St. Paul Dredging Co. v. State

107 N.W.2d 717, 259 Minn. 398, 1961 Minn. LEXIS 684
CourtSupreme Court of Minnesota
DecidedFebruary 10, 1961
Docket38,011
StatusPublished
Cited by20 cases

This text of 107 N.W.2d 717 (St. Paul Dredging Co. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Dredging Co. v. State, 107 N.W.2d 717, 259 Minn. 398, 1961 Minn. LEXIS 684 (Mich. 1961).

Opinion

Thomas Gallagher, Justice.

St. Paul Dredging Company, plaintiff, seeks damages against the State of Minnesota for breach of a contract, S. P. 6947-06, for widening and grading shoulder of state Highway No. 216 for a distance of 17 miles beginning east of Hibbing. Plaintiff’s action is based upon its contention that contract specifications called for the defendant to furnish a highway worksite free from utility poles, that it failed to do so, and that in consequence plaintiff sustained damages.

The trial court construed the contract in accordance with plaintiff’s contentions and charged the jury as a matter of law that defendant had failed in its obligation to plaintiff, submitting for determination only the issue of damages. The jury returned a verdict for plaintiff in the sum of $40,438.08. This is an appeal from an order denying defendant’s subsequent alternative motion for judgment notwithstanding the verdict or for a new trial.

Defendant does not challenge the amount of the verdict as a measure of damages but contends that (1) the court erred in instructing *400 the jury that a contractual duty rested upon it to provide plaintiff with a highway worksite free of utility poles; (2) if the language of the contract and specifications be regarded as ambiguous, the issue of what the parties intended should have been submitted to the jury; and (3) if the contract did not impose an absolute duty upon defendant to provide a construction site free of utility poles, whether the state had exercised a reasonable effort to comply with its contract obligation, and whether the delay in removal of utility poles was within the contemplation of the parties at the time the contract was executed, were fact questions for the jury. Defendant also contends that its motion to dismiss the action on the ground that plaintiff was not the real party in interest should have been granted.

The contract, dated May 5, 1955, provides that plaintiff shall complete the work within 75 working days or be subject to certain deductions for damages. It further specifies that upon receipt of written notice from the contractor of the existence of causes over which the contractor has no control which may delay the completion of the work the commissioner of highways may extend the date specified for completion.

The contract is governed by specifications for highway construction issued by the Minnesota Department of Highways, the following of which are relevant here:

1802.1. “All Right of Way for construction work will be furnished by the State. In case the State fails to effect the removal of structures and buildings from any section of the Right of Way, the right is reserved either to eliminate the work on that section from the Contract as provided in 1404, or to require the Contractor to construct the work as specified at a later date. In the latter case, the time for completion of the work will be extended for a period of time equivalent to any delay caused by such failure. If such failure by the State causes increased cost to the Contractor, fair and equitable compensation will be made therefor.”
1408. “All obstructions to the construction of the Project and other encumbrances within the construction limits as indicated in the Plans, including fences, foundations and well curbs, but not including build *401 ings and public utility properties, shall be removed by the Contractor.” (Italics supplied.)
1409. “All properties of public utility companies or municipalities, such as pole lines, conduits, gas pipes, water pipes, sewers and tile lines, which run over, through or under any part of the Right of Way and which, in the opinion of the Engineer, will interfere with the completion of the Project, will, except as otherwise provided in the Contract, be moved by the owners to the locations and in accordance with the conditions set forth in the utility permit granted by the Commissioner and on file in his office.
“The Contractor shall preserve and protect all such properties which are above the ground surface, and also those below the ground surface whose approximate locations are shown in the Plans * * * he shall assume full responsibility for reimbursing the owners thereof for any damage or injury to such properties which may be caused by his operations. * * *
* * * * *
“If the Contractor is required to perform any special work * * * along or adjacent to any public utility property located below the ground surface * * * fair and equitable compensation will be made for the cost of such special work or construction methods.”

Defendant concedes that plaintiff had no right to remove the utility poles, such right being vested in defendant alone under Minn. St. 1957, § 161.13, which provided that utility poles constructed, placed, or maintained along any trunk highway:

“* * * may be so maintained or hereafter constructed only in accordance with such regulations as may be prescribed by the commissioner of highways, who shall have power to prescribe and enforce reasonable rules and regulations with reference to the placing and maintaining * * * of the utilities * *

Order No. 13095 issued under § 161.13 by the commissioner contains the following regulations:

“11. Existing utility lines may be maintained in their present position until required to change because of the improvement of the trunk *402 highway, * * *. In all cases the reconstruction of utility lines shall be under permit and in accordance with these regulations.
“12. If at any time the State of Minnesota, acting through its Commissioner of Highways, shall deem it necessary to make any improvements or changes on ail or any part of the right of way of the trunk highway which affect the utility as located under a Department of Highways permit, then and in such event, the owner of the utility therein named will, within fifteen days after written notice from the Commissioner of Highways * * * proceed to alter, change, vacate or remove from the trunk highway right of way said public utility so as to conform to said changes, such work to be done without any cost whatsoever to the State of Minnesota and completed within the date specified in said written notice.”

Shortly after plaintiff entered into the contract, it also entered into an agreement with Seth Morse and Morse Brothers & Associates, Inc., of Rochester, hereinafter referred to as Morse, which provided that:

“This agreement covers the supervision, the furnishing of the required equipment, tools and other incidental items required to construct, according to the plans and specifications, the State Highway Project, identified as S. P. 6947-06 (S.H. 216).
* * * * *
“1. The St. Paul Dredging Company agrees to employ Mr. Seth Morse on this project as Superintendent of Construction. Both Seth Morse and Morse Brothers & Associates, Incorporated agree to such employment.
“2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Superior Gunite v. Ralph Mitzel Inc.
12 Cal. Rptr. 3d 423 (California Court of Appeal, 2004)
Alamo Community College District v. Browning Construction Co.
131 S.W.3d 146 (Court of Appeals of Texas, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
In Re Mr. Movies, Inc.
287 B.R. 178 (D. Minnesota, 2002)
D.H. Blattner & Sons, Inc. v. Firemen's Insurance Co.
535 N.W.2d 671 (Court of Appeals of Minnesota, 1995)
Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)
Waldinger Corp. v. CRS Group Engineers, Inc.
775 F.2d 781 (Seventh Circuit, 1985)
Board of County Commissioners v. CAM Construction Co.
480 A.2d 795 (Court of Appeals of Maryland, 1984)
Public Health Trust of Dade County v. M.R. Harrison Construction Corp.
454 So. 2d 659 (District Court of Appeal of Florida, 1984)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
Barbarossa & Sons, Inc. v. Iten Chevrolet, Inc.
265 N.W.2d 655 (Supreme Court of Minnesota, 1978)
Eric A. Carlstrom Construction Co. v. Independent School District No. 77
256 N.W.2d 479 (Supreme Court of Minnesota, 1977)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Wexler Construction Co. v. Housing Authority
183 A.2d 262 (Supreme Court of Connecticut, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
107 N.W.2d 717, 259 Minn. 398, 1961 Minn. LEXIS 684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-dredging-co-v-state-minn-1961.