Buchman Plumbing Co., Inc. v. Regents of the U. of M.

215 N.W.2d 479, 298 Minn. 328, 1974 Minn. LEXIS 1480
CourtSupreme Court of Minnesota
DecidedFebruary 15, 1974
Docket43976
StatusPublished
Cited by53 cases

This text of 215 N.W.2d 479 (Buchman Plumbing Co., Inc. v. Regents of the U. of M.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buchman Plumbing Co., Inc. v. Regents of the U. of M., 215 N.W.2d 479, 298 Minn. 328, 1974 Minn. LEXIS 1480 (Mich. 1974).

Opinion

*330 Edward D. Mulally, Justice. *

This matter arose out of a construction project at the University of Minnesota. It involved the addition of two floors and a penthouse to the V. F. W. Cancer Research Center.

The Regents of the University of Minnesota (University) let four contracts with prime contractors for the purpose of general construction and for elevator, mechanical, and electrical installations. Buchman Plumbing Company, Inc. (Buchman), the plaintiff, was awarded the mechanical contract. Plans and specifications were contained in a booklet that consisted of bidding requirements, general conditions, and special requirements for each of the prime contractors. The project was to commence April 23, 1968, and was to be completed within 200 consecutive days.

The University contracted with James Steele Construction Company (Steele) as the general contractor for the project. Steele’s contract was substantially identical with the contract between the University and Buchman.

After receipt of notice to proceed, Buchman moved a construction trailer onto the site but did not perform any work on the project until mid-July 1968. Buchman admitted there was some work it could have completed before July but decided that to do so would be uneconomical.

On July 1, 1968, a progress meeting of all contractors was held, and the topic of project delay was discussed. Mr. Walter Buchman, president of Buchman, asserted that at this meeting and in August, September, October, November, and December of 1968, he orally protested to Steele and to University officials about the project’s delay. John Reuer, an officer of a Buchman subcontractor, claimed he also made numerous protests. Buch-man claims that Steele was responsible for the delay. There were no written protests of delay filed with either Steele or the University.

*331 Final inspection of all the work was made on March 25, 1969. Buchman then instituted this breach-of-contract action on the theory that it had been damaged by reason of its inability to complete its part of the work on the project within the 200-day period required by the contract because of delay caused by defendant Steele and acquiesced in by defendant University.

The University asserted a cross-claim against Steele for indemnity and impleaded Steele’s surety, United Pacific Insurance Company (Pacific). Steele then cross-claimed against the University for indemnity. On November 18, 1970, the University, Pacific, and Steele moved for summary judgment, arguing that Buchman did not have valid cause of action. The motion was denied.

On July 20, 1971, trial was commenced. At the close of Buchman’s opening statement, the University and Steele moved for dismissal on the grounds that Buchman had as a matter of law failed to state a valid cause of action. On August 30, the trial court granted Steele’s motion for dismissal, denied the University’s motion, and provided that any third-party liability would await the results at trial. Buchman appealed from the Steele dismissal, and this court dismissed that appeal as premature. Buchman Plumbing Co. Inc. v. The Regents of University of Minnesota, 293 Minn. 437, 196 N. W. 2d 629 (1972).

Trial was resumed on July 10, 1972. It was agreed that the case should be divided into three parts: Liability, if any, of the University to Buchman; damages, if any, sustained by Buch-man; and liability, if any, of Steele and Pacific to the University. Following the presentation of Buchman’s evidence on the issue of liability of the University to Buchman, the University and Steele moved to dismiss. The trial court granted this motion and judgment was entered from which Buchman appeals.

The first issue to be considered is whether as a matter of *332 law Buchman has failed to state a cause of action against Steele upon which relief may be granted. 1

Buchman asserts that even though it and Steele signed separate contracts with the University, it was a creditor beneficiary of the Steele-University contract. For Buchman to maintain an action against Steele on a creditor-beneficiary claim, Buchman must establish a duty owed to it by the University, which duty was to be performed by Steele. Restatement, Contracts, § 133. Buchman claims that the University owed it the duty to create conditions which would allow it to complete its work within 200 days. Buchman finds this duty in Article VIII of the Buchman-University contract, which reads as follows:

“The Owner [University] agrees to provide all labor and material essential to the conduct of this work not included in this contract in such manner as not to delay its progress, and in the event of failure so to do, thereby causing loss to the Contractor [Buchman], agrees that it will reimburse the Contractor for such loss; and the Contractor agrees that if he shall delay the progress of the work so as to cause loss for which the Owner shall become liable, then he shall reimburse the Owner for such loss.”

Furthermore, Buchman claims that it was necessary for all contractors to cooperate to attain the end result of a completed addition and that it relied on the time-of-the-essence (200 days) clause to calculate its costs.

Steele contends there is no “intent to benefit” Buchman; that Steele’s alleged promised performance would not be sufficient to discharge the University’s duty to Buchman; that Buchman *333 is at most an “incidental beneficiary”; and that even if Buchman is a creditor beneficiary, it has failed to show breach of the University’s duty.

Buchman also argues it is a subcontractor of Steele. The record indicates the University signed separate contracts with each of the contractors.

“* * * [A] subcontractor has been defined as one to whom the principal contractor sublets a portion or all of the contract itself, or as one who performs or contracts to perform part of the principal contractor’s contract.” 17 Am. Jur. 2d, Contractors’ Bonds, § 79, p. 254.

Buchman is a contractor, not a subcontractor of Steele.

It is the prevailing rule in Minnesota and other jurisdictions in the United States that a third party may sue on a contract made for his direct benefit. Hedberg & Sons Co. v. Galvin, 274 Minn. 422, 144 N. W. 2d 263 (1966); Northern Nat. Bank v. Northern Minn. Nat. Bank, 244 Minn. 202, 70 N. W. 2d 118 (1955); La Mourea v. Rhude, 209 Minn. 53, 295 N. W. 304 (1940); 17A C. J. S., Contracts, § 519(3). In La Mourea v. Rhude, supra, this court adopted the definition of third-party beneficiaries found in Restatement, Contracts, § 133. 2

*334 This court has used two tests to determine the enforceability of contracts by third-party beneficiaries. The primary test used in Minnesota in determining whether a party may sue as a third-party beneficiary is the “intent to benefit” test. Gjovik v. Bemid-ji Local Bus Line, 223 Minn. 522, 27 N. W. 2d 273 (1947); 17A C. J. S., Contracts, § 519 (4) (c) ; 17 Am. Jur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kuchenmeister v. Healthport Techs., LLC
309 F. Supp. 3d 1342 (N.D. Georgia, 2018)
Contractors Edge, Inc. v. City of Mankato
Court of Appeals of Minnesota, 2016
Hickman v. SAFECO Insurance Co. of America
695 N.W.2d 365 (Supreme Court of Minnesota, 2005)
Dayton Development Co. v. Gilman Financial Services, Inc.
299 F. Supp. 2d 933 (D. Minnesota, 2003)
Mies Equipment, Inc. v. NCI Building Systems, L.P.
167 F. Supp. 2d 1077 (D. Minnesota, 2001)
Grenier v. Air Express International Corp.
132 F. Supp. 2d 1198 (D. Minnesota, 2001)
Sterling Capital Advisors, Inc. v. Herzog
575 N.W.2d 121 (Court of Appeals of Minnesota, 1998)
Servais v. T.J. Management of Minneapolis, Inc.
973 F. Supp. 885 (D. Minnesota, 1997)
614 Co. v. Minneapolis Community Development Agency
547 N.W.2d 400 (Court of Appeals of Minnesota, 1996)
Dynamic Construction Co. v. Barton Malow Co.
543 N.W.2d 31 (Michigan Court of Appeals, 1995)
In Re Hennepin County 1986 Recycling Bond Litigation
540 N.W.2d 494 (Supreme Court of Minnesota, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
215 N.W.2d 479, 298 Minn. 328, 1974 Minn. LEXIS 1480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buchman-plumbing-co-inc-v-regents-of-the-u-of-m-minn-1974.