CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK

Appellate Division of the Supreme Court of the State of New York·Decided October 7, 2011·No. CA 10-02278·Published

Opinion

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department

913 CA 10-02278 PRESENT: CENTRA, J.P., PERADOTTO, CARNI, GREEN, AND GORSKI, JJ.

CRANE-HOGAN STRUCTURAL SYSTEMS, INC., CLAIMANT-RESPONDENT,

V MEMORANDUM AND ORDER

STATE OF NEW YORK, DEFENDANT-APPELLANT. (CLAIM NO. 110250.)

ERIC T. SCHNEIDERMAN, ATTORNEY GENERAL, ALBANY (OWEN DEMUTH OF COUNSEL), FOR DEFENDANT-APPELLANT.

GATES & ADAMS, P.C., ROCHESTER (ANTHONY J. ADAMS, JR., OF COUNSEL), FOR CLAIMANT-RESPONDENT.

Appeal from a judgment of the Court of Claims (Philip J. Patti, J.), entered August 12, 2010. The judgment awarded claimant money damages for breach of contract, after a trial.

It is hereby ORDERED that the judgment so appealed from is unanimously modified on the law by reducing the award of $1,399,589.87 to $489,992.24 and as modified the judgment is affirmed without costs.

Memorandum: Claimant commenced this action seeking damages for defendant’s breach of a construction contract. Defendant contracted with claimant to rehabilitate the Veterans Memorial Bridge in Rochester for the sum of $18,535,215.42. The project involved partial removal and repair of the bridge deck and supporting beams and was to be completed by September 30, 1999. While the work was underway, the parties discovered that the bridge was in greater disrepair than the plans had reflected, and defendant halted construction in approximately May 1998. Thereafter, defendant issued new plans calling for, inter alia, the complete removal and replacement of the bridge deck, shoring of the bridge deck and removal and replacement of bridge beams. The new plans required additional labor and equipment and extended the construction time frame from 2½ years to 4½ years.

While the parties negotiated claimant’s compensation for the additional work, claimant agreed to proceed by “force account,” i.e., on a time and materials basis, pursuant to the Standard Specifications of the Department of Transportation (Standard Specifications). The Standard Specifications provided that, “[w]here there are no applicable unit prices for extra work ordered and agreed prices cannot be readily established or substantiated, the [c]ontractor shall be paid the actual and reasonable cost” of necessary materials, labor,

CA 10-02278

payroll taxes and insurance payments, sales tax, equipment, profit and overhead. The force account method required claimant to complete detailed forms listing labor, equipment and materials used on a daily, weekly and monthly basis. Claimant submitted proposed unit pricing to defendant in 1998 and 1999 but received no response, and claimant was ultimately advised that defendant had decided not to consider unit pricing for the additional work. As a result, the work proceeded entirely according to the force account method, with claimant reserving its right to seek additional compensation from defendant.

After claimant had completed the project and defendant had accepted the work on March 11, 2002, claimant sought additional compensation from defendant in the amount of $2,203,058.75, which included $693,314.56 in project or field overhead and $964,937.60 in corporate or home office overhead. According to claimant, 63.5% of those overhead costs were incurred completing work set forth in the original contract (hereafter, contract work), while 36.5% of those costs were incurred performing force account work, which is the subject of this action. In response to claimant’s request, defendant issued a change order or “order on contract” in the amount of $612,400.58 for “time related dispute compensation,” i.e., compensation for costs incurred beyond the expected contract completion date. That amount included $450,265 or 63.5% of the amount claimant sought for project overhead, representing the portion of the project overhead claim allocable to the contract work. Defendant refused to pay the remaining 36.5% of the claim attributable to force account work. Defendant also paid claimant $45,026.50 in corporate overhead, i.e., 10% of the amount that it awarded in project overhead, as well as $49,529.15 in profit, i.e., 10% of the amounts awarded for project and corporate overhead, based upon the Standard Specifications.

Claimant thereafter commenced this action seeking damages in the amount of $1,432,624.65, plus interest, for corporate overhead, project overhead, standby equipment and underutilized equipment. According to claimant, the project redesign “constitut[ed] a cardinal change to [its] contract” and, as a result, it “incurred significant additional costs for which it was not compensated, including additional labor, equipment and overhead[,] as well as lost profits.” Claimant subsequently prepared a statement of damages in which it reduced the amount of damages sought to $1,367,795.54.

We note at the outset that defendant does not challenge the Court of Claims’ determination that the redesigned project constituted a cardinal change to the contract or that quantum meruit is the proper measure of damages. Rather, defendant’s sole contention is that the damages award of $1,399,589.87 with interest should be reduced. The court determined that claimant incurred “uncompensated costs” for home office overhead in the amount of $834,493.35, for project overhead in the amount of $189,909.46, for standby equipment in the amount of $63,242 and for underutilized equipment in the amount of $122,445, for a total amount of $1,210,089.81. In addition, the court determined that claimant was entitled to a “ ‘markup’ ” for overhead and profit in the amount of 15.66% of the uncompensated costs or $189,500.06.

CA 10-02278

“ ‘On our review of a verdict after a bench trial, we independently review the weight of the evidence and may grant the judgment warranted by the record’ ” (Charles T. Driscoll Masonry Restoration Co., Inc. v County of Ulster, 40 AD3d 1289, 1291; see Evans-Freke v Showcase Contr. Corp., 85 AD3d 961, 962-963). As in any contract action, claimant bears the burden of establishing its damages (see Manshul Constr. Corp. v Dormitory Auth. of State of N.Y., 79 AD2d 383, 387), and “damages are limited to awards based upon ‘a definite and logical connection between what is proven and the damages sought to be recovered’ ” (Clifford R. Gray, Inc. v State of New York, 251 AD2d 728, 730). In construction contract cases, “[t]he customary method of calculating damages on a quantum meruit basis . . . is actual job costs plus an allowance for overhead and profits minus amounts paid” (Najjar Indus. v City of New York, 87 AD2d 329, 331-332, affd 68 NY2d 943; see Whitmyer Bros. v State of New York, 47 NY2d 960, 962, affg 63 AD2d 103; Miranco Contr., Inc. v Perel, 57 AD3d 956, 958).

Free access — add to your briefcase to read the full text and ask questions with AI

CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK, (N.Y. Ct. App. 2011).

CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK (CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Whitmyer Bros., Inc. v. State
393 N.E.2d 1027 (New York Court of Appeals, 1979)
Najjar Industries, Inc. v. City of New York
502 N.E.2d 997 (New York Court of Appeals, 1986)
Precision Foundations v. Ives
4 A.D.3d 589 (Appellate Division of the Supreme Court of New York, 2004)
Charles T. Driscoll Masonry Restoration Co. v. County of Ulster
40 A.D.3d 1289 (Appellate Division of the Supreme Court of New York, 2007)
Pozament Corp. v. AES Westover, LLC
51 A.D.3d 1080 (Appellate Division of the Supreme Court of New York, 2008)
Miranco Contracting, Inc. v. Perel
57 A.D.3d 956 (Appellate Division of the Supreme Court of New York, 2008)
Evans-Freke v. Showcase Contracting Corp.
85 A.D.3d 961 (Appellate Division of the Supreme Court of New York, 2011)
Whitmyer Bros., Inc. v. State
63 A.D.2d 103 (Appellate Division of the Supreme Court of New York, 1978)
Manshul Construction Corp. v. Dormitory Authority
79 A.D.2d 383 (Appellate Division of the Supreme Court of New York, 1981)
Anthony L. Castiglia, Inc. v. City of Lockport
85 A.D.2d 879 (Appellate Division of the Supreme Court of New York, 1981)
Najjar Industries, Inc. v. City of New York
87 A.D.2d 329 (Appellate Division of the Supreme Court of New York, 1982)
Ciesinski v. Town of Aurora
202 A.D.2d 984 (Appellate Division of the Supreme Court of New York, 1994)
Clifford R. Gray, Inc. v. State
251 A.D.2d 728 (Appellate Division of the Supreme Court of New York, 1998)