Franklin Pavkov Construction Co. v. Ultra Roof, Inc.

51 F. Supp. 2d 204, 5 Wage & Hour Cas.2d (BNA) 846, 1999 U.S. Dist. LEXIS 8213, 1999 WL 359666
CourtDistrict Court, N.D. New York
DecidedJune 1, 1999
Docket1:96-cv-01297
StatusPublished
Cited by9 cases

This text of 51 F. Supp. 2d 204 (Franklin Pavkov Construction Co. v. Ultra Roof, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklin Pavkov Construction Co. v. Ultra Roof, Inc., 51 F. Supp. 2d 204, 5 Wage & Hour Cas.2d (BNA) 846, 1999 U.S. Dist. LEXIS 8213, 1999 WL 359666 (N.D.N.Y. 1999).

Opinion

MEMORANDUM-DECISION AND ORDER

HURD, United States Magistrate Judge.

I. INTRODUCTION

Plaintiff, Franklin Pavkov Construction Company (“Pavkov” or “plaintiff’) alleges that defendant Ultra Roof, Inc. (“Ultra Roof’) breached a subcontract entered into between the two companies. Pavkov claims that Ultra Roof, which subcontracted with Pavkov to retrofit á roof at an Army facility in Rotterdam, New York (“Rotterdam project”), 1 did not timely commence work on the project, unreasonably delayed performance, and abandoned the project without justification. Ultra Roof contends that its duty to perform was discharged due to Pavkov’s failure, to make payments according to the terms of the subcontract and counterclaimed for breach of the subcontract. Defendant International Fidelity Insurance Company (“IFIC”) is Pavkov’s bonding company, 2 and was made an additional defendant on Ultra Roofs counterclaim. 3

II. TRIAL

A five day bench trial was ednducted from February 3, 1999 through February 9, 1999 in Utica, New York. Testifying on behalf of the plaintiff was its Vice President, Mark Pavkov. Also testifying in support of plaintiff were Vince Pavkov, project manager for the Rotterdam project, and John Miller, the Federal government inspector for the project. Finally, plaintiff called Martin Keller, owner of Kelco Roofing & Sheet Metal, Inc., Peter Corsi, and Ed Kolbako, president of Ed’s Electrical Service, Inc., to testify concerning the issues of costs of completion and work remaining on the project after Ultra Roof left the site. Testifying on behalf of the defendant were Alan Beck (“Beck”), owner of Ultra Roof, and Jackie Lane, project superintendent. Post trial proposed Findings of Fact and Conclusions of Law were filed by all parties on April 15, 1999.

Based upon all of the evidence, including voluminous exhibits, and the credibility of *208 the witnesses, the following constitutes the Findings of Fact and Conclusions of Law pursuant to Fed.R.Civ.P. 52.

III. FINDINGS OF FACT

A. The Subcontract

Pavkov is a corporation organized and existing under the laws of the State of Ohio, which engages in roof contracting. In September of 1993, Pavkov entered into a contract with the United States Government, Department of the Army, for the construction of a retrofit roof at the Army Facility in Rotterdam, New York. The contract was for the sum of $723,549.00. The contract, designated as contract number DAKF36-93-C-0094, called for performance to begin within ten (10) days and completion within three hundred sixty (360) days after receiving the notice to proceed. The contract provided that failure to complete the work within the time specified in the contract, or any extension, would result in the contractor having to pay liquidated damages in the sum of $177.91 per day for each day past the completion date. The contract also provided that, in the event that the contractor withheld any monies from a subcontractor, the contractor must provide written notice to the subcontractor, identifying the amount being withheld, the reason for the withholding, and the mandatory remedial action. In addition, a copy of such written notice must be given to the contracting officer. Specifications for the Rotterdam project and the applicable rates of wage were attached to the contract. Pavkov was to bill the Government monthly and be reimbursed monthly based upon the percentage of work completed, which Pavkov and the government inspector were to agree upon. Pursuant to the contract and the terms of the Miller Act, Pavkov obtained a performance bond and payment bond from IFIC. The payment bond was in the penal sum of $361,774.50.

Although Pavkov originally intended to perform the contract itself, it later decided to subcontract the work. In or about December of 1993, Mark Pavkov directed his brother, Vince Pavkov, to solicit bids. Vince Pavkov contacted Alan Beck, owner of Ultra Roof, who had previously quoted a price to complete the project. On December 14, 1993, Beck faxed a one-page letter to Vince Pavkov’s attention proposing to complete the Rotterdam project for the sum of $575,543.00. The letter, which was received the same day by Pavkov, contained four Roman numeral headings outlining the terms of the proposal. The fourth section, labeled “Terms and Conditions”, contained five subsections, which read as follows:

A) Ultra Roof Inc. will be paid 3% for Mobilization of the total amount of our Contract, due upon receipt of invoice.
B) Ultra Roof Inc. will furnish Certified Payroll Reports Weekely (sic) & will be paid weekely (sic) on the following Friday.
C) All material supplied by Ultra Roof Inc. to be paid Net 30 days, Ultra Roof Inc. takes exception to our payment being contingent upon the General Contractor receipt of Payment from owner.
D) Ultra Roof Inc. will not agree to liquidated damages until (sic) a mutually agreed upon schedule [is] reached.
E) Ultra Roof Inc. will perform roofing in a neat & workmanship type manor (sic), we are not responsible for subsequent cleaning.

(Ex. D-2.) Subdivision “E” was not followed by any further language other than Beck’s closing and signature line.

Vince Pavkov reviewed the proposal and discussed it with Mark Pavkov, at which time certain changes were made. Vince Pavkov handwrote “Addendum A” at the top of the proposal. In addition, since Mark Pavkov found the payment term in subdivision “B” unacceptable, an additional payment term was added at the bottom of the proposal, which read as follows:

F) First Payroll Payment will be made two weeks after commencing work and subsequent payments in line with % *209 completion and # B under terms and conditions.

(Ex. P-41.) There is no evidence that this change was ever faxed to Beck. Additionally, Vince Pavkov’s testimony at his deposition and at trial are contradictory regarding whether he had ever discussed the changes made to the proposal with Beck. (Tr. at 130, Vince Pavkov Dep. at 34, 41.)

Vince Pavkov faxed a one-page letter to Beck on December 14, 1993 requesting a meeting with Beck on December 16, 1993 at Ultra Roofs office in Jasper, Indiana to discuss the Rotterdam project, sign the subcontract, discuss the start date, submit-tals, and payment schedule, and some other matters. No mention was made in this letter of any changes made to Beck’s December 14,1993 proposal.

Prior to traveling to meet with Beck, Vince Pavkov prepared several documents which would comprise the subcontract. The first page was a preprinted subcontract agreement indicating that the subcontract applied to the Rotterdam project, the price, and a start date of April 15,1994 and completion date of August 31, 1994. In addition, the first page referenced terms contained in “Addendum A”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baum v. County of Rockland
337 F. Supp. 2d 454 (S.D. New York, 2004)
Wechsler v. Hunt Health Systems, Ltd.
330 F. Supp. 2d 383 (S.D. New York, 2004)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
Betal Environmental Corp. v. Local Union Number 78
162 F. Supp. 2d 246 (S.D. New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
51 F. Supp. 2d 204, 5 Wage & Hour Cas.2d (BNA) 846, 1999 U.S. Dist. LEXIS 8213, 1999 WL 359666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklin-pavkov-construction-co-v-ultra-roof-inc-nynd-1999.