R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.

374 N.W.2d 493, 1985 Minn. App. LEXIS 4510
CourtCourt of Appeals of Minnesota
DecidedSeptember 17, 1985
DocketC2-85-21, C4-85-22, C6-85-23 and C7-85-46
StatusPublished
Cited by6 cases

This text of 374 N.W.2d 493 (R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp., 374 N.W.2d 493, 1985 Minn. App. LEXIS 4510 (Mich. Ct. App. 1985).

Opinion

OPINION

FORSBERG, Judge.

This is a consolidated appeal from judgments in four mechanics lien actions consolidated for trial.

In the Westhampton cases, C2-85-21 and C4-85-22, the trial court found that mechanics liens of the claimants were prior to mortgages held by Rothschild Financial Corporation [Rothschild]. Rothschild contends that the trial court erred in fixing the date of first improvement for purposes of priority, and that in any event the mechanics lien claims were not valid. We affirm.

In the Prairie East actions, C7-85-46 and C6-85-23, Rothschild mortgages were found to precede the liens. The lien claimants contend that the court erred in assigning priority based on a finding that the Rothschild loan advances were obligatory rather than optional. We reverse and remand.

FACTS

Four separate parcels of real estate in two developments are involved in this appeal. All parcels were owned and developed by Windsor Development, which went out of business in October, 1983, and has made no appearance in these actions.

Priority — date of first improvement

Westhampton was a quadraminium, or four-unit condominium development. For Lots 21 and 22 of Westhampton, the parties stipulated that the first visible improvement to the property preceded the filing of the mortgage.

The second Westhampton appeal, C4-85-22, involves Lots 27 and 29. The Westh-ampton subdivision was graded beginning in the summer of 1981. The surveyor testified that he certified the grading of individual sites, including building pads for each “quad” unit, in August of 1981. As part of this certification, he staked the corners of each building pad. Staking of the foundation dimensions, for purposes of excavation, was not done until March 24, 1983, a week following the filing of the Rothschild mortgage.

The trial court found that for Lots 27 and 29, the building pad staking was a visible improvement. Since there was no evidence these stakes had been removed prior to March, 1983, it concluded that the liens had priority over the Rothschild mortgages filed March 17, 1983.

The other subdivision, Prairie East Addition, was a single-family unit development. In the action involving Lot 6, the parties stipulated that no improvements had preceded the filing of the mortgage on June 4, 1982.

In the other Prairie East case, involving Lot 31, the excavator had no records or recollection as to dates of work on individual lots. He testified that he began grading work, including adjustment of previously constructed building pads, in September, 1979. There was no testimony from the surveyor as to when staking was done on Lot 31. The foundation was excavated on December 20, 1982. The first Rothschild mortgage on Lot 31 was filed in December, 1981, the second on December 17, 1982.

The trial court found that the first visible improvement on Lot 31 occurred on December 20,1982, when the foundation was dug.

Priority — optional or obligatory advances

Rothschild began providing construction financing to Windsor from Windsor’s inception in 1974. Windsor provided Rothschild with its plans for the units to be built, and the parties would enter into a mortgage on a specific piece of property. The amount of the mortgage, however, was not immediately paid out. Rather, as Rothschild’s vice-president testified, a “credit line” was *496 established for the amount of all mortgages.

In 1982, Rothschild instituted the “new documentation,” which included a loan agreement. The loan agreement provided as follows:

No. 6. Subject to the following, lender agrees to advance the proceeds of the loan for the purpose above stated in accordance with the approved plans, specifications and sworn construction statement submitted to lender by borrower for the subject property. Lender will make advances periodically at its sole discretion and only upon receipt of written lender’s request for payment form signed by borrower. [Emphasis added].

Although the previous documentation did not include the loan agreement, Rothschild’s vice-president testified that the procedure had been the same.

When Windsor submitted a draw request, Rothschild paid out the amount requested, providing it did not exceed the undisbursed balance in that particular mortgage, and providing there was money left in the overall credit line. Rothschild did not require a certain percentage completion of the construction, nor did it require that the contractors were actually paid from the advances. In fact, Rothschild knew that in some cases subcontractors were not being paid from these funds, which were going to pay operating expenses, or interest owed to Rothschild on other mortgages. Rothschild did not make inspections of the properties, nor require lien waivers from materialmen.

The overall line of credit on Windsor projects reached $2-2 million. Rothschild’s vice-president testified that all of the mortgages in this case were fully disbursed.

Validity of mechanics liens

Rothschild claims that virtually all of the subcontractors furnished last items of labor or materials solely intended to revive their expired lien rights. It argues that the lien claims were invalid.

A Windsor employee in charge of contracting the work out testified that towards the end of Windsor’s operations, he talked to all the subcontractors about Windsor’s financial condition. He admitted that he

probably told each and every one of them that the end was coming and that they should protect themselves * * * *.

He admitted to having given out field work orders at the request of subcontractors so they could protect their lien rights. He testified that this was work which had to be done at some point, but not necessarily at the time that he ordered it.

ISSUES

1. Did the trial court err in determining the dates of first improvement on the individual lots?

2. Did the court err in determining that the loan advances were obligatory rather than optional on the part of the mortgagee?

3. Was there error in finding the mechanics liens valid where the last items of work furnished were nominal in amount?

4. Did the trial court err in determining the validity of individual lien claims?

ANALYSIS

1. Priority — date of first improvement

The priority statute provides, in part, as follows:

As against a bona fide purchaser, mortgagee, or encumbrancer without notice, no lien shall attach prior to the actual and visible beginning of the improvement on the ground, * * * *. Engineering or land surveying services with respect to real estate shall not constitute the actual and visible beginning of the improvement on the ground referred to in this section, except when such engineering or land surveying services include a visible staking of the premises.

Minn.Stat. § 514.05 (1984). The date of first improvement is an issue as to Lots 27 and 29, Westhampton, and Lot 31 of Prairie East.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

POURED CONCRETE FOUNDATION v. Andron Inc.
529 N.W.2d 506 (Court of Appeals of Minnesota, 1995)
Thompson Plumbing Co. v. McGlynn Companies
486 N.W.2d 781 (Court of Appeals of Minnesota, 1992)
R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.
383 N.W.2d 362 (Court of Appeals of Minnesota, 1986)
RB Thompson, Jr. Lumber v. Windsor Dev.
383 N.W.2d 357 (Court of Appeals of Minnesota, 1986)
Richard Knutson, Inc. v. Westchester, Inc.
374 N.W.2d 485 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
374 N.W.2d 493, 1985 Minn. App. LEXIS 4510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rb-thompson-jr-lumber-co-v-windsor-development-corp-minnctapp-1985.