Enviro-Fab, Inc. v. Blandin Paper Co.

349 N.W.2d 842, 1984 Minn. App. LEXIS 3152
CourtCourt of Appeals of Minnesota
DecidedMay 22, 1984
DocketC8-83-1332
StatusPublished
Cited by9 cases

This text of 349 N.W.2d 842 (Enviro-Fab, Inc. v. Blandin Paper Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enviro-Fab, Inc. v. Blandin Paper Co., 349 N.W.2d 842, 1984 Minn. App. LEXIS 3152 (Mich. Ct. App. 1984).

Opinion

OPINION

RANDALL, Judge.

This appeal arises from a mechanic’s lien action. Appellant property owner appeals from a judgment, an amended judgment, and an order denying its motion for a new trial. The trial court allowed the subcon *845 tractor to foreclose on its lien claim, then denied property owner’s motion for a new trial. The appellant contends (1) the record does not support the trial court’s findings that the lien statement was timely filed and the lien foreclosure action was timely commenced; (2) the trial court improperly denied the contractor’s setoff claim; (3) the trial court’s findings about the reasonable value of the services for a clarifier are not supported by the evidence; (4) the trial court abused its discretion in awarding attorney’s fees to the prevailing lien claimant; and (5) the trial court improperly denied appellant’s request to post a surety bond in lieu of cash to release the lien and serve as a supersedeas bond for appeal purposes. We affirm on all issues.

FACTS

Blandin Paper Company sought bids for the construction of a fuel conversion and cogeneration facility at its Grand Rapids, Minnesota, plant. Azco, Inc., was interested in being the general contractor. Azco contacted Tom Bliznik, sales manager for Enviro-Fab, Inc. (EFI) regarding a subcontract for a fly ash silo, a required pollution control device for Blandin’s new facility. Bliznik gave a tentative telephone quote of $46,500 and also discussed the fabrication of miscellaneous shop tanks with Azco.

Following Azco’s successful bid of the mechanical contract, at $3,040,383, Azco’s project engineer, George Chapman, advised Bliznik of its award and also discussed EFI’s erection of a clarifier and fabrication of seven shop tanks. Upon receipt of the drawings and specifications, and following extended negotiations, EFI agreed to fabricate the seven tanks for $29,000 and to erect the fly ash silo for $42,000 and the clarifier for $34,000. The drawings were returned to Azco.

EFI delivered the seven tanks to Azco in early 1980 and was paid the $29,000 contract price. EFI completed the erection of the clarifier on time but was not paid. Its last work on the clarifier was on June 24, 1980.

The fly ash silo erection posed problems. The work date was set back to August 18, 1980 because of a union jurisdictional dispute. This delay added to EFI’s costs. There was a further delay in sending EFI the original drawings for comparison with the working drawings. EFI’s examination of the working drawings disclosed substantial changes from the original drawings, necessitating considerably more work. Azco insisted that EFI proceed with the erection and work out the extra charges later. EFI insisted that Azco approve the extra charges before it began work. Following numerous unsuccessful communications between the parties, on September 15, 1980, Azco repudiated and terminated the contract. Azco then hired the L.H. Sowles Company to complete the fly ash silo for about $90,000.

EFI decided to file a mechanic’s lien for the unpaid work on the clarifier. On September 10, 1980, EFI received a request from Azco or Blandin for a gasket needed on one of the fabricated tanks that had already been built. The gasket was delivered on September 16, 1980. EFI filed its mechanic’s lien statement on November 7, 1980, and commenced its action to foreclose on the lien on September 16, 1981.

The trial court concluded EFI’s lien statement was timely filed and its foreclosure action was timely commenced. It awarded EFI $34,578.75 (plus interest) and $11,766.87 attorney’s fees. Both parties, at one point, had agreed on the figure of $34,578.75 as the claim. Azco initially refused to pay, not on the merits of the figure, but based on their alleged right to a setoff claim. In denying Blandin’s motion for a new trial, the trial court amended its judgment by stating the $34,578.75 was a reasonable value for the work EFI performed on the clarifier. The court also ordered that Blandin could not post a surety bond to release the lien and that a cash deposit was required which could also serve as a supersedeas bond for appeal purposes.

*846 ISSUES

1. Does the record support the trial court’s findings that the lien statement was timely filed and the lien foreclosure action was timely commenced?

2. Did the trial court improperly deny Azco’s setoff claim?

3. Is the trial court’s finding that $34,-578.75 was a reasonable value for the clari-fier work supported by the evidence?

4. Did the trial court abuse its discretion in awarding $11,766.87 attorney fees to EFI?

5. Did the trial court improperly deny appellant’s request to post a surety bond in lieu of cash to release the lien and serve as a supersedeas bond for appeal purposes?

ANALYSIS

I

Under our mechanic’s lien law, a lien claimant must file its statement within 90 days after doing the last work or furnishing the last materials. Minn.Stat. § 514.08, Subd. 1 (1982); Lesmeister v. Dilly, 330 N.W.2d 95 (Minn.1983). The mechanic’s lien is to “protect those who furnish material or services for the improvement of another’s property * * Giullaume & Associates, Inc. v. Don-John Co., 336 N.W.2d 262, 263 (Minn.1983). Our statute is strictly construed on whether a mechanic’s lien attaches, but liberally construed after the lien has been created. Dolder v. Griffin, 323 N.W.2d 773, 780 (Minn.1982). The appellant argues that EFI’s furnishing of a gasket for a steel tank on September 16, 1980, cannot be considered the last work since the lien is for the work on the clarifier. The appellant contends that the tank jobs were separate from the clarifier and fly ash silo jobs.

The trial court found the parties intended a single unitary contract of $105,000. Thus, even though the last work on the clarifier was performed on June 24, 1980, the November 7, 1980, filing was timely because it was within 90 days of the September 16, 1980, gasket delivery.

On review, the trial court’s findings will not be disturbed unless clearly erroneous. Rule 52.01, Minn.R.Civ.P.; Duininck Bros. & Gilchrist v. Brandondale Chaska Corip., 311 Minn. 291, 248 N.W.2d 743 (1976). Where the evidence is partly oral and partly written, and where the written evidence does not render the credibility of the oral testimony extremely doubtful, an appellate court should defer to the trial court’s assessment of the evidence. Anda Construction Co. v. First Federal Savings & Loan Association, 349 N.W.2d 275 (Minn.App.1984). See In Re Trust Known as Great Northern Iron Ore Properties, 308 Minn. 221, 225-26, 243 N.W.2d 302, 305-06,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

POURED CONCRETE FOUNDATION v. Andron Inc.
529 N.W.2d 506 (Court of Appeals of Minnesota, 1995)
C. Kowalski, Inc. v. Davis
472 N.W.2d 872 (Court of Appeals of Minnesota, 1991)
Klingelhutz v. Woodsmen Construction, Inc.
455 N.W.2d 98 (Court of Appeals of Minnesota, 1990)
Har-Ned Lumber Co. v. Amagineers, Inc.
436 N.W.2d 811 (Court of Appeals of Minnesota, 1989)
Wingen v. Blue Earth County
415 N.W.2d 394 (Court of Appeals of Minnesota, 1987)
Cox v. First National Bank of Aitkin
415 N.W.2d 385 (Court of Appeals of Minnesota, 1987)
Steffl v. Roediger
406 N.W.2d 535 (Court of Appeals of Minnesota, 1987)
R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.
374 N.W.2d 493 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
349 N.W.2d 842, 1984 Minn. App. LEXIS 3152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enviro-fab-inc-v-blandin-paper-co-minnctapp-1984.