Fehlhaber Corp. & Horn Construction Co. v. State

69 A.D.2d 362, 419 N.Y.S.2d 773, 1979 N.Y. App. Div. LEXIS 11818
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 26, 1979
DocketClaim No. 54855
StatusPublished
Cited by27 cases

This text of 69 A.D.2d 362 (Fehlhaber Corp. & Horn Construction Co. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fehlhaber Corp. & Horn Construction Co. v. State, 69 A.D.2d 362, 419 N.Y.S.2d 773, 1979 N.Y. App. Div. LEXIS 11818 (N.Y. Ct. App. 1979).

Opinion

OPINION OF THE COURT

Mahoney, P. J.

Claimant Fehlhaber Corporation and Horn Construction Co., Inc., a joint venture, contracted with the State of New York on February 6, 1967 for the construction of the founda[367]*367tion of the Cultural Center of the Empire State Plaza.1 The completion date was December 31, 1968. When the job was unfinished on that date and for a period of approximately two and one-half years thereafter, the contract was terminated "not for cause” by the State as of July 1, 1971. Immediately prior to the termination date, on May 26, 1971, claimant had made a request that the retainage held by the State be released and that a final payment estimate be prepared. On March 27, 1972 a claim alleging that delays caused by the State resulted in damages of $4,398,380.74 was filed. Fehlhaber also claimed retainage money in the sum of $306,720.74. Thereafter, the State’s motion to serve and file a counterclaim of $2,853,636.84 was denied and trial began on November 3, 1976. At the conclusion of the trial, Fehlhaber moved to sever the retainage claim and for partial summary judgment thereon. The State opposed the motion, asserting a right to set off the value of remedial work required on the cultural center foundation against the retainage. The trial court granted claimant’s motion and judgment was entered for the amount of the retainage. On appeal from that judgment, this court, on June 1, 1978, reversed and remanded for a full trial on all issues, including the State’s counterclaim (Fehlhaber Corp. v State of New York, 63 AD2d 1038). When we made that determination, no appeal from a final judgment in claimant’s breach of contract action against the State was before us. On November 4, 1977, the trial court awarded claimant damages against the State. By order to show cause, claimant moved to correct the trial court’s decision, alleging that it had erred in its mathematical calculation. The decision was amended as of December 13, 1977 increasing the award to $2,746,747.37. Fehlhaber then moved for reargument of our decision reversing the denial of the State’s attempt to assert a counterclaim (63 AD2d 1038, supra) and remanding the matter for a new trial on all issues, and the State appealed from the judgment entered December 13, 1977 on the breach of contract action. We granted claimant’s motion for reargument and heard the same in connection with the State’s appeal from the final judgment below.

APPEAL FROM THE FINAL JUDGMENT

Claimant alleged that interference on the part of the State [368]*368resulted in extraordinary delay, specifically, that the State failed to construct a permanent roadway structure at the site causing delay in construction of the foundation, that the State made constant revisions in the contract drawings, and that the State failed to timely award the superstructure contract. As a consequence, claimant alleged that it was damaged in that it had to incur excessive costs in performing the work. The trial court found delay and interference on the part of the State, and, by amended decision, awarded damages in the sum of $3,265,412.99, which it apportioned 75% against the State, 25% against claimant, resulting in an award of $2,449,059.74 for excess cost of performing the work.

The State contends that the trial court improperly used the total cost theory of damages. We disagree. We have held that where a claimant does not seek damages in an amount by which its estimated costs plus overhead and profit exceed its bid, but, rather, by setting forth actual costs, together with any allowance for overhead and profit without regard to bid figures, we would sanction that theory of damages (Fehlhaber Corp. v State of New York, 65 AD2d 119; D'Angelo v State of New York, 41 AD2d 77, 80; Westcott v State of New York, 264 App Div 463, 464). Here, Fehlhaber’s records were kept on a daily basis and meticulously recorded the number of men and machines on the job each day as well as the type of work being done on each day. To these base costs2 Fehlhaber added amounts for overhead, profit and [369]*369equipment for the period from December 31, 1968 (contract termination date) to July 1, 1971 (the date the contract was terminated "not for cause”). The State audited claimant’s books and records, but never offered its findings as rebuttal evidence. We have previously held that a trial court is justified in crediting oral testimony of a claimant in the absence of any rebuttal by the State with its vast reservoir of engineering and construction experience (D’Angelo v State of New York, 46 AD2d 893, affd 39 NY2d 781; cf. Johnson v State of New York, 5 AD2d 919). We conclude likewise on these facts and hold that claimant has proved its claim by a fair preponderance of the evidence (Fehlhaber Corp. v State of New York, 65 AD2d 119, supra), and we are foreclosed from disturbing such findings on this record (Merritt-Chapman & Scott Corp. v State of New York, 54 AD2d 37, 40, affd 43 NY2d 690). However, claimant’s base costs occasioned by the State’s interference with its contract performance, particularized in footnote 2 of this opinion, must be modified as hereinafter explained.

I

HOME OFFICE OVERHEAD

The State is in error in relying on Berley Inds. v City of New York (45 NY2d 683) to support its position that claimant should not be awarded home office overhead, since that case calls into play the so-called "Eichleay Formula” to determine the amount of home office overhead to be included in arriving at a contractor’s delay damages only in those instances where it can be shown that delay was not precipitated by design or engineering problems that call for central staff consideration during the overrun period. It is clear that the trial court held that the main cause of the State’s interference resulted from multiple design changes, and these multiple design changes unmistakably required central staff consideration. The record, however, is barren of any explanation or breakdown of this item, and we conclude that we cannot credit such an arbitrary sum as additional costs.

II

REPAIRS AND MAINTENANCE

Next, while we accept claimant’s right to charge the fair and reasonable rental value of owned equipment (Fehlha[370]*370ber Corp. v State of New York, 65 AD2d 119, 128, supra), the Associated Equipment Dealer’s Manual (AED) employed by claimant to arrive at the charged rental rates explains the general industry practice that all costs of equipment repair not due to normal wear and tear are the responsibility of the lessee. The record reveals no evidence by claimant indicating what part of the $43,271.38 claimed for repairs and maintenance was for costs which would be claimant’s responsibility under the AED guidelines. "It is fundamental to the law of damages that one complaining of injury has the burden of proving the extent of the harm suffered” (Berley Inds. v City of New York, supra, p 686). The burden of providing information on cost allocation for equipment and cost of repairs to same is on the claimant (Bero Constr. Corp. v State of New York, 27 AD2d 974) and, where, as here, a contractor wrongfully delayed fails to establish the extent to which its costs were increased by compensable repairs and maintenance, speculation will not be indulged and damages will be limited to damages actually proven.

III

INCREASED STEEL COSTS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shapiro v. State of New York
2025 NY Slip Op 51245(U) (New York State Court of Claims, 2025)
Shelton v. New York State Liquor Authority
61 A.D.3d 1145 (Appellate Division of the Supreme Court of New York, 2009)
Hanover Insurance v. Alisa Construction Co.
14 Misc. 3d 864 (New York Supreme Court, 2007)
Aniero Concrete Co. v. New York City Construction Authority
308 F. Supp. 2d 164 (S.D. New York, 2003)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
F.W. Sims, Inc. v. T. Moriarty & Son, Inc.
265 A.D.2d 234 (Appellate Division of the Supreme Court of New York, 1999)
Brown v. Stone
66 F. Supp. 2d 412 (E.D. New York, 1999)
John B. Pike & Son, Inc. v. State
169 Misc. 2d 1037 (New York State Court of Claims, 1996)
AEL Industries, Inc. v. Loral Fairchild Corp.
882 F. Supp. 1477 (E.D. Pennsylvania, 1995)
Port Chester Electrical Construction Corp. v. HBE Corp.
782 F. Supp. 837 (S.D. New York, 1991)
Efdey Electrical Contractors, Inc. v. Melita
167 A.D.2d 501 (Appellate Division of the Supreme Court of New York, 1990)
Sharp Bros. Contracting Co. v. American Hoist & Derrick Co.
703 S.W.2d 901 (Supreme Court of Missouri, 1986)
Port Chester Electrical Co. v. State of New York
103 A.D.2d 825 (Appellate Division of the Supreme Court of New York, 1984)
City of Clayton v. Grumman Emer. Prod.
576 F. Supp. 1122 (E.D. Missouri, 1983)
Ames Contracting Co. v. City University
120 Misc. 2d 358 (New York State Court of Claims, 1983)
Wikarski v. State
91 A.D.2d 1174 (Appellate Division of the Supreme Court of New York, 1983)
Zimmerman v. State
116 Misc. 2d 521 (New York State Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
69 A.D.2d 362, 419 N.Y.S.2d 773, 1979 N.Y. App. Div. LEXIS 11818, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fehlhaber-corp-horn-construction-co-v-state-nyappdiv-1979.