Lambert Houses Redevelopment Co. v. HRH Equity Corp.

117 A.D.2d 227, 502 N.Y.S.2d 433, 1986 N.Y. App. Div. LEXIS 52477
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 20, 1986
StatusPublished
Cited by25 cases

This text of 117 A.D.2d 227 (Lambert Houses Redevelopment Co. v. HRH Equity Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lambert Houses Redevelopment Co. v. HRH Equity Corp., 117 A.D.2d 227, 502 N.Y.S.2d 433, 1986 N.Y. App. Div. LEXIS 52477 (N.Y. Ct. App. 1986).

Opinion

OPINION OF THE COURT

Asch, J.

Plaintiff Lambert Houses Redevelopment Company (Lambert) owns three Federally assisted low and moderate income housing projects located in the Bronx Park South Urban Renewal Area. The projects were constructed in the early 1970’s. The general contractor, defendant HRH Equity Corporation (HRH), subcontracted work to third-party defendants M.W.R. Construction Corporation, Wolkow-Braker Roofing Corp. and Prince Carpentry, Inc.

In 1977, following completion of the construction, Lambert commenced the instant action against HRH alleging breach of contract, negligence and breach of warranty pertaining to the mortar, masonry, roofing, insulation, waterproofing and stud walls.

HRH answered the complaint denying liability and commenced a third-party action against the subcontractors. The subcontractors impleaded (1) Glen-Gery Corporation, the masonry manufacturer; (2) Davis, Brody & Associates, the architect; and (3) GAF Corporation, the roofing material supplier.

In 1978, Lambert commenced a second action against M.W.R. and Glen-Gery regarding the construction. The two actions were subsequently consolidated.

The parties have since engaged in discovery proceedings which are not yet concluded.

On June 17, 1985, Lambert and HRH entered into a written agreement governing resolution of the claims made against HRH pertaining to work actually performed by the subcontractors. Lambert agreed that the claims alleged in the actions constitute all of its claims against HRH. The contractor admitted liability to Lambert for the claims asserted in the complaint and HRH’s liability was fixed and liquidated in such amounts as may be recovered against the third-party [230]*230defendants. In addition, HRH agreed to pay $375,000 to help defray the expenses of prosecuting the action.

HRH also agreed that it would move for permission to amend its answer and cross complaints so as to reflect the acknowledgment of liability for Lambert’s claims and to assert claims against the various defendants. The agreement was to become effective upon the issuance of the order granting the amendment. Pursuant to the agreement, HRH moved to interpose a second amended answer and an amended third-party complaint. The proposed answer admitted the allegations asserted in Lambert’s complaint and asserted the liquidated damages provision of the agreement as an affirmative defense.

The third-party complaint served by HRH in 1977 set forth the following allegations: As against M.W.R., Martin Rosen, Wolkow-Braker and Prince Carpentry, Inc., the contractor contended that it had no part in the actual performance of the alleged defective construction and no knowledge that M.W.R.’s work was not in accordance with the construction contracts. Alleging that the subcontractors breached their respective contracts in that they failed to perform in a skillful manner and in conformity with the construction contracts, HRH sought indemnification.

The proposed amended third-party complaint specifies that HRH admitted liability to Lambert and, under the terms of the subcontracts, the subcontractors are responsible to HRH for the damages that have been and will be sustained as a result of said defects in the subcontractors’ work.

Special Term denied HRH’s motion finding that the amended pleadings would prejudice the subcontractors at trial, citing Meleo v Rochester Gas & Elec. Corp. (72 AD2d 83). The court further held that the agreement between HRH and Lambert appeared to be an attempt to circumvent General Obligations Law § 15-108 (a) and would deprive the other defendants of their statutory right of setoff.

We disagree with the conclusions reached by Special Term and reverse to grant HRH’s motion to amend its pleadings.

The agreement herein is a standard form of liquidating agreement providing that all recovery will, in effect, pass through the general contractor to the injured party, thereby leaving the subcontractor and the owner to pursue their claims against each other.

Agreements liquidating the general contractor’s liability in [231]*231such amounts as can be recovered against the party who allegedly caused the injury have been uniformly upheld. (See, e.g., Ardsley Constr. Co. v Port of N. Y. Auth., 61 AD2d 953; Degnon Contr. Co. v City of New York, 235 NY 481, 487; Whitmyer Bros. v State of New York, 63 AD2d 103, 105, affd 47 NY2d 960.)

In Ardsley Constr. Co. (supra, p 954), an agreement between a general contractor and a subcontractor was upheld whereby the general contractor’s liability to a subcontractor was liquidated in the amount of "any monies that may be recovered from” the owner on account of the subcontractor’s claims. This court rejected the owner’s argument that the agreement was ineffective, explaining: "Such agreement between plaintiffs [the general contractor] and the subcontractor with respect to any recovery from defendant [the owner] affects only the relationship between plaintiffs and the subcontractor and should not be available to defendant as a shield against liability for breach of contract.” (61 AD2d, at p 954.) The court noted that suits based upon such agreements are routinely entertained in the Federal courts and concluded that they were permissible under New York law, as well.

The agreement between HRH and Lambert is identical in substance. It provides that HRH’s liability to Lambert is liquidated in the amount of any recovery from the other parties and that recovery by HRH on its claims against the other parties will be passed through to Lambert. In both cases the general contractor has liquidated its liability to the claiming party in such amounts as can be recovered from the other party. In both cases the liquidating agreement bridges the gap in privity between subcontractor and owner, allowing the general contractor to withdraw as an active participant.

There is no necessity for a liquidating agreement to include a release of the general contractor. There was no release in the agreement upheld in Ardsley (supra), nor do any of the other cited cases upholding liquidating agreements mention releases.

In fact, a release would be completely inconsistent with the aim and purpose of a liquidating agreement, which is not to release liability but rather to liquidate liability in whatever amounts can be recovered against the other parties. A release of the general contractor HRH would prevent the continued assertion of such claims between plaintiff Lambert and the subcontractors. The absence of such release is not an attempt [232]*232to circumvent General Obligations Law § 15-108 (a). In the absence of such agreement, HRH cannot recover from the subcontractors because the damage has been suffered by the owner, and the owner cannot recover from the subcontractors for breach of contract because it lacks privity of contract with the subcontractors. The agreement here, just as the liquidating agreement upheld in Ardsley (supra), permits the claim at issue to be litigated between owner and subcontractor.

The general purpose of General Obligations Law § 15-108 is to encourage settlements. (Rock v Reed-Prentice Div. of Package Mach. Co., 39 NY2d 34, 40-41.)

Section 15-108 provides:

"(a) Effect of release of or covenant not to sue tortfeasors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RAD & D'Aprile Inc. v. Arnell Construction Corp.
49 Misc. 3d 189 (New York Supreme Court, 2015)
I.T.R.I. Masonry Corp. v. State
21 A.D.3d 990 (Appellate Division of the Supreme Court of New York, 2005)
North Moore Street Developers, LLC v. Meltzer/Mandl Architects, P.C.
23 A.D.3d 27 (Appellate Division of the Supreme Court of New York, 2005)
Bovis Lend Lease LMB, Inc. v. GCT Venture, Inc.
285 A.D.2d 68 (Appellate Division of the Supreme Court of New York, 2001)
Perno v. For-Med Medical Group, P. C.
176 Misc. 2d 655 (New York Supreme Court, 1998)
Barry, Bette & Led Duke, Inc. v. State
240 A.D.2d 54 (Appellate Division of the Supreme Court of New York, 1998)
John B. Pike & Son, Inc. v. State
169 Misc. 2d 1037 (New York State Court of Claims, 1996)
Barry, Bette & Led Duke, Inc. v. State
169 Misc. 2d 594 (New York State Court of Claims, 1996)
City of Olean v. New York State Environmental Facilities Corp.
213 A.D.2d 1018 (Appellate Division of the Supreme Court of New York, 1995)
Morse/Diesel, Inc. v. Trinity Industries, Inc.
875 F. Supp. 165 (S.D. New York, 1994)
Schiavone Construction Co. v. Triborough Bridge & Tunnel Authority
209 A.D.2d 598 (Appellate Division of the Supreme Court of New York, 1994)
Hulse v. A.B. Dick Co.
162 Misc. 2d 263 (New York Supreme Court, 1994)
Solow Development Corp. v. Fentron Architectural Metals Corp.
194 A.D.2d 420 (Appellate Division of the Supreme Court of New York, 1993)
Gonzales v. Armac Industries, Ltd.
611 N.E.2d 261 (New York Court of Appeals, 1993)
Hubbell Electric, Inc. v. State
153 Misc. 2d 810 (New York State Court of Claims, 1992)
Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
Gonzalez v. Armac Industries, Ltd.
768 F. Supp. 107 (S.D. New York, 1991)
Andrulonis v. United States
924 F.2d 1210 (Second Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
117 A.D.2d 227, 502 N.Y.S.2d 433, 1986 N.Y. App. Div. LEXIS 52477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lambert-houses-redevelopment-co-v-hrh-equity-corp-nyappdiv-1986.