Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica

717 F. Supp. 1021, 1989 U.S. Dist. LEXIS 8378, 1989 WL 81346
CourtDistrict Court, S.D. New York
DecidedJuly 21, 1989
Docket86 Civ. 7980 (WCC)
StatusPublished
Cited by3 cases

This text of 717 F. Supp. 1021 (Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica, 717 F. Supp. 1021, 1989 U.S. Dist. LEXIS 8378, 1989 WL 81346 (S.D.N.Y. 1989).

Opinion

*1022 OPINION AND ORDER

WILLIAM C. CONNER, District Judge.

Respondent Alumina Partners of Jamaica (“Alpart”) brings this motion asserting that changed circumstances require my intervention in two arbitration proceedings pending before the American Arbitration Association (“AAA”), which I consolidated over a year ago, between petitioners Paul N. Howard Company (“Howard”) and Cable Belt Conveyors, Inc. (“Cable Belt”) (AAA Case No. 13-110-0452-85) and between Cable Belt and Alpart (AAA Case No. 13-110-0113-86). See Cable Belt Conveyors Inc. v. Alumina Partners of Jamaica, 669 F.Supp. 577 (S.D.N.Y.) (consolidating the proceedings), aff'd, 857 F.2d 1461 (2d Cir.), cert. denied, 484 U.S. 855, 108 S.Ct. 161, 98 L.Ed.2d 116 (1987). Specifically, Alpart asks me to (1) enjoin Cable Belt from asserting claims on behalf of Howard; and (2) vacate my order consolidating the proceedings, and enjoin Howard from participating in the arbitration between Alpart and Cable Belt. For the reasons set forth below, Alpart’s motion is denied in its entirety.

BACKGROUND

Under a contract dated March 31, 1981, Cable Belt promised Alpart that it would supply and install a conveyor system to transport bauxite from Alpart’s mine to a storage dome at Alpart’s plant site in Manchester Plateau, Jamaica (the “Contract”). On April 9, 1982, Howard entered into a subcontract with Cable Belt to, among other things, install and commission the conveyor system (the “Subcontract”). Both contracts required that disputes between the parties be submitted to arbitration.

In June, 1985, Howard demanded arbitration against Cable Belt for claims totaling thirty-three million dollars. Cable Belt responded that the claims were unjustified, and, pursuant to Section 35(d) of the Subcontract, 1 through a separate demand for arbitration served on Alpart on January 23, 1986, claimed over and against Alpart for such portions of Howard’s claims that were sustained and for which Alpart was determined to have been responsible.

I consolidated these arbitration proceedings on March 5, 1987, on the grounds that they involved common questions of law and fact and that resolution of the disputes in separate arbitrations could lead to inconsistent findings:

Howard, the subcontractor, has demanded arbitration against Cable Belt to recover damages for the alleged cost of changes, delays and disruptions in the performance of its subcontract with Cable Belt. Cable Belt has denied liability to Howard for its claim as stated but has claimed over and against Alpart for such portions of Howard’s claims as may be established as justified. A possible result of this arbitration is a finding that Cable Belt must pay Paul Howard certain damages on claims for which Alpart is deemed ultimately responsible. If the arbitrations are not consolidated, Alpart *1023 might not be held ultimately liable on those claims since the arbitrator in Cable Belt’s arbitration against Alpart would not be bound by the decision of the arbitrator in Howard’s arbitration, and may reach a decision which is inconsistent with the other arbitrator.

669 F.Supp. at 579.

In May, 1988, Cable Belt and Howard entered into an agreement (the “Agreement”) to cooperate in the prosecution of their claims against Alpart and divide between them any resulting award or settlement. “[A]s between” Cable Belt and Howard, the Agreement “supersed[d] for all purposes ... the [Subcontract.” Agreement 111. 2

On November 7, 1988, Alpart wrote to the arbitral tribunal arguing that the Agreement had resolved all disputes between Howard and Cable Belt and asked the tribunal to (1) dismiss the claims asserted by Cable Belt against Alpart on the basis of Cable Belt’s potential liability to Howard; and (2) dismiss the Howard-Cable Belt arbitration.

After extensive briefing and oral argument, the arbitral tribunal, on December 6, i9gg) denied Alpart’s requests “in all respects.” 3 This motion followed,

DISCUSSION

Petitioners have raised numerous procedural bars to my reaching the merits of Alpart’s motion. Since Alpart’s motion is patently meritless, I have decided not to address the more difficult question of whether it is properly before me. In the following discussion, therefore, I have assumed, without deciding that the issues presented may be resolved by the courts.

I. The Pass-Through Claims

Alpart maintains that the Agreement precludes Cable Belt from asserting claims on Howard’s behalf. I disagree. Although the Agreement is drafted somewhat awkwardly, it is evident that the par *1024 ties were attempting to join forces in a suit against the owner and split the proceeds. Contracts of this sort do not extinguish an owner’s liability for damages incurred by the subcontractor.

“It is common practice for a contractor to present claims of its subcontractors in a suit against the other party to a prime contract.” U.S. Industries, Inc. v. Blake Construction Co., 671 F.2d 539, 550 (D.C.Cir.1982) (citing United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039 (1944)); accord Ardsley Construction Company, Inc. v. The Port of New York Authority, 61 A.D.2d 953, 954, 403 N.Y.S.2d 43, 45 (1st Dep’t 1978). Yet a prerequisite to the general contractor’s right to recover from the owner on the subcontractor’s claim, is the general contractor’s liability to the subcontractor. See J.L. Simmons Co. v. United States, 158 Ct.Cl. 393, 304 F.2d 886, 888 (1962); Barnard-Curtiss Company v. United States, 157 Ct.Cl. 103, 301 F.2d 909 (1962) (“In order to recover this amount from [the owner, the general contractor] must first show that it is liable to the subcontractor for the amount.”). Thus, if the general contractor releases the subcontractor from liability, the owner’s liability to the contractor will be extinguished. See Severin v. United States, 99 Ct.Cl. 435 (1943) (where subcontract provided that general contractor could not be held liable for any loss or damage caused by the owner, general contractor could not sue owner on subcontractor's behalf), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944). Whether the subcontractor has released the general contractor turns on whether there is an express negation of liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
717 F. Supp. 1021, 1989 U.S. Dist. LEXIS 8378, 1989 WL 81346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cable-belt-conveyors-inc-v-alumina-partners-of-jamaica-nysd-1989.