STANDARD CONSTRUCTION CO. INC. v. National Tea Co.

62 N.W.2d 201, 240 Minn. 422, 1953 Minn. LEXIS 713
CourtSupreme Court of Minnesota
DecidedDecember 11, 1953
Docket35,845
StatusPublished
Cited by10 cases

This text of 62 N.W.2d 201 (STANDARD CONSTRUCTION CO. INC. v. National Tea Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STANDARD CONSTRUCTION CO. INC. v. National Tea Co., 62 N.W.2d 201, 240 Minn. 422, 1953 Minn. LEXIS 713 (Mich. 1953).

Opinions

Frank T. Gallagher, Justice.

This was an action by Standard Construction Company, Inc., referred to hereinafter as Standard, to foreclose a mechanic’s lien for $11,268.47, in which defendant National Tea Company, referred to hereinafter as National, counterclaimed for $180,333.26 allegedly paid under protest in excess of the amount due plaintiff. The case was tried before the court without a jury. Judgment was granted for plaintiff in the amount of $10,776.33, plus $10,000 attorneys’ fees and $10 costs, and National’s counterclaim was denied. Defendants National and Northwestern Mutual Life Insurance Company of Milwaukee, Wisconsin, appealed from an order denying their alternative motion for amended findings of fact and conclusions of law or for a new trial.

On March 23, 1946, Standard signed a contract to build a huge combination garage, warehouse, bakery, and office building for National in Hopkins, Minnesota. Northwestern Mutual Life Insur[424]*424anee Company purchased the building after its completion and leased it to National, but for the purposes of this opinion we will consider the action as one between Standard and National. Because of the circumstances in which National found itself in 1946, extreme haste characterized the project from its inception to the completion of the work. The federal government had ordered that no commercial construction be continued after March 25, 1946, unless an integral part of the structure was in existence on that date. There was testimony that it was imperative to National that construction go forward because at that time its whole development in this area depended upon this expansion of its base of operations. In any event, in an apparent effort to comply with government regulations, a few yards of concrete footing were poured on March 25, 1946, although never incorporated into the structure which was built. According to the record, National’s desire for haste continued throughout the course of construction because it was being subjected to high demurrage costs as the result of the inadequacy of its old warehouse and because it wanted to vacate and sell the old warehouse while the market was still favorable and before threatened major repairs became necessary.

The contract provided that Standard procure all necessary materials and construct the building according to the plans then in existence for a fixed percentage of the total cost, which was not to exceed $1,245,000. No completion date was specified. It seems agreed that the plans and specifications then available were at best a hazy approximation of the building which resulted. The original plans were produced in less than a week, although there was testimony that from six to twelve months are usually required to draw complete plans for a building of this type. Standard’s estimator was given only 24 hours in which to prepare the bid based on these plans.

Plan changes, confusion, and delays accompanied almost every step of the construction process. Altogether 146 change orders were presented. Their purpose apparently was to permit adjustment of the maximum guaranteed price in order to allow for the cost of departures from or elaborations of the plans on which the original bid was based. Only four of these change orders are disputed on this [425]*425appeal. The conceded cost of the building was more than half a million dollars over the original bid. After the bid was accepted, the proposed location and elevation of the building was changed. Later, it was decided to construct the building of reinforced concrete rather than structural steel; the size of the structure was increased by about one-fourth; and numerous other significant changes were made. Although the trial court held that the contract was still in force, it observed in its memorandum that the facts of the case provided considerable support for the contention that the conduct of the parties had resulted in an abandonment of the original contract or a waiver of the ceiling price provision.

As of the date of trial National conceded the propriety of change orders resulting in an increase over the original bid of $615,171.57, making a total cost of $1,860,171.57. The trial court found that the original price, plus allowable change orders, resulted in a net price of $2,058,011.17, of which National had already paid all except $10,776.33. It granted judgment in that amount with interest at six percent from the date of completion of the building, plus $10,000 attorneys’ fees and $10 costs. On this appeal, National contends that the allowance of four of these change orders was not supported by the evidence and was contrary to law.

In allowing change order No. 107 the trial court found that the guaranteed maximum price of the building should be increased by $71,815.66 to cover the cost of compaction not contemplated when the original contract was signed. Compaction is the process which was used for compressing earth that had been hauled in to serve as support for the concrete floor of the warehouse. Its purpose was to increase the density of the freshly hauled earth to approximately that of natural soil, thus reducing the danger that the structure supported by the fresh fill would be damaged by settling. Most of the compaction on this project involved spreading of earth and clay in an eight-inch layer which was then sprinkled with water and rolled with sheep’s-foot rollers until the proper density of soil resulted. The process was then repeated with successive eight-inch layers of fill until the proper elevation was reached. Part of the [426]*426floor of the building rested on fill which had been hauled and compacted until it reached a depth of over 17 feet. Where there was insufficient room for operation of the cumbersome machinery used in this type of compaction, the fill was hand compacted. This involved shoveling the earth into place and compressing it with vibrators which were similar in operation to compressed-air hammers. Part of the compacting was done by means of a third process which involved saturating the fresh fill with water, thus producing a concentration of the particles of earth after the water had drained away.

National accepts the finding of the trial court that Standard performed 44,454 cubic yards of machine compaction and 3,699 cubic yards of hand compaction. It contends, however, that the cost of compaction was or should have been included in Standard’s original bid and that, therefore, no addition to the guaranteed maximum price is justified. National further contends that, if any price increase was properly allowed, the cost per cubic yard used in calculating the increase was excessive. The findings of the trial court must be judged by the familiar rule which requires that they be upheld if reasonably supported by the evidence considered as a whole. Knutson v. Lasher, 219 Minn. 594, 18 N. W. (2d) 688; Meiners v. Kennedy, 221 Minn. 6, 20 N. W. (2d) 539; Ehmke v. Hill, 236 Minn. 60, 51 N. W. (2d) 811; 1 Dunnell, Dig. (3 ed.) § 411.

Whether Standard should have allowed for the cost of compaction when it made its bid depends in part on the meaning of the original plans and specifications. With reference to the preparation of the earth beneath the building they provided that the contractor “prepare for paving where shown.” Since the technical significance of this phrase is not apparent on its face, opinions of witnesses qualified as experts in the construction trade properly were received. St. Paul & Minneapolis Trust Co. v. Harrison, 64 Minn. 300, 66 N. W. 980. Theodore A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Contractors Edge, Inc. v. City of Mankato
Court of Appeals of Minnesota, 2016
Rainforest Cafe, Inc. v. State Investment Board
677 N.W.2d 443 (Court of Appeals of Minnesota, 2004)
McCarron's Building Center, Inc. v. Einertson
482 N.W.2d 529 (Court of Appeals of Minnesota, 1992)
Gardner v. Hatch
408 N.W.2d 879 (Court of Appeals of Minnesota, 1987)
Richard Knutson, Inc. v. Westchester, Inc.
374 N.W.2d 485 (Court of Appeals of Minnesota, 1985)
Klingelhutz v. Grover
236 N.W.2d 610 (Supreme Court of Minnesota, 1975)
Hertz v. Hertz
229 N.W.2d 42 (Supreme Court of Minnesota, 1975)
Palmer v. Watson Construction Co.
121 N.W.2d 62 (Supreme Court of Minnesota, 1963)
Powers v. Siats
70 N.W.2d 344 (Supreme Court of Minnesota, 1955)
STANDARD CONSTRUCTION CO. INC. v. National Tea Co.
62 N.W.2d 201 (Supreme Court of Minnesota, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
62 N.W.2d 201, 240 Minn. 422, 1953 Minn. LEXIS 713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-construction-co-inc-v-national-tea-co-minn-1953.