This text of 85 A.D.2d 879 (Anthony L. Castiglia, Inc. v. City of Lockport) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony L. Castiglia, Inc. v. City of Lockport, 85 A.D.2d 879 (N.Y. Ct. App. 1981).

Opinion

Judgment unanimously modified and, as modified, affirmed, without costs, in accordance with the following memorandum: The decision for plaintiff, in its action to recover payment for materials and services provided defendant in the construction of a municipal parking garage, is supported by sufficient proof in the record. Since defendant breached the contract when it unjustifiably prevented completion, plaintiff could recover in quantum, meruit for work done (Paterno & Sons v Town of New Windsor, 43 AD2d 863). In calculating the damages, however, defendant should have been given credit for excavation payments already made, and should not have been required to pay overhead and profit on general payments retained by it under the contract, as the retainage already reflected such amounts. Therefore, judgment is modified to the sum of $283,608.51: (1) 3,600 cubic yards of garbage excavation at $1.01 per cubic yard, plus 5% overhead and 10% profit, for a total of $4,199.58; (2) 7,000 cubic yards of gravel fill, compaction and testing at $5.40 per cubic yard, plus 5% overhead and 10% profit, for a total of $43,659; (3) 883 cubic yards of rock excavation at $62.48 per yard, less credit for $4,710 already paid, for a total of $50,459.84; (4) interest on the total of the preceding three figures from [880]*880December 25, 1975 in the amount of $28,492.65; (5) expenses incurred after December 25, 1975 as calculated by the court, less retainage, plus 5% overhead and 10% profit for a total of $86,147.68; (6) retainage in the amount of $36,850, and (7) interest on the total of the preceding three sums from April 1, 1976 in the amount of $33,799.76. (Appeal from judgment of Niagara Supreme Court, Wolf, J. — breach of construction contract.) Present — Dillon, P. J., Hancock, Jr., Callahan, Doerr and Moule, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK
Appellate Division of the Supreme Court of New York, 2011
Crane-Hogan Structural System, Inc. v. State
88 A.D.3d 1258 (Appellate Division of the Supreme Court of New York, 2011)

Cite This Page — Counsel Stack