Juengel Const. Co., Inc. v. Mt. Etna, Inc.

622 S.W.2d 510, 1981 Mo. App. LEXIS 3160
CourtMissouri Court of Appeals
DecidedJuly 28, 1981
Docket42327
StatusPublished
Cited by41 cases

This text of 622 S.W.2d 510 (Juengel Const. Co., Inc. v. Mt. Etna, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Juengel Const. Co., Inc. v. Mt. Etna, Inc., 622 S.W.2d 510, 1981 Mo. App. LEXIS 3160 (Mo. Ct. App. 1981).

Opinion

GUNN, Acting Presiding Judge.

Plain tiff-respondent Juengel Construction Co., Inc. (Juengel) brought suit against defendants-appellants, Mt. Etna, Inc., Grasso Brothers, Inc. (Grasso), National Supermarkets, Inc. (National) and Hastings & Chivetta Architects, Inc. (Hastings & Chivetta), arising out of the renovation and remodeling of a building for National. Count I was against Grasso and Mt. Etna and sought damages for lost profits for breach of a construction contract. Count II sought actual and punitive damages from National and Hastings & Chivetta for tor-tious interference of contract. A third count alleging defamation was dismissed by Juengel before trial.

In a jury waived case judgment was for Juengel against Mt. Etna and Grasso on Count I for $44,770.78 for lost profits by reason of breach of contract. Judgment was against Hastings & Chivetta on Count II for $1.00 actual and $10,000 punitive damages for tortious interference of contract.

On appeal Grasso and Mt. Etna raise the following points: (1) the contract was unenforceable for failure of performance of conditions precedent; (2) Juengel failed to prove the amount of lost profits with sufficient certainty. Additionally, National and Hastings & Chivetta allege that proof is lacking for tortious interference of con *512 tract; that even if there were such interference, it was justified.

We affirm the judgment.

The Grasso brothers are the sole stockholders of Mt. Etna, Inc., which in turn owns Grasso Plaza, a shopping center in St. Louis County. National Supermarkets, Inc. is the principal tenant at Grasso Plaza. In late 1975 the Grassos contemplated remodeling a portion of Grasso Plaza, and notified Juengel Construction Company, Inc., which had previously performed various construction jobs for them, of their expectations.

In February, 1976, Mt. Etna, as lessor, and National, as lessee, executed a lease which provided for remodeling and expansion of the National store at Grasso Plaza. The parties agreed that Mt. Etna would pay $400,000 of the construction costs and National would pay the excess; the amount of Mt. Etna’s obligation was later increased to $500,000.

The complicated series of interactions between the parties effectively commenced with a meeting in March, 1976 at the Grasso Plaza jobsite for a discussion of the construction project. Attending were representatives of Juengel, Mt. Etna, National and Hastings & Chivetta, the architects retained by National.

On May 3, 1976, Juengel and Mt. Etna executed the agreement written by Juengel that is the subject of this lawsuit. The instrument, entitled “Construction Contract and Agreement between Owner and General Contractor,” names Juengel as the general contractor and delineates its duties regarding the Grasso Plaza project. The contract provides that Juengel perform according to the specifications of Hastings & Chi-vetta Architects, with ?!t. Etna and National being entitled to name the subcontractors and suppliers to submit bids for the project. The contract further provides that “[t]he General Contractor, Owner and National Supermarkets will jointly decide which of the sub bidders will be awarded a contract on their phase of the work.”

Subsequently, in a letter dated June 17, 1976, addressed to Mt. Etna, a National representative set out terms of agreement between National and Mt. Etna on the Grasso Plaza project. National substantially duplicated portions of the Juengel-Mt. Etna contract, providing that the “Lessor and the Lessee ... shall jointly name the subcontractors and suppliers to submit prices” for the project and that “[t]he General contractor [Juengel Construction Co., Inc.], Lessor and Lessee will jointly decide which of the subcontractors will be awarded a contract on their phase of the work.”

Juengel and all defendants met several times in the spring and summer of 1976. They agreed that Juengel would solicit subcontractor bids upon receipt of architectural plans from Hastings & Chivetta. Juengel prepared a list of subcontractors to be invited to submit bids and circulated the list for the approval of the other parties, allowing them to add or delete names of subcontractors. Juengel also initiated the demolition of the area to be renovated, which was one of its contractual duties.

By the end of the summer, Hastings & Chivetta completed the project’s plans and forwarded them to Juengel, which in turn invited subcontractor bids. After Juengel had received, compiled and tabulated the bids, the parties met in late September to review them. The total projected cost of the job was $759,442.00, to which was added the general contractor’s fee — described as overhead and profit — of 6% of cost, or approximately $45,567.00, resulting in a total price of $805,009.00. 1 National objected at the meeting that the overall price was too high, but individual subcontractor bids were not discussed.

Shortly after this encounter, National informed the Grassos of its intent to have the project rebid. When the Grassos protested that they had a contract with Juengel, National assured them that it would indemnify if Juengel sued, a fact denied by National.

*513 Mr. Grasso notified Juengel of National’s intent to rebid the project and sought a meeting of the parties to resolve differences, but National refused to meet. National proceeded to invite bids for general contractor and subcontractor positions. Bids from the lowest successful bidders amount to a total projected price of $712,-388.00, with the job ultimately costing approximately $795,000.00.

For their first point of error defendants Mt. Etna and the Grasso Brothers contend that their contract with Juengel was unenforceable because a condition precedent to their duty to perform — joint agreement on subcontractors by Juengel, the Grassos and National — had not been fulfilled. The Grassos maintain that they in good faith attempted to secure satisfaction of the condition and that failure of the condition was due to the noncooperation of National, a third party which was beyond the control of the parties to the contract.

A condition precedent is an act or event that must be performed or occur, after the contract has been formed, before the contract becomes effective. Globe American Corp. v. Miller Hatcheries, Inc., 110 S.W.2d 393, 396 (Mo.App.1937). Conditions precedent are disfavored, and contract provisions are construed as such only if unambiguous language so requires or they arise by necessary implication. Kansas City Southern Railway Co. v. St. Louis-San Francisco Railway Co., 509 S.W.2d 457, 460 (Mo.1974); Miran Investment Co. v. Medical West Building Corp., 414 S.W.2d 297, 304 (Mo.1967); Servco Equipment Co. v. C. M. Lingle Co., 487 S.W.2d 869, 871 (Mo.App.1972).

The requirement in a contract of a third party’s acquiescence or the performance of some act by him may or may not be a condition precedent to enforcement of the contract. On the one hand, if the fulfillment of the contract depends on the act or consent of a third party, the contract is unenforceable until the third party so acts or consents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank J. Laenen, and Jennifer R. Laenen v. Beth A. Laenen
451 S.W.3d 715 (Missouri Court of Appeals, 2014)
Vantage Credit Union v. Jimmy M. Chisholm
447 S.W.3d 740 (Missouri Court of Appeals, 2014)
Olathe Millwork Co. v. Dulin
189 S.W.3d 199 (Missouri Court of Appeals, 2006)
Forney v. Missouri Bridge & Concrete, Inc.
112 S.W.3d 471 (Missouri Court of Appeals, 2003)
Howard v. Youngman
81 S.W.3d 101 (Missouri Court of Appeals, 2002)
MECO Systems, Inc. v. Dancing Bear Entertainment, Inc.
42 S.W.3d 794 (Missouri Court of Appeals, 2001)
Meco Systems v. DANCING BEAR ENT.
42 S.W.3d 794 (Missouri Court of Appeals, 2001)
Cosky v. Vandalia Bus Lines, Inc.
970 S.W.2d 861 (Missouri Court of Appeals, 1998)
Alexander & Alexander Inc. v. B. Dixon Evander & Associates, Inc.
650 A.2d 260 (Court of Appeals of Maryland, 1994)
Hood-Rich, Inc. v. County of Phelps
872 S.W.2d 584 (Missouri Court of Appeals, 1994)
Paglin v. Saztec International, Inc.
834 F. Supp. 1184 (W.D. Missouri, 1993)
James E. Brady & Co. v. Eno
992 F.2d 864 (Eighth Circuit, 1993)
J. & J. Home Builders, Inc. v. Dobas
839 S.W.2d 737 (Missouri Court of Appeals, 1992)
Ibarra v. Missouri Poster & Sign Co.
838 S.W.2d 35 (Missouri Court of Appeals, 1992)
Fitch v. J.A. Tobin Construction Co.
829 S.W.2d 497 (Missouri Court of Appeals, 1992)
Eades Commodities, Co. v. Hoeper
825 S.W.2d 34 (Missouri Court of Appeals, 1992)
Hastings & Chivetta Architects v. Burch
794 S.W.2d 294 (Missouri Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
622 S.W.2d 510, 1981 Mo. App. LEXIS 3160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/juengel-const-co-inc-v-mt-etna-inc-moctapp-1981.