C. Kowalski, Inc. v. Davis

472 N.W.2d 872, 1991 Minn. App. LEXIS 676, 1991 WL 115529
CourtCourt of Appeals of Minnesota
DecidedJuly 2, 1991
DocketC2-90-2639
StatusPublished
Cited by7 cases

This text of 472 N.W.2d 872 (C. Kowalski, Inc. v. Davis) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. Kowalski, Inc. v. Davis, 472 N.W.2d 872, 1991 Minn. App. LEXIS 676, 1991 WL 115529 (Mich. Ct. App. 1991).

Opinion

OPINION

EDWARD D. MULALLY, Judge.

Appellants challenge the trial court’s order finding that respondent had a validly perfected mechanics’ lien, ordering its foreclosure, and awarding attorney fees. We affirm.

FACTS

Respondent C. Kowalski, Inc., a carpentry firm owned by Clarion Kowalski, brought this action to foreclose a mechanics’ lien arising out of the construction of a house for appellants Michael W. and Margaret McPhail Davis in Minnetrista, Minnesota.

Beginning in the summer of 1985, the Davises hired appellant D.F. Florek Corporation (the general contractor) to build a single-family house for the couple. Paul Jaunich designed the house and participated in its construction.

Jaunich testified that in designing the house, he was asked to design an office on the second floor to accommodate Margaret McPhail Davis’ court reporting business. The house plans contain a room entitled “office” that is 24' x 16'6" in dimension. Kowalski testified that he was aware that the office was designed to be used in Margaret McPhail Davis’ business. The Davis-es maintain that the “office” was not ultimately used as an office because of the inconvenience of operating the business from the house.

The parties dispute the square footage of the house. Kowalski testified that according to his measurements the house was 5,200 square feet in area. Jaunich, in contrast, testified that the structure had an area of only 3,800 square feet. On cross- *874 examination, however, Jaunich conceded that he did not measure the structure and therefore did not know the actual square footage of the house. In her deposition, Margaret McPhail Davis testified that based on Michael Davis’ measurements the house was 5,050 square feet.

In order to prepare his bid for the house, D.F. Florek solicited bids for carpentry work on the project. All bidders on the project based their bids on an eight page blueprint plan of the proposed house. Respondent, through its owner, submitted an oral bid of $23,771. The bid, subsequently reduced to writing, did not contain any breakdown of the specific work that would be performed under the bid.

During the course of construction, the Davises decided to delete a gazebo originally planned for the center of the structure and replaced it with a tower on the end of the house. Kowalski did not do any siding work on the house.

After receiving one payment of $17,262 for part of the work, on March 18, 1986 Kowalski submitted a billing statement to Florek requesting final payment of $13,-718. The sum reflected extra charges of $7,209 but no deletion for the gazebo or for wood siding. Ultimately, Kowalski submitted a revised bill reflecting a $2,000 deletion for the gazebo with a total sum due of $11,718.

Appellants principally dispute two aspects of Kowalski’s bill: (1) a deduction of $2,000 rather than $4,500 for the deleted gazebo; and (2) no deletion for siding after the exterior was changed to brick.

Florek and Kowalski gave differing versions of the appropriate deduction for the gazebo that was deleted from the original plans. Kowalski maintains that Florek suggested a $2,000 deletion for the gazebo and that Kowalski assented. Conversely, Florek denies agreeing to a $2,000 deduction and contends that a $4,500 reduction from the original bid price was appropriate.

Kowalski testified that he believed at the time of bidding that the siding work was not to be included in his bid. Gary Lebov-sky, one of Kowalski’s employees on the project, testified that Kowalski believed that the siding was not included. Lebov-sky remembers having seen the house plan in the summer of 1985 and noting that the plan appeared to call for lap siding. He testified in part:

I asked what kind of siding it would be because if it was the same siding we were putting on, it’s a little, narrow lap siding and it takes a long time to do, and this one had a considerable amount of siding, so I asked him what the siding was and he said there was no siding, it was going to be an all-brick exterior so we wouldn’t have to worry about siding.

(Emphasis added.)

In contrast, Dale Florek testified that the plans submitted to the potential subcontractors called for wood siding. In July of 1985, when Florek asked for the Kowalski bid in writing, he stated:

I need this bid in writing because we will have to sit down at a later date to figure out where we were because the owner is going to be making some chang[es] and they are thinking [of] doing some brick work.

Florek maintains that he based his bid to Davis for the whole project on using wood siding.

Jaunich, the project designer, testified that the exterior plan was not changed to brick until a meeting with Florek and the Davises on September 7,1985, after Kowal-ski submitted his bid.

Following a bench trial, the court issued an order finding a validly perfected mechanics’ lien in the amount of $11,717.55 plus interest, costs and attorney fees. After the dismissal of the initial appeal in this matter because the trial court had not awarded attorney fees, the trial court issued an amended order for judgment awarding attorney fees of $14,195, interest of $3,781.19, costs and disbursements of $723.45 in addition to the lien recovery of $11,717.55 for a total recovery of $30,-417.19. The district court subsequently entered judgment in the amount of $30,525.97 against each of the appellants.

*875 ISSUES

1. Did the trial court err by ruling that respondent need not give pre-lien notice?

2. Did the trial court properly calculate the amount of the lien?

3. Did the trial court award excessive attorney fees?

ANALYSIS

I.

In a mechanics’ lien proceeding, the appellate court must sustain the trial court’s findings if they are supported by evidence in the record. Heyn v. Braun, 239 Minn. 496, 501, 59 N.W.2d 326, 329-30 (1953). When reviewing a decision reached by a court sitting without a jury, this court’s scope of review is limited to determining “whether the trial court’s findings are clearly erroneous, either without substantial evidentiary support or based on an erroneous conclusion of law.” Warthan v. Midwest Consol. Ins. Agencies, 450 N.W.2d 145, 147 (Minn.App.1990) (footnote omitted). “Mechanics’ lien laws are strictly construed as to the question whether a lien attaches, but are construed liberally after the lien has been created.” Dolder v. Griffin, 323 N.W.2d 773, 780 (Minn.1982) (quoting Annot., 76 A.L.R.3d 605, 618 (1977)).

Generally, a lien claimant must give pre-lien notice to a homeowner before a court will enforce the lien. Minn.Stat. § 514.011, subd. 2 (1984). Minn.Stat. § 514.011, subd. 4c(a), however, carves out an exception:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ryan Contracting Company v. O'Neill & Murphy, LLP
868 N.W.2d 473 (Court of Appeals of Minnesota, 2015)
TC/American Monorail, Inc. v. Custom Conveyor Corp.
822 N.W.2d 812 (Court of Appeals of Minnesota, 2012)
Bendiske Concrete & Masonry, Inc. v. Barthel Construction, Inc.
515 N.W.2d 95 (Court of Appeals of Minnesota, 1994)
KIRKWOLD CONST. v. MGA Const., Inc.
498 N.W.2d 465 (Court of Appeals of Minnesota, 1993)
Kirkwold Construction Co. v. M.G.A. Construction, Inc.
498 N.W.2d 465 (Court of Appeals of Minnesota, 1993)
Emison v. J. Paul Sterns Co.
488 N.W.2d 336 (Court of Appeals of Minnesota, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
472 N.W.2d 872, 1991 Minn. App. LEXIS 676, 1991 WL 115529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-kowalski-inc-v-davis-minnctapp-1991.