William Wharton, Jr., & Co. v. Winch

35 N.E. 589, 140 N.Y. 287, 55 N.Y. St. Rep. 652, 95 Sickels 287, 1893 N.Y. LEXIS 1146
CourtNew York Court of Appeals
DecidedDecember 5, 1893
StatusPublished
Cited by41 cases

This text of 35 N.E. 589 (William Wharton, Jr., & Co. v. Winch) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William Wharton, Jr., & Co. v. Winch, 35 N.E. 589, 140 N.Y. 287, 55 N.Y. St. Rep. 652, 95 Sickels 287, 1893 N.Y. LEXIS 1146 (N.Y. 1893).

Opinion

Maynard, J.

Defendant was the contractor for the construction of a street railway in Lincoln, Nebraska, and entered into - an agreement with plaintiff by the terms of which the latter was to furnish the materials and labor for the entire construction of the railway tracks in consideration of the sum of $56,000, to be paid by the defendant as follows: $5,000 within five days after the execution of the agreement; the market value with the freight added of the materials needed for the construction of the tracks whenever and as soon as delivered in Lincoln ; $11,200 when a half mile of double track shall have been laid, less the amount previously paid for materials used in its construction, and similar payments for each half mile of double track laid. The $5,000 first paid was to be deducted from the last payment due. The plaintiff began the construction of the tracks, and at the request of the defendant prepared to first lay down a single track for the whole distance of two and one-half miles, instead of constructing both tracks simultaneously, and on Nov. 9, 1887, notified the defendant that all the materials for the construction of the single track were in Lincoln and the plaintiff was ready to proceed to lay the track upon receipt of $12,000, the cost of the material. The plaintiff’s place of business was at Philadelphia and that of the defendant in New York, and it is evident that defendant expected to raise the money in Lincoln from the sale of stock and bonds of the railway company to parties there, and he immediately informed plaintiff that he had received word from Lincoln and that the check for the materials was on the way and would be forwarded without delay. The check, however, did not arrive, and there was further correspondence in which defendant explained the failure to make payment as expected, but on Nov. 12th he *291 forwarded a cheek for $4,000, and requested plaintiff to go ahead with the work at once without fail, saying that as soon as plaintiff began work the parties at Lincoln would send more money. Plaintiff replied on the 14th that it would begin work, but the amount sent was so small that it would have only a small portion of the work done. Defendant, again promised $5,000 or $10,000 cash by the next Wednesday, or other security, and urged plaintiff to keep working at Lincoln. Two days later plaintiff wrote defendant that it would lay-down a half mile of single track, and after recalling the terms of the contract and showing how it had not been kept by defendant, the plaintiff further stated that it most certainly did not intend to lay any more than the one-half mile of single track until defendant made payment as agreed.

Neither cash nor securities were forthcoming, and Nov. 23 plaintiff telegraphed defendant that its men were idle at Lincoln and it should order them home in forty-eight hours. The defendant replied proposing other security and urging plaintiff to lay a half mile more before December 1st. Plaintiff telegraphed requesting defendant to come over the next day and bring the proposed security, and that probably they could arrange matters. Defendant replied that he would be there, but did not come. December 2d plaintiff wrote defendant, formally notifying him that his failure to comply with the terms of the contract had been the cause and was still the cause of considerable loss; that there were constantly daily expenses accruing for men, interest on materials, etc., which it would look to him to make good, and further notifying him that in view of the breach of the contract on the part of the defendant the plaintiff did not consider itself further bound thereby. The defendant replied the next day that he had telegrams and letters from plaintiff stating that it should withdraw its men from Lincoln on a specified date, and that if it had not done so the delay was upon its own responsibility. After this there was some correspondence with reference to the substitution of other parties in place of the defendant, but the plaintiff stated that the negotiations were favored with the *292 full understanding that the defendant, by his own acts of omission to make payments as agreed upon, had already canceled the contract, provided the plaintiff chose to have it canceled. These negotiations failed, and no • further work was done by plaintiff under the contract, and no further payments made by defendant. The plaintiff brought this action Nov. 10, 1888, to recover the damages sustained by defendant’s breach of the contract. The contract price of the one-half mile of road constructed, including the materials, was $5,600, and the whole amount received under the contract was $9,560. The plaintiff has thus received from defendant $3,960 more than the contract price of that part of the road actually built, but it claims that if it had been allowed to complete the construction of the road and had been paid for it according to the contract, that it would have made a profit of $13,871, and that it has, therefore, sustained damage to the amount of $9,911, and it is that sum which it seeks to recover in this action. The sole question presented for judicial decision is whether, upon the facts proven in this case, the plaintiff is entitled to recover prospective profits because of the failure of the defendant to pay the installment of the contract price which fell due upon the delivery of the material at Lincoln on Nov. 9th. The execution of the contract, and what the parties did under it, and what they failed or refused to do, are all matters about which there is no conflict or dispute in the testimony given upon the trial, and at the close of the evidence both parties requested the direction of a verdict, and the motion of the defendant was granted, to which the plaintiff excepted. The plaintiff then requested the court to submit to the jury the question whether or not the evidence in this case did not evince an intention on the part of defendant not to comply with the terms of the contract, and a total failure on his part, which was declined and an exception taken.

In view of the structure of this contract it would seem to> be clear that the mere failure of the defendant to make punctual payment of an installment due according to its provisions *293 was not such a breach of the entire contract as to permit the plaintiff to refuse to proceed further under it, and recover damages for the profits which he would have earned had the contract been fully performed on his part.

In the able and elaborate brief submitted by the learned counsel for the appellant our attention has not been called to any case where the contrary of this proposition has been maintained. While the question does not seem to have been the subject of frequent discussion in this state, authority is not wanting to support this view.

In Moore v. Taylor (42 Hun, 45), the plaintiff sought to recover prospective profits upon the failure to pay an installment under a contract for railroad construction similar in its important features to the one before us, and it was held by the General Term of the fifth department, Judge Bradley delivering the opinion of the court, that mere default in the payment of an installment when it becomes due is not such a denial of the right of the contractor to continue in the performance of the service, as in legal effect to constitute a breach of the entire contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin Pavkov Construction Co. v. Ultra Roof, Inc.
51 F. Supp. 2d 204 (N.D. New York, 1999)
BROWN BROS. v. Beam Constr.
361 N.E.2d 999 (New York Court of Appeals, 1977)
Brown Bros. Electrical Contractors, Inc. v. Beam Construction Corp.
41 N.Y. 397 (New York Court of Appeals, 1977)
Veverka v. Spinella
60 Misc. 2d 529 (New York Supreme Court, 1969)
Palmer v. Watson Construction Co.
121 N.W.2d 62 (Supreme Court of Minnesota, 1963)
Sklar Door Corp. v. Locoteta Homes Inc.
33 Misc. 2d 299 (New York Supreme Court, 1961)
S. T. Grand, Inc. v. Cedar Bay Park Corp.
14 Misc. 2d 428 (New York Supreme Court, 1958)
Indian River Islands Corp. v. Manufacturers Trust Co.
253 A.D. 549 (Appellate Division of the Supreme Court of New York, 1938)
Rosenthal v. Becher
159 Misc. 856 (City of New York Municipal Court, 1936)
New York Life Insurance v. Viglas
297 U.S. 672 (Supreme Court, 1936)
Edelman v. Wechsler
245 A.D. 748 (Appellate Division of the Supreme Court of New York, 1935)
Rogers v. United Grape Products, Inc.
2 F. Supp. 70 (W.D. New York, 1933)
Rich v. Arancio
178 N.E. 743 (Massachusetts Supreme Judicial Court, 1931)
O'Rourke Engineering Construction Co. & Duit, Inc. v. City of New York
229 A.D. 261 (Appellate Division of the Supreme Court of New York, 1930)
Anderson v. John L. Hayes Construction Co.
153 N.E. 28 (New York Court of Appeals, 1926)
Washburne v. Property Owners Co-operative Ass'n of Middlesex County, Inc.
209 A.D. 365 (Appellate Division of the Supreme Court of New York, 1924)
Berger v. Urban Motion Picture Industries, Inc.
206 A.D. 379 (Appellate Division of the Supreme Court of New York, 1923)
Ryan v. Rodgers & Hagerty, Inc.
197 A.D. 662 (Appellate Division of the Supreme Court of New York, 1921)
Cochran v. Hamblen
215 S.W. 374 (Court of Appeals of Texas, 1919)
Helgar Corporation v. . Warner's Features
119 N.E. 113 (New York Court of Appeals, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
35 N.E. 589, 140 N.Y. 287, 55 N.Y. St. Rep. 652, 95 Sickels 287, 1893 N.Y. LEXIS 1146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-wharton-jr-co-v-winch-ny-1893.