R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.

383 N.W.2d 362
CourtCourt of Appeals of Minnesota
DecidedMarch 11, 1986
DocketC5-85-1325, C7-85-1374, C8-85-1917, C1-85-1919, C9-85-1957, C8-85-1903, CX-85-1918, C2-85-1945, C4-85-1977 and C6-85-1978
StatusPublished
Cited by9 cases

This text of 383 N.W.2d 362 (R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp., 383 N.W.2d 362 (Mich. Ct. App. 1986).

Opinion

OPINION

WOZNIAK, Judge.

This is a consolidated appeal from judgments in ten mechanic’s lien actions consolidated for trial.

In C4-85-1977, the trial court found that mechanic’s liens of the claimants were pri- or to mortgages held by Rothschild Financial Corporation. Rothschild contends that the trial court erred in fixing the date of first improvement for purposes of priority. We affirm.

In C2-85-1945, the trial court found that mortgages held by Rothschild were prior to mechanic’s liens of the claimants. The claimants contend that the trial court erred in fixing the date of first improvement for purposes of priority. We reverse.

In C2-85-1945, Rothschild mortgages were found to precede the liens. The lien claimants contend that the trial court erred in finding that the loan advances were obligatory rather than optional. We reverse and remand.

In C5-85-1325, C8-85-1917, CX-85-1918, C9-85-1957, C4-85-1977, and C6-85-1978, Rothschild raises various issues in contending that the trial court erred in finding certain mechanic’s liens valid. We affirm.

In C7-85-1374, C8-85-1903, and Cl-85-1919, the trial court found that R.B. Thompson Lumber Company was not entitled to mechanic’s liens. Thompson contends that the trial court erred in finding that Thompson did not deliver materials to the properties within the 120-day period preceding the filing of its liens. We reverse.

In C7-85-1374, the trial court did not award attorney’s fees and costs to Thompson because it found that Thompson was not entitled to its mechanic’s lien. Thompson contends that, if this court finds that Thompson was entitled to a mechanic’s lien, then Thompson is also entitled to attorney’s fees and costs. We remand.

FACTS

While this case does involve different individual lots, the facts are essentially as stated by this court in R.B. Thompson, Jr. Lumber Co. v. Windsor Development Corp., 374 N.W.2d 493 (Minn.Ct.App.1985), pet. for rev. denied (Minn. Nov. 25, 1985).

ISSUES

1. Are the trial court’s findings concerning the dates of first improvement on the individual lots clearly erroneous?

2. Is the trial court’s finding that the loan advances were obligatory clearly erroneous?

3. Are the trial court’s findings that certain liens are valid and certain others are invalid clearly erroneous?

4. Is Thompson entitled to attorney’s fees and costs?

*365 ANALYSIS

I.

1.Priority — date of first improvement.

Rothschild contends that the staking for grading, the rough grading of the whole development, and the compaction of soil for building pads in 1981 were part of the overall project rather than bearing directly on the erection of any building in 1983. Thus,'Rothschild argues that such improvements for the overall subdivision may not be used in determining the “actual and visible beginning of the improvement on the ground” of individual lots and buildings. Rothschild submits that, based upon existing case law, the relevant date for determining priority is either the staking of the building or the beginning of the excavation for the building itself (the beginning of the first work which is directly related to the construction of the building).

In the prior case, we held that the staking of the building pad can constitute the first visible improvement. 374 N.W.2d at 497. That decision is affirmed in the companion ease issued contemporaneously with this ease (J. Sedgwick), 383 N.W.2d 357.

In C4-85-1977, the trial court found that grade staking, construction of the building pad, installation of a water top box, and placement of an elevation stake all took place before Rothschild’s mortgage was recorded. Thus, the trial court properly ruled that the lien claimants had priority over the mortgage.

In C2-85-1945, however, the trial court held that Rothschild had priority over the lien claimants. The trial court acknowledged that the building pad had been constructed, but noted that the excavator could not specifically testify that grading stakes remained visible on that particular lot at the time the mortgage was recorded. The trial court referred to photographs taken seven days after the mortgage was filed which “do not show the presence of any stakes or other visible improvements on the land.” At trial, however, the excavator testified that he cut down the level of this lot three to five feet, and pushed the dirt onto adjoining lots. Such significant grading in addition to the building pad was certainly an improvement which would be visible to anyone conducting a reasonably diligent inspection of the lot. Under the logic expressed in the prior case and the companion case to this case, the trial court was clearly erroneous in finding that there were no visible improvements prior to the recording of Rothschild’s mortgage. Thus, we reverse the trial court and hold that the lien claimants had priority over Rothschild’s mortgage.

2. Priority — obligatory or optional advances.

This precise issue was decided in the prior case, id. at 498, and we again reverse the trial court. Rothschild’s advances were optional and have priority over mechanic’s liens only for the amounts advanced up to the attachment of the liens. We remand for a determination of these amounts.

3. Validity of liens.

Rothschild contends that certain lien claims were invalid because the claimants’ last items of labor were nominal in amount and furnished solely to protect their lien rights. This issue was decided in our prior case, id., and we again affirm the trial court.

Rothschild also contends that certain lien claims were invalid because the last items were furnished pursuant to a separate contract. This argument was rejected in our prior case, id., and we again affirm the trial court.

Rothschild also contends that certain liens were invalid because the lien statements included amounts in excess of the contract prices. This issue was decided in our prior case, id., and we again affirm the trial court.

Finally, Rothschild contends that the trial court erred in finding that certain lien waivers executed by Thompson were fraudulently induced and should be rescinded. However, the record contains suffi *366 cient evidence to support the trial court’s finding. Rothschild represented that the mortgages given in return for the lien waivers would be second mortgages. That was a representation of existing fact. However, on the day the waivers were executed, there were already two mortgages on each of the lots. In fact, Thompson received a mortgage that was fourth in priority. The trial court is affirmed on this issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Hicks
583 N.W.2d 757 (Court of Appeals of Minnesota, 1998)
Anker v. Little
541 N.W.2d 333 (Court of Appeals of Minnesota, 1995)
Kirkwold Const. v. MGA CONST.
513 N.W.2d 241 (Supreme Court of Minnesota, 1994)
Kirkwold Construction Co. v. M.G.A. Construction, Inc.
513 N.W.2d 241 (Supreme Court of Minnesota, 1994)
Thompson Plumbing Co. v. McGlynn Companies
486 N.W.2d 781 (Court of Appeals of Minnesota, 1992)
RB Thompson, Jr. Lumber v. Windsor Dev.
383 N.W.2d 357 (Court of Appeals of Minnesota, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
383 N.W.2d 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rb-thompson-jr-lumber-co-v-windsor-development-corp-minnctapp-1986.