Frank Briscoe Co., Inc. v. County of Clark

772 F. Supp. 513, 1991 U.S. Dist. LEXIS 15513, 1991 WL 145166
District Court, D. Nevada·Decided July 31, 1991·No. CV-S-80-135-RDF·Published·Cited by 2 cases

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR DECLARATORY JUDGMENT AND DENYING DEFENDANT’S MOTION FOR SUMMARY AND DECLARATORY JUDGMENT

ROGER D. FOLEY, District Judge.

INTRODUCTION

This Order is the latest decision in a case filed in 1980 between Frank Briscoe Company, Inc. (“Briscoe”) and Clark County (“the County”). Currently pending before this court are Briscoe’s Motion for Declaratory Judgment (doc. no. 1560), and the County’s Motion for Declaratory and Summary Judgment (doc. no. 1561). These Motions involve Briscoe’s standing to maintain this action against the County, and the County’s liability to Briscoe.

This court heard oral arguments on these Motions on July 15, 1991. After considering these oral arguments and the parties’ well-briefed- Motions, this court renders the following decision.

FACTS

These parties have enjoyed a long and tumultuous relationship with this court that began when Briscoe initiated an action against numerous defendants — including the County — in 1980. Originally, Briscoe, the prime contractor, sought declaratory and injunctive relief for disputes that arose during the construction of an advanced waste water treatment plant in Clark County, Nevada. The County counterclaimed against Briscoe for breach of contract, and Briscoe responded with its own breach of contract counterclaim against the County.

In 1983, Howard Electrical and Mechanical Company, Inc. (“Howard”), a Briscoe subcontractor on the advanced waste water treatment plant project, filed suit in this court against Briscoe for damages incurred during the construction of the water treatment facility, (doc. 1560, exh. A at 1). Additionally, Howard instituted arbitration proceedings against Briscoe. Subsequently, Briscoe filed an action against Howard in the United States District Court for the District of New Jersey.

*515 Originally, Briscoe sought indemnification from the County for the claims of its subcontractors, including Howard. However, this court — in an Order issued after the trial between Briscoe and the County began — held that the contract between Briscoe and the County precluded the County’s indemnification of Briscoe, (doc. no. 1561, exh. D at 12).

The day after this court issued its decision — and five months into the trial — Briscoe revealed to the court and opposing counsel a liquidating agreement signed by Briscoe and Howard on November 14, 1985. 1 The agreement provided that Briscoe would pursue Howard’s claim against the County 2 ; pay ninety-two percent (92%) of the litigation costs; remit a portion of the recovery, if any, to Howard; 3 and dismiss its New Jersey action against Howard. In return, Howard agreed to dismiss both of its pending actions against Briscoe, and accept its portion of the recovery from the County in full settlement of its claims against Briscoe. The following liquidating agreement provisions are important to the disposition of this case:

(1) Howard acknowledged that sole responsibility for its claims of, inter alia, increased costs, additional and extra work, impacts and delays rested with the County. However, because Howard was not in privity with the County, Briscoe agreed to assert Howard’s claim against the County, and for that purpose, Briscoe acknowledged its liability for Howard’s claims;

(2) the parties limited Briscoe’s liability to Briscoe’s obligation to present and pursue Howard’s claims, and to remit a portion of the recovery to Howard;

(3) the parties agreed that Howard would bear the cost and responsibility of furnishing Briscoe with internal research, data, other evidence, witnesses and experts, and would pay eight percent (8%) of the litigation costs;

(4) Howard assigned to Briscoe “all of its rights, title of interest in and to any judgment, award or settlement amount allocated or determined as attributable” to Howard’s claims (doc. no. 1560, exh. A); and

(5) the parties agreed to allocate any recovery from the County in the following manner: Howard would receive nine and one half percent (9.5%) of the first $20,000,-000, and five percent (5%) of any amount above $20,000,000.

About two weeks after this court denied Briscoe’s indemnification claim, Briscoe moved this court for permission to amend its Complaint to allege subcontractor damages. In support of its Motion, Briscoe maintained: “Briscoe is obligated to Howard to pursue these claims of .damage against the County Defendants, and remains liable to Howard to the extent these claims of damage are recovered from the County Defendants.” (doc. no. 1561, exh. A at 2). Although this court granted Briscoe leave to amend, the court severed Howard’s claims against the County from the rest of Briscoe’s case, and reserved the subcontractor’s claims until a later trial.

In September 1986, a final judgment was entered against the County for $16,240,000 plus pre-judgment and post-judgment interest. After exhausting post-trial motions and other avenues of appeal, the County *516 finally paid Briscoe $28,310,257.63. However, Briscoe initially refused to pay Howard any part of this settlement arguing that Howard was not entitled to any recovery until the completion of the trial on Howard’s claim, (doc. no. 1560, exh. A at 1). In response, Howard initiated an action against Briscoe in this court in July 1989. Subsequently, on January 31, 1990, Briscoe and Howard entered into a second agreement in which Briscoe agreed to remit $1,331,523.15 to Howard — the portion of the $28,310,257.63 recovery allocated to Howard under the November 1985 liquidating agreement. Additionally, the parties agreed that Howard would receive five percent (5%) of any additional monies Briscoe recovered on Howard’s claims less Howard’s share of litigation cost. 4 Now, pursuant to the November 1985 liquidating agreement, Briscoe seeks to prosecute Howard’s claim against the County.

DISCUSSION

1. Motion for Summary Judgment:

A. The Standard for Summary Judgment:

Free access — add to your briefcase to read the full text and ask questions with AI

Frank Briscoe Co., Inc. v. County of Clark, 772 F. Supp. 513, 1991 U.S. Dist. LEXIS 15513, 1991 WL 145166 (D. Nev. 1991).

772 F. Supp. 513 (Frank Briscoe Co., Inc. v. County of Clark) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)