Manshul Construction Corp. v. Dormitory Authority

79 A.D.2d 383, 436 N.Y.S.2d 724, 1981 N.Y. App. Div. LEXIS 9718
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 10, 1981
StatusPublished
Cited by36 cases

This text of 79 A.D.2d 383 (Manshul Construction Corp. v. Dormitory Authority) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manshul Construction Corp. v. Dormitory Authority, 79 A.D.2d 383, 436 N.Y.S.2d 724, 1981 N.Y. App. Div. LEXIS 9718 (N.Y. Ct. App. 1981).

Opinion

OPINION OF THE COURT

Silverman, J.

This action arises out of a construction contract whereby plaintiff Manshul Construction Corp. contracted to do certain work for defendant Dormitory Authority of the State of New York (DASNY) in connection with La Guardia Community College, a division of the City University of New York.

Plaintiff’s complaint had three causes of action—the first for balance due under the contract, the second for reasonable value of extra, changed and/or additional work, and the third for damages essentially for delay due to defendant’s failure to provide adequate access to the job site, proper information, proper drawings and plans, failure to co-ordinate the work of other contractors, etc. Defendant counterclaimed for delay damages and for fair and reasonable value of work not performed by plaintiff, and work deleted from the contract.

After a six-week non jury trial in which the court painstakingly went into the many claims, the court awarded plaintiff $259,754 on the first cause of action, being essentially full recovery on that cause of action; $212,149 on the second cause of action; and $160,639 on the third cause of action; and the court allowed to defendant a credit of $105,750 on its counterclaim for work deleted or not per[385]*385formed, said credit being applied against the award to plaintiff on the second cause of action. In addition, pursuant to a stipulation of partial settlement, the judgment awarded to plaintiff recovery on various items of extra work in stipulated amounts.

Both parties have appealed from the judgment. The issues on this appeal relate essentially to interest, and to the third cause of action for delay damages.

(1) Interest on credits to defendant. The trial court awarded to plaintiff sums of money on its first cause of action for contract balance, on its second cause of action for extras, and on its third cause of action for damages for delay, in each case with interest to the date of the decision. The court also awarded to defendant $105,750.91 for credits due for work deleted or not performed, but no predecision interest was awarded on this item. In the judgment, this $105,750.91 without interest, was simply subtracted from the total of $768,809.42 (which included predecision interest) awarded to plaintiff, and a net award was made to plaintiff of the difference, $663,058.51, together with interest from the date of decision. But the correct net amount actually owed by defendant to plaintiff is of course only the gross amount of plaintiff’s claim, as allowed, minus the credits allowed to defendant; and predecision interest should be allowed to plaintiff only on that net amount. The credits for work deleted or unperformed would seem logically most closely related to the amount allowed to plaintiff on the first cause of action as contract balance due. Indeed the contract provides that where changes are made altering, adding to or deducting from the work, the contract sum shall be adjusted accordingly. We therefore direct that the $105,750.91 credited to defendant be applied against the $259,754.29 awarded to plaintiff on its first cause of action, and that predecision interest on the first cause of action be allowed only on the net balance of $154,003.38.

(2) Rate of prejudgment and predecision interest. Chapter 585 of the Laws of 1939 provides that the rate of interest to be paid by a “public corporation” upon “any judgment or accrued claim” shall not exceed 4 % per annum. The trial court agreed that defendant is a public corporation, and therefore allowed only 4% per annum as postjudgment [386]*386interest rather than 6% per annum. But prejudgment interest has been calculated at 6%. We hold that prejudgment interest must also be calculated at 4% per annum. The statute is applicable not only to judgments but to “accrued” claims. The prejudgment interest awarded was for the most part from dates after the completion of the work and just about the commencement of the action, thus the claims could fairly be deemed accrued as of those dates. The most likely significance of the use of the phrase “accrued claim” in the statute is to avoid an interpretation that interest is payable on nonaccrued claims. In any event, it would not make sense for the statute to be interpreted to mean that a 4% rate of interest should be applicable for the period after the claims are established but a higher rate of interest should be charged for the period before the claims are established and while they are still disputed.

(3) The Cord-Wall—dry wall subcontractor claim. Paragraph (mm) of the judgment allows $13,681, with interest thereon, to Manshul, purportedly on account of its third cause of action for delay relating to the dry wall subcontractor. In fact, it is clear that this figure represents the amount of work that the dry wall subcontractor alleged that it had done that was extra to the contract. Concededly, there was no claim by the dry wall subcontractor directly for extra work. Insofar as such extra work was claimed to have been done by the dry wall subcontractor and allowed by the court, it was included in other direct claims allowed by the court for extras, e.g., items (p) and (ff) of the judgment, and thus its allowance represents a duplication of those items. The court appears to have found (p) and (ff) to be well documented whereas, the amount in (mm), though a larger sum than items (p) and (ff), was merely the amount that the subcontractor estimated as the value of its extra work. As plaintiff has the burden of proof, we accept the documented claims in items (p) and (ff) and we strike item (mm). As to the subcontractor’s claim for delay, the trial court thought it was “grossly exaggerated”, speculative and not supported by the preponderance of the credible evidence. We agree. There was no showing that the delays suffered by the subcontractor were the defendant’s responsibility.

[387]*387(4) Damages for delay. The third cause of action claims damages for breach of contract, including damages for delay.

On this cause of action, the court awarded:

(i) $143,325 overhead and profits as delay damages (item [kk] of the judgment).

(ii) $3,633 in connection with the claim of the door manufacturer (item [11] of the judgment).

(iii) $13,681 relating to the dry wall subcontractor (item [mm] of the judgment).

The last of these items has been discussed and stricken above.

The second item is apparently not questioned by the parties and will not be discussed further by us.

We shall discuss primarily the first item, including plaintiff’s claim that the award should have been much larger and defendant’s claim that it should have been much smaller or nothing.

As in all contract actions, the burden of proving the damages is on plaintiff. (Berley Inds. v City of New York, 45 NY2d 683, 686.) When claims are made for damages for delay, plaintiff must show that defendant was responsible for the delay; that these delays caused delay in completion of the contract (eliminating overlapping or duplication of delays); that the plaintiff suffered damages as a result of these delays; and plaintiff must furnish some rational basis for the court to estimate those damages, although obviously a precise measure is neither possible nor required. (Rusciano Constr. Corp. v State of New York, 37 AD 2d 745; Bero Constr. Corp. v State of New York, 27 AD2d 974; Tully & DiNapoli v State of New York,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henick-Lane, Inc. v. 616 First Ave. LLC
2024 NY Slip Op 34283(U) (New York Supreme Court, New York County, 2024)
Hudson Meridian Constr. Group LLC v. Bayport Constr. Corp.
2024 NY Slip Op 03383 (Appellate Division of the Supreme Court of New York, 2024)
Five Star Elec. Corp. v. A.J. Pegno Constr. Co., Inc./Tully Constr. Co., Inc.
198 N.Y.S.3d 340 (Appellate Division of the Supreme Court of New York, 2023)
LPCiminelli, Inc. v. JPW Structural Contr., Inc.
2023 NY Slip Op 03112 (Appellate Division of the Supreme Court of New York, 2023)
Iannucci v. Kucker & Bruh, LLP
2018 NY Slip Op 3514 (Appellate Division of the Supreme Court of New York, 2018)
Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority
89 A.D.3d 819 (Appellate Division of the Supreme Court of New York, 2011)
CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK
Appellate Division of the Supreme Court of New York, 2011
Crane-Hogan Structural System, Inc. v. State
88 A.D.3d 1258 (Appellate Division of the Supreme Court of New York, 2011)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Metropolitan Steel Industries, Inc. v. Perini Corp.
36 A.D.3d 568 (Appellate Division of the Supreme Court of New York, 2007)
City of New York v. State
27 A.D.3d 1 (Appellate Division of the Supreme Court of New York, 2005)
Aniero Concrete Co. v. New York City Construction Authority
308 F. Supp. 2d 164 (S.D. New York, 2003)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
In Re Regional Building Systems, Inc.
273 B.R. 423 (D. Maryland, 2001)
Binghamton Precast & Supply v. A. Servidone, Inc./B. Anthony Construction Corp.
257 A.D.2d 731 (Appellate Division of the Supreme Court of New York, 1999)
G & A Moving & Storage Co. v. Computer Associates International, Inc.
233 A.D.2d 479 (Appellate Division of the Supreme Court of New York, 1996)
Indu Craft, Inc. v. Bank Of Baroda
87 F.3d 614 (Second Circuit, 1996)
Weinreich v. Sandhaus
850 F. Supp. 1169 (S.D. New York, 1994)
Mid-State Precast Systems, Inc. v. Corbetta Construction Co.
202 A.D.2d 702 (Appellate Division of the Supreme Court of New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
79 A.D.2d 383, 436 N.Y.S.2d 724, 1981 N.Y. App. Div. LEXIS 9718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manshul-construction-corp-v-dormitory-authority-nyappdiv-1981.