Paterno & Sons, Inc. v. Town of New Windsor

43 A.D.2d 863, 351 N.Y.S.2d 445, 1974 N.Y. App. Div. LEXIS 5875
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 28, 1974
StatusPublished
Cited by16 cases

This text of 43 A.D.2d 863 (Paterno & Sons, Inc. v. Town of New Windsor) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paterno & Sons, Inc. v. Town of New Windsor, 43 A.D.2d 863, 351 N.Y.S.2d 445, 1974 N.Y. App. Div. LEXIS 5875 (N.Y. Ct. App. 1974).

Opinion

In an action (1) to rescind a contract under which plaintiff was to construct a sewerage trunk system for a sewer district in defendant town and (2) to recover in quantum meruit for work done, (a) plaintiff appeals from an order of the Supreme Court, Orange County, entered June 28, 1973, which, after reargument, inter alla (i) denied plaintiff’s motion for summary judgment “for the relief demanded in the complaint ”, (ii) granted plaintiff summary judgment for the balance due under the contract to the date the contract was terminated, the amount to be determined upon an assessment, and (iii) granted in part defendant’s motion to amend its answer to set forth a counterclaim for liquidated damages; and (2) defendant cross-appeals, as limited by its brief, from so much of the order as denied the branch of its cross motion which was for leave to interpose a second and third counterclaim against plaintiff and a first and second cross claim [864]*864against other parties. Order modified, on the law, by (1) deleting from the first decretal paragraph thereof (which denied plaintiff’s motion for the relief demanded in the complaint”) the word “denied” and substituting therefor the word “granted”; (2) deleting the third decretal paragraph thereof (which granted plaintiff summary judgment for the above mentioned balance) ; and (3) deleting from the fourth decretal paragraph (which directed that the assessment be held before the court “ and a jury ”) the word “ and ” and substituting therefor the word “without”. As so modified, order affirmed, with $20 costs and disbursements to plaintiff. We agree with Special Term that the failure of defendant to make the periodic payments due under the contract constituted a breach entitling plaintiff to regard the contract as terminated (Anderson v. Mayes Gonstr. Go., 243 N. Y. 140, 149-150; 10 N. Y. Jur., Contracts, § 384). However, we do not believe that the fact that the contract calls for periodic payments limits plaintiff to recovering the balance due under the contract. We consider it well-settled law that a plaintiff has the right of electing, on the breach of a contract, to maintain an action on the contract for the work performed and the material supplied and for the damage flowing from the failure of the defendant to permit him to complete the contract, or, as in the case at bar, to abandon any claim on or under the contract and to sue for quantum meruit for the work, labor and services and materials furnished (Balle v. Peerless Amer. Prods. Co., 192 App. Div. 506; Atlantic, Gulf & Pacific Go. v. Woodmere Realty Go., 156 App. Div. 351). Having elected to sue in equity, for recission, plaintiff has waived its right to a jury trial on the assessment in quantum meruit. Plaintiff is entitled to recover in quantum meruit. However, defendant may plead a counterclaim for liquidated damages for the alleged delay in the performance by plaintiff prior to defendant’s breach so as to reduce the final award to plaintiff if defendant can establish its right to such liquidated damages (CPLR 3019, subd. [a]). Hopkins, Acting P. J., Shapiro, Christ and Brennan, JJ., concur; Benjamin, J., dissents in part and votes to modify the order by striking the third decretal paragraph thereof and substituting therefor a provision granting plaintiff summary judgment for the reasonable value, of the work done by plaintiff, but limited proportionately to the total contract price and less the total of the payments made, with the following memorandum: Plaintiff and defendant entered into a written agreement whereby plaintiff agreed to furnish all labor, plant, materials, etc., for the construction of a sewer trunk system for the defendant town. The contract provided for periodic payments as the work progressed, contained prices for each unit of various items or categories of work, and provided for such payment as would be agreed upon for any additional or extra work. The payments were to be made not later than the 15th day of each month, “on the basis of a duly certified approved Engineer’s Estimate of the work performed during the preceding calendar month by the Contractor ”, with the usual 10% retained by the town until final completion. In October, 1972 plaintiff did not receive the engineer’s certification for the amount approved for payment of the work performed to the end of September, 1972. On October 6, 1972 defendant informed plaintiff that it lacked sufficient funds with which to make further payments. On October 20, 1972 plaintiff notified defendant that the latter’s inability to pay was a material breach and that plaintiff considered the contract terminated and rescinded. At the time plaintiff suspended performance it would have been entitled to a further payment from defendant of about $75,000 for the work performed during September, 1972. Further, defendant had retained approximately $130,000 from previous monthly payments. Thus, the maximum due under the contract for work done at the time performance was suspended was $205,-[865]*865000. Plaintiff sought recovery upon the theory of quantum meruit, claiming the reasonable value of the work performed until the breach to be $1,976,975, less $1,163,686 (moneys previously paid to plaintiff), resulting in a claimed net sum due of $813,289. Thus, by employing a quantum meruit theory of recovery, plaintiff sought to gain a net surplusage over the payments due pursuant to the contract of $608,289. It is contended that the unilateral termination of the contract by the municipality permits such a windfall. I agree that the law permits plaintiff to abandon the contract and seek recovery in quantum meruit under the circumstances here involved (Clark v. Mayor, etc., of City of New York, 4 N Y. 338). I do not read that case, however, as supporting a “ penalty ” recovery. In Clark, the contract provided for 150,000 cubic yards of earth to be excavated at the unit price of $1 a yard. After some 68,000 yards of earth had been excavated, the governmental authority, just as in the case at bar, decided not to go forward with the remaining portion of the contract. The issue, therefore, was whether Clark was entitled to $1 per yard for the some 68,000 yards, plus whatever profit he might have made had the contract been completed so that he might he made whole in damages for the breach by the defendant, or whether he had the right to deem the contract terminated and rescinded and recover in quantum meruit the actual reasonable value of the work completed at the time of the contract’s termination. The evidence there supported a finding that the geological character of the premises excavated was such that the reasonable value of the some 68,000 yards excavated, largely rock, was substantially more than the base unit price of $1 per yard; and the Court of Appeals held that Clark had the right to recover in quantum meruit such actual reasonable value, rather than to rely upon the ordinary contract damages of the amount specified in the contract, less the reasonable cost of completion. The effect of this decision, therefore, was merely to decree as an elective remedy a determination of the value of the work done as against the total contract and to make plaintiff whole for the value of the work done. It is clear that such an apportionment is appropriate. A hypothetical builder who takes a contract for $50,000 to build a house and brings it to enclosure, at which point the owner decides to abandon it, certainly should have the right to recover the $50,000, less what it would have cost him to finish the job so that his profit under the job would thus be preserved to him. The proof, however, in such a situation might be onorous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PAS Technology Services, Inc. v. Middle Village Healthcare Management, LLC
92 A.D.3d 742 (Appellate Division of the Supreme Court of New York, 2012)
Mike Building & Contracting, Inc. v. Just Homes, LLC
27 Misc. 3d 833 (New York Supreme Court, 2010)
Martin Iron & Construction Co. v. Grace Industries, Inc.
14 A.D.3d 495 (Appellate Division of the Supreme Court of New York, 2005)
Bat-Jac Contracting, Inc. v. Amagansett Fire District
294 A.D.2d 455 (Appellate Division of the Supreme Court of New York, 2002)
Brown v. Stone
66 F. Supp. 2d 412 (E.D. New York, 1999)
Bausch & Lomb Inc. v. Bressler
977 F.2d 720 (Second Circuit, 1992)
Bausch & Lomb Incorporated v. Bernard Bressler
977 F.2d 720 (Second Circuit, 1992)
Laberge Engineering & Consulting Group, Ltd. v. Mayer
184 A.D.2d 950 (Appellate Division of the Supreme Court of New York, 1992)
Rich Associates, Inc. v. Verimun Construction Associates, Inc.
148 A.D.2d 599 (Appellate Division of the Supreme Court of New York, 1989)
Anthony L. Castiglia, Inc. v. City of Lockport
85 A.D.2d 879 (Appellate Division of the Supreme Court of New York, 1981)
Carvatt v. Lippner
82 A.D.2d 818 (Appellate Division of the Supreme Court of New York, 1981)
Beaumont Birch Co. v. Najjar Industries, Inc.
477 F. Supp. 970 (S.D. New York, 1979)
Geller v. Julien
52 A.D.2d 808 (Appellate Division of the Supreme Court of New York, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
43 A.D.2d 863, 351 N.Y.S.2d 445, 1974 N.Y. App. Div. LEXIS 5875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paterno-sons-inc-v-town-of-new-windsor-nyappdiv-1974.