POURED CONCRETE FOUNDATION v. Andron Inc.

529 N.W.2d 506, 1995 WL 156488
CourtCourt of Appeals of Minnesota
DecidedApril 11, 1995
DocketC8-94-1875
StatusPublished
Cited by4 cases

This text of 529 N.W.2d 506 (POURED CONCRETE FOUNDATION v. Andron Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
POURED CONCRETE FOUNDATION v. Andron Inc., 529 N.W.2d 506, 1995 WL 156488 (Mich. Ct. App. 1995).

Opinion

529 N.W.2d 506 (1995)

POURED CONCRETE FOUNDATION, INC., Plaintiff,
v.
ANDRON, INC., et al., Defendants,
Construction Mortgage Investors, Inc., Respondent,
Dura Supreme, Inc., et al., London Brick, Inc., Appellants.

No. C8-94-1875.

Court of Appeals of Minnesota.

April 11, 1995.
Review Denied May 31, 1995.

*508 James A. Beitz, Hagerty, Johnson, Albrightson & Beitz, P.A., Minneapolis, for respondent.

Vincent J. Fahnlander, Curtis D. Smith, Moss & Barnett, P.A., Minneapolis, MN, for appellants Dura Supreme, Inc.

Reese Chezick, Hastings, for appellant London Brick, Inc.

Considered and decided by PARKER, P.J., NORTON and SCHUMACHER, JJ.

OPINION

NORTON, Judge.

Appellant lien claimants contend the trial court erred in invalidating their mechanic's liens. They argue their work on a home relates back to the date of the original excavation of the lot. We agree and reverse.

FACTS

Defendant Andron, Inc., is a development company comprised solely of Richard Andron, owner, architect, developer. In two transactions that occurred in November 1987 and June 1988, Andron purchased two pieces of real estate in Edina now identified as Lots 1-8, Block 1, Interlachen Bluff, County of Hennepin, State of Minnesota. Andron received financing for this purchase from Shelard National Bank. At the time of purchase, two older homes existed on this land. Andron intended to demolish them and develop the land into new residential properties. Specifically, Andron intended initially to build one house on lot 7 and use it as a model home to sell the remaining seven lots.

The City of Edina granted Andron permission to plat and divide the land into eight residential lots. The agreement between Andron and Edina required Andron to clear, grub, and grade the subdivision to make eight buildable lots, and to create streets, curbs, gutters, and building pads. The development required substantial excavating and grading in order to create buildable lots. Andron hired the engineering firm of Krueger and Associates to create the grading plan for the subdivision.

Once Andron received approval from the City of Edina, he hired Kevitt Excavating to cut in the road, grub and grade the subdivision, and create building pads for each future home. Kevitt had prepared land for 24-36 homes for Andron before this project. Scott Kevitt testified that he and Andron had one contract for the subdivision development work, which occurred in the summer and fall of 1988 and included constructing the building pads on the lots, and a separate contract to dig the basement for the home on lot 7 which began in early 1989.

In the fall of 1988, Andron applied to respondent Construction Mortgage Investors (CMI) for financing to build the home on lot 7. Before approving the loan of over $500,000, Ron Allar of CMI inspected the entire subdivision and, in particular, lot 7. Allar testified that when he viewed the property, the site grading was substantially complete, the lots had been "balanced," and he assumed that the building pads had already been "corrected." CMI closed on the loan with Andron on November 17, 1988 and recorded its mortgage the same day. Allar testified that CMI protected itself from potential lien claimants by purchasing title insurance.

Throughout 1989, the following lien claimants, whose claims are on appeal here, worked on the home on lot 7: The Stephen Donnelly Company did the lathe and stucco work; Woodlake Cement Construction Company provided cement for the pool, deck, and steps; London Brick provided the masonry work and materials; Northwestern Tile and Marble provided ceramic tile and marble for the interior of the home; Dura Supreme, Inc. provided cabinets and vanities; and Creative Lighting, Inc. provided lighting fixtures. Upon completion of the home on lot 7, Andron was owner and occupant. Despite Andron's efforts, the home did not sell.

After CMI foreclosed the mortgage, CMI purchased the home for $617,551.36 at a sheriff's sale on April 16, 1991. Andron, who continued to live in the home during the six *509 month redemption period, failed to redeem the property.

This case is a continuation of that mortgage foreclosure action. A bifurcated court trial began in 1991 to consider first the priority of the liens, and then the validity of the liens. In order to gain priority over CMI, the lien claimants sought to prove that their liens related back to the first visible improvement to lot 7, to wit, the excavation of the site, which occurred before CMI loaned Andron the money and recorded its mortgage. After the close of the lien claimants' case, the court found the excavation work had not been an improvement to lot 7, the excavation was separate and distinct from the lien claimants' work on the house, and CMI's mortgage had priority. Based upon those findings, the court granted CMI's motion for involuntary dismissal.

On appeal, this court reversed and remanded, ruling that the excavation was the first visible sign of improvement to lot 7 under Minn.Stat. § 514.05, subd. 1 (1990). Poured Concrete Foundations, Inc. v. Andron, Inc., 1992 WL 166694 (Minn.App.1992), pet. for rev. denied (Minn. Sept. 30, 1992) (Poured Concrete I). The court also noted, "Kevitt's work was admittedly noticed by CMI in its pre-loan inspection and many of its aspects pertained only to construction of the house on lot 7." Id., slip op. at 5.

On remand, CMI moved to complete the trial on the priority issue. The trial court denied this motion without explanation. When CMI appealed that decision, this court reversed again, holding that CMI retained its right to present evidence on the priority issue now that the initial involuntary dismissal had been reversed. See Poured Concrete Foundations, Inc. v. Andron, Inc., 507 N.W.2d 888, 891-92 (Minn.App.1993) (trial court dismissed case before CMI had opportunity to present evidence), pet. for rev. denied (Minn. Jan. 27, 1994) (Poured Concrete II).

During the remainder of the bifurcated trial, CMI presented evidence regarding the separate and distinct issue, and then all parties presented evidence regarding the amount and validity of their mechanic's liens. The trial court ruled in favor of CMI, finding that the lien claimants' work on lot 7 was separate and distinct from the excavation work on the lot, that CMI's mortgage had priority to the mechanic's liens, and that London Brick's lien was invalid because it had performed its last item of work for the sole purpose of extending the time to file its mechanic's lien. The court later denied the lien claimants' motion for amended findings or a new trial.

ISSUES

1. Did the trial court abuse it discretion when it found the subdivision improvements separate and distinct from the home improvements so as to prevent appellants from relating their liens back to the initial date of excavation on the land?

2. Does the record support the trial court's finding that London Brick attempted to extend its lien rights when it washed the brick on the house in 1991?

ANALYSIS

1. Separate and distinct improvements

Our first task is to determine our scope of review. Appellants claim this court has already "determined as a matter of law" that the excavation and construction of the building pad "was part of a continuous project to construct a house" on lot 7. Consequently, because this case is now on its third appeal, appellants contend that prior "ruling" is now law of the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage of Anderson v. Anderson
897 N.W.2d 828 (Court of Appeals of Minnesota, 2017)
Big Lake Lumber, Inc. v. Security Property Investments, Inc.
836 N.W.2d 359 (Supreme Court of Minnesota, 2013)
Big Lake Lumber, Inc. v. Security Property Investments, Inc.
820 N.W.2d 253 (Court of Appeals of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
529 N.W.2d 506, 1995 WL 156488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/poured-concrete-foundation-v-andron-inc-minnctapp-1995.