John B. Pike & Son, Inc. v. State

169 Misc. 2d 1037, 647 N.Y.S.2d 654, 1996 N.Y. Misc. LEXIS 341
New York Court of Claims·Decided July 1, 1996·No. Claim No. 70979·Published·Cited by 2 cases

Opinion

OPINION OF THE COURT

Louis C. Benza, J.

This matter was remitted to the Court of Claims for determination of damages on two causes of action (Pike & Son v State of New York, 212 AD2d 963).

Prior to analyzing the damages in the first cause of action, this court notes its perception of what constitutes that part of the record limiting or setting the parameters for such analysis.

The lower court dismissed claimant’s first cause of action based on claimant’s failure of proof that the extra work was done under State directive. "In the present case, while the State did order extra work (meaning the direction that the claimant complete by whatever means necessary holes abutting obstructed holes) what the contractor and its subcontractor did here was not that extra work. Rather, they unilaterally adopted a different methodology to install the drains by preaugering all holes. While this method resulted in some still obstructed drains as well as completed drains, it did not change in any way the basis of payment under which the State contracted. That was a per-linear-foot basis. While we have no doubt that this preaugering method was more expensive for the contractor and the subcontractor, the State was not obligated to pay those costs under those circumstances established at bar” (Ct Cl, Nov. 18, 1993, Margolis, J., claim No. 70979, slip opn, at 10-11).

After dismissing the claimant’s first cause of action on the above-stated basis, Judge Margolis stated in dicta: "In sum, the settlement agreement between claimant and its subcontractor does not provide a separate defense to the defendant for claimant’s first and second causes of action. Nevertheless, defendant is entitled to a judgment dismissing those causes of action” (supra, at 19).

[1039] Although the lower court addressed the State’s contention for dismissal of claimant’s claim for damages sustained by its subcontractor Vibroflotation for failure to prove the existence of a liquidation agreement between claimant and its subcontractor, it never addressed the issue as to whether claimant’s settlement agreement with Vibroflotation limited claimant’s damages for Vibroflotation’s extra work costs to restitution of the amount paid in the settlement agreement. Although the Appellate Division reversed the lower court and found liability against the State on the first cause of action, and found to be without merit the State’s contention that the failure of a liquidation agreement barred claimant from recovery, the decision did not address the above-stated issue as to whether claimant’s recovery is limited to restitution based on the general release.

Absent any other theory of recovery recognized in law, claimant, in its action against defendant for losses sustained by Vibroflotation, is limited, upon proof at trial, to its out-of-pocket costs as established by the settlement agreement entered into evidence by claimant as exhibit 66 (First Natl. Bank v Fourth Natl. Bank, 77 NY 320, 328; City of New York v Selden, 255 F 317, 319).

The record clearly establishes that claimant is not suing defendant on behalf of Vibroflotation. Any recovery here benefits claimant and does not flow through it to the benefit of Vibroflotation. In this respect, the present case differs from the usual procedure adopted by principal contractors in obtaining damages for subcontractors resulting from extra work orders by owners (see, Ardsley Constr. Co. v Port of N. Y. Auth., 61 AD2d 953, 954 [1st Dept 1978]; Lambert Houses Redevelopment Co. v HRH Equity Corp., 117 AD2d 227, 230-231 [1st Dept 1986]; Fehlhaber Corp. & Horn Constr. Co. v State of New York, 69 AD2d 362, 370-371). Absent any liquidation agreement to bridge the gap in privity between subcontractors and owners (Lambert Houses Redevelopment Co. v HRH Equity Corp., supra, at 227-231), claimant cannot pursue Vibroflotation’s unliquidated damages for extra work against the defendant (City of New York v Selden, 255 F 317, supra; Ardsley Constr. Co. v Port of N. Y. Auth., 61 AD2d 953, supra). City of New York v Selden (supra, at 319) did recognize the right of the principal contractor to pursue the owner for subcontractor losses which were recognized and paid for by the principal contractor (Mars Assocs. v New York City Educ. Constr. Fund, 126 AD2d 178, 191, lv dismissed 70 NY2d 747; Degnon Contr. Co. v City of New York, 235 NY 481, 487).

[1040] In the instant case, claimant and Vibroflotation entered into an agreement to settle a lawsuit brought in the State Supreme Court by Vibroflotation against claimant for losses sustained by Vibroflotation under its subcontract. All of Vibroflotation’s claims were settled for $75,000. As part of the agreement, Vibroflotation assigned all claims arising from the contract to claimant. The agreement reads in pertinent part as follows: "4. Effective upon the payment referred to in Paragraph 1 of this Settlement Agreement, Vibroflotation hereby assigns, sells, and transfers to Pike without warranty, representation or recourse all of Vibroflotation’s rights and interests in and to any and all claims arising from the Project, asserted or unasserted, including all claims arising out of drilling in the area of the Project’s North Abutment, all claims arising out of drilling in the area of the Project’s South Abutment, and all claims arising out of the quantity of material installed. Vibroflotation agrees to cooperate with Pike and to make its files and personnel available to Pike to support Pike’s preparation and presentation of such claims against the State. Such availability will be upon reasonable notice and during customary business hours, and Pike shall reimburse Vibroflotation for its out-of-pocket costs incurred in connection therewith, including but not limited to, telephone, copying, postage, travel and hotel charges, plus a reasonable witness fee.” (Exhibit 66.)

Free access — add to your briefcase to read the full text and ask questions with AI

John B. Pike & Son, Inc. v. State, 169 Misc. 2d 1037, 647 N.Y.S.2d 654, 1996 N.Y. Misc. LEXIS 341 (N.Y. Super. Ct. 1996).

169 Misc. 2d 1037 (John B. Pike & Son, Inc. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

RAD & D'Aprile Inc. v. Arnell Construction Corp.
49 Misc. 3d 189 (New York Supreme Court, 2015)
Harrison & Burrowes Bridge Constructors, Inc. v. State
42 A.D.3d 779 (Appellate Division of the Supreme Court of New York, 2007)