Contractors Edge, Inc. v. City of Mankato

CourtCourt of Appeals of Minnesota
DecidedJanuary 11, 2016
DocketA14-223
StatusUnpublished

This text of Contractors Edge, Inc. v. City of Mankato (Contractors Edge, Inc. v. City of Mankato) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractors Edge, Inc. v. City of Mankato, (Mich. Ct. App. 2016).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-0223

Contractors Edge, Inc., Appellant,

vs.

City of Mankato, Respondent.

Filed January 11, 2016 Affirmed Reilly, Judge

Blue Earth County District Court File No. 07-CV-10-2311

Stephen F. Buterin, Heley, Duncan & Melander, PLLP, Minneapolis, Minnesota; and

Aaron A. Dean, Moss & Barnett, Minneapolis, Minnesota (for appellant)

James M. Strommen, James J. Thomson, Kennedy & Graven, Chartered, Minneapolis, Minnesota (for respondent)

Considered and decided by Schellhas, Presiding Judge; Rodenberg, Judge; and

Reilly, Judge.

UNPUBLISHED OPINION

REILLY, Judge

Appellant-contractor Contractors Edge, Inc. (CEI) challenges the district court’s

judgment in this breach-of-contract action for extra work performed on a construction

contract. Appellant alleges that the district court erred by concluding that (1) appellant was not entitled to additional compensation for extra work performed, and (2) appellant failed

to comply with the claims process outlined in the contract. Because the district court’s

findings and conclusions are supported by the record and are not clearly erroneous, we

affirm.

FACTS

In July 2009, the City of Mankato (the city) advertised for bids for Eastwood Energy

Industrial Park-Power Drive Extension Project No. 08059 (the project). The project

involved the extension of a city street in the northeast part of Mankato and included

construction of a road, drainage facilities, a water main, a sanitary sewer, storm drains,

grading, landscaping, a berm, and a type of drainage ditch known as a “bio-swale.” The

excavated material would be used for improvements or hauled to a stockpile site within

one-half mile of the project. The contract documents provided that the city would designate

the stockpile sites after awarding the contract. The location of the stockpile site was

important to the cost of the project because it necessitated heavy equipment to move the

excavated material, along with associated fuel and labor costs. The hauling route would

be based on a city-approved “haul route” within the project itself.

Appellant interpreted the one-half mile haul distance to be measured by driving

distance and submitted a bid of approximately $476,000, which was the lowest of the bids

considered. On August 11, 2009, the city and CEI entered into a written contract for the

project. The project was divided into three areas: the construction of Power Drive, the

excavation for the west bio-swale, and the excavation for the east bio-swale. The city

required the work to be completed by October 30, 2009. Jeff Johnson was the engineer for

2 the city. The city designated Michael McCarty as the project engineer and Brian Bentdahl

as the chief inspector. CEI began work on the project in August 2009.

The contract documents for the project included the Engineers Joint Contract

Documents Committee (EJCDC) Standard General Conditions (the general conditions).

Article 10 of the general conditions articulated the change-order process for “Changes in

the Work; Claims.” The parties agreed that if they could not agree “on entitlement to, or

on the amount or extent, if any, of an adjustment in the Contract Price or Contract Times,

or both, that should be allowed as a result of a Work Change Directive, a Claim may be

made therefor as provided in Paragraph 10.05.” Paragraph 10.05(B) provides:

Written notice stating the general nature of each Claim shall be delivered by the claimant to Engineer and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. The responsibility to substantiate a Claim shall rest with the party making the Claim. Notice of the amount or extent of the Claim, with supporting data shall be delivered to the Engineer and the other party to the Contract within 60-days after the start of such event (unless Engineer allows additional time for claimant to submit additional or more accurate data in support of such Claim). A claim for an adjustment in contract price shall be prepared in accordance with the provisions of Paragraph 12.01.B . . . . Each claim shall be accompanied by claimant’s written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event. The opposing party shall submit any response to Engineer and the claimant within 30 days after receipt of claimant’s last submittal.

The engineer had the authority to approve or deny any claim. A denial would be

considered “final and binding” unless the aggrieved party “invoke[s] the dispute resolution

procedure set forth in [the general conditions] within 30 days of such action or denial.”

3 Article 10 concludes: “No Claim for an adjustment in Contract Price or Contract Times

will be valid if not submitted in accordance with this Paragraph 10.05.” CEI acknowledges

that Article 10 of the contract governs the change-order and claims process. During the

course of construction, the parties agreed to six separate change orders, only one of which

is in dispute.

On September 18, 2009, CEI’s president, John Brindley, advised the project

engineer and the city’s chief inspector that CEI would require additional compensation

because CEI would have to haul excess material from the west bio-swale berm at an

increased hauling distance. CEI stated that the haul distance to the newly designated

disposal area was over one-half mile, resulting in higher hauling costs. CEI declined to

finish work on the west bio-swale until a change order was approved. On October 19,

2009, the project engineer prepared and signed Change Order 3 providing for a price

increase of $160,722, for a total of $233,198, plus a 40-day extension of time to complete

the project. The project engineer presented Change Order 3 to city engineer Jeff Johnson,

who did not sign it. The change order was not sent to the city council for approval.

Brindley believed that a valid change order was in place and CEI continued work on the

project.

In November 2009, the city rescinded Change Order 3 on the ground that the

straight-line measurement between the haul material and the dumpsite was less than the

one-half mile distance provided for within the contract. The city advised CEI of the

rescission. On December 1, 2009, CEI challenged the rescission and sent a letter to the

city requesting payment under Change Order 3. The December 1 letter outlined the Change

4 Order 3 approval as understood by appellant, but did not include supporting documentation

such as the number of hours involved, wage rates, or labor or material costs.

On December 3, 2009, CEI’s counsel sent a letter to Jeff Johnson, the city engineer,

entitled “Notice of Claim,” and “provid[ing] CEI’s notice of claim regarding the City of

Mankato’s purported rescission of Change Order 3.” Like the earlier letter, the December 3

letter sought payment for extra work without providing detailed evidence supporting the

claim in the way of number of hours worked, wage rates, or labor or material costs. Instead,

the letter asserted a number of legal arguments and cited to legal authority, rather than to

documentation supporting the extra work itself.

Johnson denied additional payment. CEI continued to work on the project, which

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DLH, Inc. v. Russ
566 N.W.2d 60 (Supreme Court of Minnesota, 1997)
STANDARD CONSTRUCTION CO. INC. v. National Tea Co.
62 N.W.2d 201 (Supreme Court of Minnesota, 1953)
Day Masonry v. Independent School District 347
781 N.W.2d 321 (Supreme Court of Minnesota, 2010)
Marso v. Mankato Clinic, Ltd.
153 N.W.2d 281 (Supreme Court of Minnesota, 1967)
Janssen v. Best & Flanagan, LLP
704 N.W.2d 759 (Supreme Court of Minnesota, 2005)
Buchman Plumbing Co., Inc. v. Regents of the U. of M.
215 N.W.2d 479 (Supreme Court of Minnesota, 1974)
Cooke v. Belzer
413 N.W.2d 623 (Court of Appeals of Minnesota, 1987)
D.H. Blattner & Sons, Inc. v. Firemen's Insurance Co.
535 N.W.2d 671 (Court of Appeals of Minnesota, 1995)
New Ulm Building Center, Inc. v. Studtmann
225 N.W.2d 4 (Supreme Court of Minnesota, 1974)
Lundstrom Construction Co. v. Dygert
94 N.W.2d 527 (Supreme Court of Minnesota, 1959)
Halverson v. Village of Deerwood
322 N.W.2d 761 (Supreme Court of Minnesota, 1982)
Chergosky v. Crosstown Bell, Inc.
463 N.W.2d 522 (Supreme Court of Minnesota, 1990)
Caldas v. Affordable Granite & Stone, Inc.
820 N.W.2d 826 (Supreme Court of Minnesota, 2012)
Ruiz v. 1st Fidelity Loan Servicing, LLC
829 N.W.2d 53 (Supreme Court of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Contractors Edge, Inc. v. City of Mankato, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-edge-inc-v-city-of-mankato-minnctapp-2016.