Ed Kimber Heating & Cooling, Inc. v. Travelers Casualty & Surety Co.

411 F. Supp. 2d 111, 2006 U.S. Dist. LEXIS 3323, 2006 WL 233388
CourtDistrict Court, D. Connecticut
DecidedJanuary 26, 2006
Docket3:03CV2111(SRU)
StatusPublished
Cited by1 cases

This text of 411 F. Supp. 2d 111 (Ed Kimber Heating & Cooling, Inc. v. Travelers Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ed Kimber Heating & Cooling, Inc. v. Travelers Casualty & Surety Co., 411 F. Supp. 2d 111, 2006 U.S. Dist. LEXIS 3323, 2006 WL 233388 (D. Conn. 2006).

Opinion

RULING ON MOTION FOR PARTIAL SUMMARY JUDGMENT

UNDERHILL, District Judge.

On December 1, 2004, the plaintiff, Ed Kimber Heating and Cooling, Inc. (“Kimber”), filed a motion for partial summary judgment, asking the court to dismiss the portion of Travelers Casualty and Surety Co.’s (“Travelers”) counterclaim that seeks excess costs of completion. 1 On November 18, 2005, the court heard oral argument by both parties. For the reasons that follow, I grant Kimber’s motion for partial summary judgment, dismissing the portion of Traveler’s counterclaim seeking excess costs of completion.

I. Factual Background

The Town of Southington hired Trataros Construction, Inc. (“Trataros”) as the general contractor to make additions and alterations to the William H. Hatton School. Travelers issued payment and security bonds as the surety for Trataros. Trataros subcontracted with Kimber, which performed HVAC and plumbing work for the project from March 2002 until February 7, 2003.

*113 Trataros made periodic progress payments to Kimber; the last check Kimber received was dated December 10, 2002. Trataros prepared a payment check, dated January 27, 2003, but the check was written on an account requiring approval by Travelers, and Travelers did not sign the check. The parties agree that Trataros did not give Kimber a progress payment in January 2003. Defendant’s Local Rule 56(a)(2) Statement at ¶¶ 9-10.

On approximately January 30, 2003, Travelers contracted with Newfield Construction, Inc. (“Newfield”) to complete the project, because Trataros could not do so. In February 2003, Newfield employed Action Air Systems to perform work that was within the scope of Kimber’s work. Trataros stopped working on the project on February 28, 2003.

The parties agree for purposes of summary judgment that the operative subcontract includes the written subcontract agreement and an October 1, 2002 letter written by Kimber and annotated by Trataros. Ed Kimber’s Affidavit in Support of Plaintiffs Application for Partial Summary Judgment Dismissing Counterclaim, Exhibits 1-2. The written subcontract contains a choice-of-law clause that provides: “This subcontract shall be governed by and construed in accordance with the laws of the State of New York.” Ed Kimber’s Affidavit in Support of Plaintiffs Application for Partial Summary Judgment Dismissing Counterclaim, Exhibit 1 at ¶ 25. The parties agree that the subcontract required Trataros to make monthly progress payments to Kimber. Defendant’s Local Rule 56(a)(2) Statement at ¶ 6; Ed Kimber’s Affidavit in Support of Plaintiff’s Application for Partial Summary Judgment Dismissing Counterclaim, Exhibit 1 at ¶ 2(c). The subcontract requires that, if Kimber breaches the subcontract, Trataros must give it three days’ written notice prior to a declaration of default. Ed Kimber’s Affidavit in Support of Plaintiffs Application for Partial Summary Judgment Dismissing Counterclaim, Exhibit 1 at ¶ 8(a).

Travelers did not assume and was not assigned Kimber’s subcontract with Trataros. Neither Trataros nor Travelers ever gave Kimber three days’ written notice of default.

Kimber is suing Travelers for breach of contract in the amount of $136,987.58. 2 Travelers counterclaimed for $478,000, which includes the excess cost to complete the work under the subcontract, the cost of corrective work, and the cost to reimburse Kimber’s vendors. Travelers paid $30,310.70 for corrective work, $37,487.25 for payments to Kimber’s vendors, and $313,262 for excess completion costs.

Kimber now seeks summary judgment on the excess completion costs portion of Travelers’ counterclaim, alleging that Travelers is not entitled to recover its excess costs from Kimber because its principal, Trataros, breached the subcontract, thereby justifying Kimber’s decision to stop performing under the contract.

II. Discussion

A. Standard of Review

Summary judgment is appropriate when the evidence demonstrates that “there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” FED. R. CIV. P. 56(c); see also Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986) (plaintiff must present affirmative evidence in order to defeat a properly supported motion for summary judgment).

When ruling on a summary judgment motion, the court must construe the facts *114 in the light most favorable to the nonmoving party and must resolve all ambiguities and draw all reasonable inferences against the moving party. Anderson, 477 U.S. at 255, 106 S.Ct. 2505; Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970); see also Aldrich v. Randolph Cent. Sch. Dist, 963 F.2d 520, 523 (2d Cir.1992) (court is required to “resolve all ambiguities and draw all inferences in favor of the nonmoving party”), cert. denied, 506 U.S. 965, 113 S.Ct. 440, 121 L.Ed.2d 359 (1992). When a motion for summary judgment is properly supported by documentary and testimonial evidence, however, the nonmoving party may not rest upon the mere allegations or denials of his pleadings, but rather must present significant probative evidence to establish a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 327, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Colon v. Coughlin, 58 F.3d 865, 872 (2d Cir.1995).

“Only when reasonable minds could not differ as to the import of the evidence is summary judgment proper.” Bryant v. Maffucci, 923 F.2d 979, 982 (2d Cir.1991), cert. denied, 502 U.S. 849, 112 S.Ct. 152, 116 L.Ed.2d 117 (1991); see also Suburban Propane v. Proctor Gas, Inc., 953 F.2d 780, 788 (2d Cir.1992). If the nonmoving party submits evidence that is “merely colorable,” or is not “significantly probative,” summary judgment may be granted. Anderson, 477 U.S. at 249-50, 106 S.Ct. 2505.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weber v. Fujifilm Medical Systems U.S.A., Inc.
933 F. Supp. 2d 285 (D. Connecticut, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
411 F. Supp. 2d 111, 2006 U.S. Dist. LEXIS 3323, 2006 WL 233388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ed-kimber-heating-cooling-inc-v-travelers-casualty-surety-co-ctd-2006.