Kirkwold Construction Co. v. M.G.A. Construction, Inc.

498 N.W.2d 465, 1993 Minn. App. LEXIS 346
CourtCourt of Appeals of Minnesota
DecidedApril 6, 1993
DocketNos. C1-92-1227, C5-92-1764
StatusPublished
Cited by2 cases

This text of 498 N.W.2d 465 (Kirkwold Construction Co. v. M.G.A. Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirkwold Construction Co. v. M.G.A. Construction, Inc., 498 N.W.2d 465, 1993 Minn. App. LEXIS 346 (Mich. Ct. App. 1993).

Opinion

OPINION

KLAPHAKE, Judge.

Miller and Schroeder Investments Corporation and Holiday Stationstores, Inc. appeal from an amended judgment and order denying post-trial motions, contending the trial court erred in holding mechanics’ lien claims superior to their interests and further challenge the awards of attorney fees. Turner Excavating Company appeals from an amended judgment, contending the trial court erred in holding Turner did not establish a valid lien claim against Holiday’s property. We affirm in part and reverse in part.

FACTS

In 1989, Duckwood Crossings, Inc. (Duckwood) began developing a retail project on three lots in Dakota County. Duck-wood retained respondents Minnesota Valley Surveyors (Minnesota Valley) and Ul-teig Engineers (Ulteig) to perform surveying and engineering work on the lots. Minnesota Valley began work on February 20, 1989 and Ulteig began work on April 10, 1989. Duckwood, however, did not make full payment.

On October 30, 1989, Duckwood sold one lot (the Holiday lot) to appellant Holiday Stationstores, Inc. (Holiday), mortgaged the remaining lots (the Miller lots) with appellant Miller and Schroeder Investments Corporation (Miller), and recorded the transactions. Although both Holiday and Miller knew of Minnesota Valley and Ul-teig’s work, neither knew the two companies had not been paid. At the closing, Duckwood provided an affidavit stating no [468]*468unpaid labor or material had been provided to the property.

On November 2,1989, respondent Turner Excavating Company (Turner) began the first visible improvement on the ground. Duckwood instructed Turner to give priority to the preparation of the Holiday lot. During late 1989, Turner stripped top soil from the Holiday lot and stockpiled the dirt on the property line between the Holiday lot and the adjoining Miller lot.

After Duckwood failed to meet leasing obligations, Miller foreclosed on its mortgages. In the meantime, Minnesota Valley and Ulteig filed mechanics’ liens. Turner also filed a mechanics’ lien, along with respondents Kirkwold Construction Company (Kirkwold), Cherrier Land Surveyors, Inc. (Cherrier) and Specialty Systems, Inc. (collectively “subsequent lienholders”), three other companies who had contributed labor or materials after November 2, 1989.

In two separate actions, Minnesota Valley and Kirkwood sued to establish lien priority. These actions were later consolidated and the parties, except Turner, litigated the priority issue before the court in the first phase of a bifurcated trial. The trial court concluded the lien claimants’ interests took priority over the Miller mortgages, allowing the subsequent lienholders to tack onto the date of Ulteig and Minnesota Valley’s first contribution to the improvement. The trial court also concluded that the Ulteig and Minnesota Valley liens were superior to Holiday’s ownership interest, but refused to allow the Cherrier claim to take priority over Holiday because Cher-rier failed to serve the required statutory notice. See Minn.Stat. § 514.08 (1990). During the second phase, the trial court determined Turner’s lien to be superior to the Miller mortgages by tacking onto Ul-teig and Minnesota Valley’s first contribution date. The court also found Turner did not establish a valid lien claim to the Holiday lot. Finally, the trial court awarded damages, attorney fees and costs to all of the lien claimants. Holiday and Miller appeal from the amended judgment and order denying their post-trial motions, Turner appeals from the amended judgment.

ISSUES

1. Did the trial court err in ruling the liens of Ulteig and Minnesota Valley had priority over the recorded interests of Holiday and Miller?

2. Did the trial court err in allowing all subsequent lienholders to tack onto Ulteig and Minnesota Valley’s lien, thereby giving them priority over the interests of Holiday and Miller?

3. Did the trial court err in denying Turner a lien against the Holiday lot?

4. Did the trial court abuse its discretion in awarding attorney fees?

ANALYSIS

The issue of lien priority involves interpretation of the mechanics’ lien statutes and presents a question of law reviewable by this court. See Hibbing Educ. Ass’n v. Public Employment Relations Bd., 369 N.W.2d 527, 529 (Minn.1985). We need not defer to the trial court when reviewing its conclusions of law. Frost-Benco Elec. Ass’n v. Minnesota Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984). Should application of the law depend on findings of fact, however, such findings will not be overturned on appeal unless clearly erroneous. Citizens State Bank of Hayfield v. Leth, 450 N.W.2d 923, 925 (Minn.App.1990).

I.

The parties do not dispute that Ul-teig and Minnesota Valley are entitled to assert mechanics’ liens against the Holiday and Miller properties. At issue is the question of priority among the interests. Holiday and Miller contend their interests are superior to those of Ulteig and Minnesota Valley because Holiday and Miller recorded their interests before any actual and visible improvement on the ground. We disagree.

Minn.Stat. § 514.05, subd. 1 (1990) determines the priority between lienholders and others who hold an interest in the property:

All liens, as against the owner of land, shall attach and take effect from the time the first item of material or labor is [469]*469furnished upon the premises for the beginning of the improvement, and shall be preferred to any mortgage or other encumbrance not then of record, unless the lienholder had actual notice thereof. As against a bona fide purchaser, mortgagee, or encumbrancer without actual or record notice, no lien shall attach prior to the actual and visible beginning of the improvement on the ground.

(Emphasis added.)

Here, both Holiday and Miller had actual notice of the work performed by Ulteig and Minnesota Valley. Under the plain language of the statute, Holiday and Miller are not bona fide purchasers or mortgagees without actual or record notice and therefore fall outside of the actual and visible beginning provision. See Nadeau v. Austin Mut. Ins. Co., 350 N.W.2d 368, 373 (Minn.1984) (statute construed according to plain and ordinary meaning). Rather, Holiday and Miller stand in the same position as an owner for priority purposes. See Reuben E. Johnson Co. v. Phelps, 279 Minn. 107, 113, 156 N.W.2d 247, 251 (1968) (where mortgagee has notice that labor or materials for improvement have been furnished, mortgagee stands in same position as owner).

As against an owner, a mechanics’ lien attaches at the time the first material or labor for the improvement is furnished upon the property. Minn.Stat. § 514.05, subd. 1. Therefore, we agree with the trial court that the liens of Ulteig and Minnesota Valley attached when they first began working on the property and have priority over the interests of both Miller and Holiday.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

POURED CONCRETE FOUNDATION v. Andron Inc.
529 N.W.2d 506 (Court of Appeals of Minnesota, 1995)
KIRKWOLD CONST. v. MGA Const., Inc.
498 N.W.2d 465 (Court of Appeals of Minnesota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
498 N.W.2d 465, 1993 Minn. App. LEXIS 346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirkwold-construction-co-v-mga-construction-inc-minnctapp-1993.