Palmer v. Watson Construction Co.

121 N.W.2d 62, 265 Minn. 195, 1963 Minn. LEXIS 650
Supreme Court of Minnesota·Decided April 5, 1963·No. 38,713·Published·Cited by 6 cases

Opinion

Sheran, Justice.

The appeal is from an order of the district court denying defendants’ motion for judgment notwithstanding the verdict or, in the alternative, a new trial.

The action was instituted by plaintiff to recover progress payments, retained percentages, and damages for breach of contracts for excavation and backfilling, one being dated August 26, and the other September 20, 1960. In response defendant Watson Construction Company 1 asserted default by plaintiff and counterclaimed for damages occasioned by his failure to perform.

The subject matter of the contracts was excavation, backfilling, sodding, and seeding to be performed in connection with the construction of four buildings and connecting tunnels being built at the state hospital at Brainerd pursuant to a prime contract between defendant and the State of Minnesota.

Relevant contract provisions fixing the obligations of these parties included the following:

“The Contractor agrees—
*****
“h) To pay the Subcontractor on demand for his work or materials as far as executed and fixed in place, less the retained percentage, * * *."

*197 The subcontractor’s obligations are described as follows:

“Section 3. The Subcontractor agrees to complete the several portions and the whole of the work herein sublet by the time or times following: As required by the progress of the job. Sub-Contractor agrees to provide sufficient equipment to complete the excavation of the four buildings this fall and, further agrees that if he does not provide proper equipment to complete his contract, the contractor has the right to bring in additional equipment and charge the cost of same against his contract.”

The contracts involved do not contain provisions governing resolution of disputes between the parties as to quantities of work performed for purpose of progress payments where, as here, there was no certification by the architect. 2

On October 6, 1960, plaintiff submitted to defendant a statement for work completed as of September 20, 1960, which included a claim for $7,760 for excavation of 19,400 cubic yards of earth at 40¡¿ per cubic yard. Upon receipt defendant disputed the quantity of excavation for which it had been billed and sent plaintiff a check which included the sum of $5,400, less retained percentage, representing payment for excavation of 13,500 cubic yards of material. Protracted negotiations then ensued during the course of which plaintiff insisted that he was entitled to payment based upon his figures, which represented the quantity of material which he claimed he had in fact removed. Defendant persisted in its refusal to accept these figures on the theory that if the quantity of material claimed by plaintiff had in fact been removed, plaintiff had “overexcavated,” i. e., excavated from the foundation grade to the level of the ground at an angle in excess of that prescribed by defendant and by proper and customary standards of workmanship. Plaintiff’s response to this contention was that certain stakes had been placed at the job site by defendant and that plaintiff, excavating *198 with reference to the stakes, was performing the work in the manner in which defendant had directed.

Defendant denied that the stakes had been placed by its agents and in this connection Walter Coppersmith, job superintendent for defendant, testified:

“Q. Who did the staking out of whatever staking was done for the excavation?
“A. Mr. Palmer and his men.
“Q. Did you ever send anybody from the Watson Company out to do staking of the excavation?
“A. None whatsoever.”

Following further testimony with respect to the stakes, Coppersmith related this conversation with the plaintiff:

“Q. What conversation did you have at that time?
“A. I told them they were not digging according to my instructions and were overdigging.
“Q. What did Mr. Palmer have to say about it?
“A. He told me it — with that type of equipment they needed roads to get in and out and with that type of equipment they couldn’t dig 1 to 1 slope and that’s the best they could do with that type of equipment.
“Q. Did you have conversation with him at that time about payments?
“A. Yes, I told him I didn’t want the hole dug that large and that it made it too tough to build the buildings and I told him we would not be paying him for that type of digging. He told me not to worry about it and he said, ‘When the holes are measured we will allow for our roads and the over-excavation and will settle up that way, and don’t worry about it.’ ”

Although plaintiff submitted statements for and received payment on account of additional excavation performed during the month of November, the disagreement with respect to the quantity for which he was entitled to payment in connection with the digging done by him and included in the October 6 billing was never resolved. Apparently construction work on the project was resumed in February 1961, but plaintiff de *199 dined to perform further under his subcontracts unless he was paid in conformity with his calculations. Upon recross-examination he was asked:

“Q. Do you remember receiving a letter from Watson in February stating if you did not get back on the job they were going to have to get somebody else to do it?
“A. Yes.
* * * * *
“Q. You didn’t ever go back on the job to do the work, did you?
“A. Not after that time.”

Free access — add to your briefcase to read the full text and ask questions with AI

Palmer v. Watson Construction Co., 121 N.W.2d 62, 265 Minn. 195, 1963 Minn. LEXIS 650 (Mich. 1963).

121 N.W.2d 62 (Palmer v. Watson Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First State Bank of Floodwood v. Jubie
86 F.3d 755 (Eighth Circuit, 1996)
First State Bank Of Floodwood v. Jubie
86 F.3d 755 (First Circuit, 1996)
BAKER DOMES, DIV. OF RM BAKER CO. v. Wolfe
403 N.W.2d 876 (Court of Appeals of Minnesota, 1987)
Sheet Metal Workers Local 76 Credit Union v. Hufnagle
295 N.W.2d 259 (Supreme Court of Minnesota, 1980)
Dale v. Fillenworth
162 N.W.2d 234 (Supreme Court of Minnesota, 1968)