same aquifer as the existing well of that depth. He also wanted five-inch casing used in order to increase the pumping capacity beyond that possible with the two-inch casing used in the existing 60 foot well.

*537 Steffi, an experienced well driller, explained that state law prohibited drilling into the existing well pit. A nearby location was selected by the two men, although there is some disagreement about the precise drilling spot chosen.

Steffi filled out a form labeled “Job Invoice” and gave it to Roediger. The form contained Roediger’s name and address and the following information:

Quant. Description of material used Price Amount
60' 5' drilling & casing 14.50/ft. 870.00
5' 5' stainless steel screen 60.00/ft. 300.00
Screen fitting 70.00
Chlorination & water test 40.00
1280.00

On the morning of August 15, Steffi and his brother Thomas set up the drilling rig. Roediger states that he was unaware the rig was on his property until he came out of his house after the rig had been set up. Steffi says he called Roediger before moving the rig to the site. Roediger did not speak to either of the Steffis upon seeing the rig located on his property. When drilling reached 13 to 14 feet, a rock layer interrupted the drilling. Roediger then spoke briefly to Michael Steffi but did not comment on the location of the well.

The Roedigers left to do some shopping. During their absence drilling reached 60 to 65 feet. Steffi then went to the Roediger house to tell them of the depth reached without finding water. Unable to talk to the Roedigers, Steffi decided to keep drilling. When Roediger returned to the drilling site a few hours later, Steffi said they had reached water at a depth of 106 feet. Roediger did not complain but stated he hoped they had found good water, meaning water with a low iron content.

Roediger had the water tested and found it contained 5.7 parts per million of iron. The two wells on the property which produced water with an unusable iron content tested at 2.7 and 3.3 parts per million of iron. Roediger refused to pay the $1,947 billed for the 106 foot deep well and has not used water from the well. While the water is safe for human consumption, a filtration system costing over $4,000 would be needed to make the water usable for minnow hatchery purposes according to Roediger.

Steffi commenced this action to enforce and foreclose a mechanic’s lien, and Roedi-ger counterclaimed for breach of contract damages. The trial court awarded Steffi judgment in the amount of $1,947, determined that a mechanic’s lien had been created and ordered foreclosure.

ISSUES

1. Did the trial court err in awarding judgment because Steffi had not substantially performed the contract?

2. Was an independent contractor involved, requiring notice under Minn.Stat. § 514.011 (1984) in order to create a mechanic’s lien?

ANALYSIS

I.

The duty under a contract is full and substantial performance. Ylijarvi v. Brockphaler, 213 Minn. 385, 389-90, 7 N.W.2d 314, 318 (1942). In well drilling contracts, this duty is satisfied by substantial performance. Id.

[Substantial performance means performance of all the essentials necessary to the full accomplishment of the purposes for which the thing contracted for has been constructed, except for some slight and unintentional defects which can be readily remedied or for which an allowance covering the cost of remedying the same can be made from the contract price. Deviations or lack of performance, which are either intentional- or so material that the owner does not get substantially that for which he bargained are not permissible.

Id. at 390, 7 N.W.2d at 318.

The Roedigers argue that Steffi has not substantially performed the contract, which they contend required drilling a well with five inch casing at the site of an existing well, and drilling to the depth of 60 feet in an attempt to tap an aquifer of low iron water for the purpose of providing water suitable for a minnow hatchery. There is no issue regarding the size of the casing *538 because five inch casing was used. Regarding location of the well, Steffi told Roediger that the well could not be drilled into the existing well pit and Roediger agreed that an alternate site could be used. Further, Roediger saw where the drilling rig was set up before drilling began and did not protest the location. As a result, Roediger either contracted for a well to be drilled at the site used or, by his failure to complain, agreed to modify the contract. Consequently, there is no issue regarding location of the well.

There is an issue regarding the contract element relating to depth of the well. Was there a contract to drill to a specific depth in order to tap an aquifer Roediger believed contained water of a specific quality, or did the contract merely specify the per foot cost of drilling a well? The trial court made several findings regarding the contractual obligations of the parties:

The parties entered into a written contract with themselves on August 14, 1985, providing for the drilling of a 5 inch casing well, at 60 feet for the agreed price of $1,280.00, with the work to be performed within two weeks or earlier if [Steffi] became available. The [Roedigers] discussed the reasons for the drilling [of] the well with [Steffi] prior to entering into the contract. The [Roedi-gers] requested that the well be drilled to approximately 60 foot level because the existing well had water which they felt suitable for their business. * * * The parties has [sic] no discussion as to what would happen if they did not hit water at 60 feet or if the well had to be drilled at a different depth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enviro-Fab, Inc. v. Blandin Paper Co.
349 N.W.2d 842 (Court of Appeals of Minnesota, 1984)
ICC Leasing Corp. v. Midwestern MacHinery Co.
257 N.W.2d 551 (Supreme Court of Minnesota, 1977)
Ylijarvi v. Brockphaler
7 N.W.2d 314 (Supreme Court of Minnesota, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
406 N.W.2d 535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steffl-v-roediger-minnctapp-1987.