Rochester's Suburban Lumber Company v. Slocumb

163 N.W.2d 303, 282 Minn. 124, 1968 Minn. LEXIS 937
CourtSupreme Court of Minnesota
DecidedDecember 6, 1968
Docket41163
StatusPublished
Cited by8 cases

This text of 163 N.W.2d 303 (Rochester's Suburban Lumber Company v. Slocumb) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rochester's Suburban Lumber Company v. Slocumb, 163 N.W.2d 303, 282 Minn. 124, 1968 Minn. LEXIS 937 (Mich. 1968).

Opinion

Nelson, Justice.

This is an appeal from a judgment for defendants in a mechanics lien foreclosure action. In 1964 defendants Charles H. Slocumb and Mary C. Slocumb engaged the services of an architect to design a house. They selected building contractor Thornton G. Egner of Rochester, Minnesota, then doing business as Four Star Builders, to build the house.

Plaintiff, Rochester Suburban Lumber Company, was at the time engaged in retailing lumber and building materials. The contractor, Egner, began ordering lumber supplies from plaintiff on October 14, 1964. The record indicates that specifications were not shown to the plaintiff and that the material was from time to time ordered on a piece-by-piece basis. A running account was kept and it appears that the account was very active to January 14, 1965. Some goods were returned on February 15, 1965.

The owners moved into their home on February 26, 1965. Thereafter, on March 23, 1965, an employee of Egner picked up three large redwood boards at plaintiff lumber company to be used for shelving on the west wall of the recreation room after they had been given the same mill work treatment as had some previously installed shelves on the east wall of the recreation room. It appears that the contractor arranged for the mill work and delivered the finished product to defendants’ garage. They were installed by Joseph J. Weichselbaum, the architect, and Dr. Slocumb personally put on brackets which Mr. Weichselbaum had purchased separately.

The record is not clear as to when the house was completely finished, for various finishing work was performed by Egner’s men up to and after March 23, 1965. The final item furnished by plaintiff was an oak board, costing $2.40, which was sold June 18, 1965, and was used by Egner to cover a wall crack. Plaintiff’s mechanics lien was prepared June 17, 1965, and filed June 18, so it did not include the oak board.

*126 In about May or June 1965, it became apparent to the owners that Egner was not paying bills for supplies. At that time they owed Egner $4,320.77. Defendants later paid this amount to various suppliers, but plaintiff did not receive any payment on its account, which according to the mechanics lien statement amounted to $2,299.64, with interest thereon from May 23,1965.

The trial court held that plaintiff’s lien statement was only effective for the March 23 delivery in the amount of $30.10. Plaintiff appealed, contending the judgment should have been for the full amount claimed under the lien statement it filed June 18, 1965. 1

The court below appears to have accepted defendants’ claim that the original contract called for the supplying of materials for, and construction of, the house, including installation of items such as bookshelves by the contractor, whereas the subsequent transaction on March 23, 1965, was a separate transaction for the supply of lumber materials because Dr. Slocumb intended to install the shelves himself. This reasoning does not substantiate the finding of a separate contract upon the record before us.

There is nothing in the record to indicate affirmatively that either Egner or his employees were unwilling to install the bookshelves pursuant to the contract with the Slocumbs. The installation appears to have been so minor that Dr. Slocumb preferred to do it himself with the assistance of the architect, who saw to it that the proper brackets were provided. It is to be noted that Egner not only procured the lumber from plaintiff but also had the boards planed and finished to match the other bookshelves which were installed under the original contract. It seems most likely that since defendants Slocumb were already dealing with plaintiff through the contract with Egner they decided to obtain the boards under the same arrangements. This inference is further sup *127 ported by the fact that when an additional piece of lumber was required for the house on June 18, 1965, defendants went to plaintiff, who supplied it and charged its cost of $2.40 to the contractor’s account. We conclude that the evidence is insufficient upon the record before us to support the existence of separate contracts, one calling for the supplying of materials for, and the construction of, the house and another contract calling merely for the supplying of material for shelving.

The fact that defendants were occupying the house approximately a month previous to March 23 is not persuasive that the original contract to complete the house was fully consummated. Defendants cite Villaume Box & Lbr. Co. v. Condon, 146 Minn. 156, 178 N. W. 492, but in that case the house was found to be completed upon occupancy, the building contractor in that case having specified that it would be complete upon occupancy and acceptance. There was no evidence of any such agreement here. The record indicates that defendant owners admitted there were several things to be done subsequent to the occupancy.

Plaintiff cites several facts appearing in the record which clearly tend to indicate the house was not completed before March 23, 1965, and that boards were then supplied pursuant to the original contract. First, defendants’ exhibit D, a letter from the architect to the owner dated February 2, 1966, included a list of additions and deletions received from the contractor up to January 6, 1965, which resulted in a cost increase of $1,386, and a second list of additions and deletions received from the contractor to May 11, 1965, resulting in a further cost increase of $775.57. The latter contains 10 changes, including “[a]dd 3 shelves, rec. rm. (including hdwr.) + $46.00” and “[a]dd extra shelves, rec. rm. + $16.00.” The architect testified that these changes were for the shelves on the west and east walls of the recreation room respectively. The next change was “[a]dd shelves and hardware in study -j- $46.92.” Shelving was thus added three different times.

Second, lien statements filed by others who furnished labor or materials in the construction of the house indicated May 26, 1965, and May 21, 1965, as the last dates on which these claimants had furnished labor or material. In both cases the final work was completed 3 months after the house was occupied. These liens were paid in full by defendants.

*128 Third, after a payment by defendants to the contractor on February 16, 1965, the unpaid balance due, as adjusted to May 11, 1965, was $4,320.77. While no part of this was paid directly to the contractor, that amount was paid to various unpaid suppliers after May 11, 1965.

Fourth, Dale Fagerlind, a carpenter for the contractor, testified that he was involved in the finishing of the house, that the house was not fully completed on February 26, 1965, and that finishing work involving lumber was required. Fagerlind visited the house several times after March 23 to make adjustments, purchasing and using whatever materials were required, and he had to install a new mailbox slot. He testified when he delivered the shelves to the house another carpenter was finishing up who might have installed the shelving.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Big Lake Lumber, Inc. v. Security Property Investments, Inc.
836 N.W.2d 359 (Supreme Court of Minnesota, 2013)
Big Lake Lumber, Inc. v. Security Property Investments, Inc.
820 N.W.2d 253 (Court of Appeals of Minnesota, 2012)
POURED CONCRETE FOUNDATION v. Andron Inc.
529 N.W.2d 506 (Court of Appeals of Minnesota, 1995)
Witcher Construction Co. v. Estes II Ltd. Partnership
465 N.W.2d 404 (Court of Appeals of Minnesota, 1991)
R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.
374 N.W.2d 493 (Court of Appeals of Minnesota, 1985)
Enviro-Fab, Inc. v. Blandin Paper Co.
349 N.W.2d 842 (Court of Appeals of Minnesota, 1984)
CHICAGO LUMBER CO. OF OMAHA v. Horner
317 N.W.2d 87 (Nebraska Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
163 N.W.2d 303, 282 Minn. 124, 1968 Minn. LEXIS 937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rochesters-suburban-lumber-company-v-slocumb-minn-1968.