Covington Bros. v. Valley Plastering, Inc.

566 P.2d 814, 93 Nev. 355, 1977 Nev. LEXIS 569
CourtNevada Supreme Court
DecidedJuly 1, 1977
Docket8519
StatusPublished
Cited by21 cases

This text of 566 P.2d 814 (Covington Bros. v. Valley Plastering, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Covington Bros. v. Valley Plastering, Inc., 566 P.2d 814, 93 Nev. 355, 1977 Nev. LEXIS 569 (Neb. 1977).

Opinion

*357 OPINION

By the Court,

Mowbray, J.:

Valley Plastering, Inc., the respondent, commenced this action against Covington Brothers, the appellant, seeking (1) foreclosure of a mechanic’s lien and (2) damages for breach of contract. Both causes of action arose out of a housing construction project in Las Vegas. The district judge ruled in favor of Valley, ordering foreclosure of the lien in the amount of $3,858.10 and awarding $20,000 damages for breach of contract.

The issues presented are whether the court erred in its findings that Valley was entitled to recover $3,858.10 under its mechanic’s lien and that Covington had breached its contract with Valley. If Covington did breach its contract, then we must determine whether the $20,000 damage award was proper.

1. The Facts.

Covington, as owner and general contractor for a housing project called El Sol Del Pueblo, entered into a written contract with Valley to “[fjurnish all necessary labor, equipment and materials for [a] complete exterior plaster (stucco) job,” covering 48 four-plex buildings. The construction consisted of *358 two phases: the first included 22 units, and the second, 26 units.

Covington agreed to pay Valley $62,106 upon completion of the first phase, and $73,398 when the second phase was completed.

A dispute arose soon after work started regarding who had the responsibility of applying the lath backing for the stone veneer on the buildings. Rather than delay the construction, Mr. Bryan, project superintendent for Covington, told Mr. Friel, president of Valley, to go ahead and do the work. The testimony is conflicting, however, whether Bryan unconditionally promised Friel payment for the additional work or whether he promised payment only if Covington’s main office should determine that the work was not within the scope of the contract.

Before commencement of the second phase of the project, Covington sent letters to all its subcontractors, including Valley, asking for a written assurance of their intent to perform phase 2. Valley did not comply with Covington’s request. The testimony is in conflict whether oral assurances were given. Valley stated they were given. Covington claimed, however, that Valley had previously expressed an unwillingness to go forward unless the contract price for phase 2 was increased. Covington later notified Valley that it had selected another subcontractor. This lawsuit resulted.

2. The Issues.

Covington urges that Valley should not be awarded $3,858.10 for applying the lath backing for the stone veneer. Covington presented evidence indicating that plaster subcontractors customarily did lathing work and urged that the terms of the contract indicated that the work was included in the contract price.

The terms of the contract are ambiguous. While the contract specifies “all lath and plaster required for a complete job,” it also refers to work required for a complete stucco exterior. No reference is made to portions of the exterior that were brick or stone. Valley offered evidence that it did not consider the work within the scope of the contract and that it did the work only because of Covington’s expressed assurance of additional payment. 1 The court found for Valley, and the finding is supported by substantial evidence. It may not be disturbed on *359 appeal. Shell Oil Co. v. Ed Hoppe Realty Inc., 91 Nev. 576, 540 P.2d 107 (1975).

Covington suggests that it did not breach its contract by awarding phase 2 to another subcontractor, because Valley had already committed an anticipatory repudiation of its contractual obligations. The record shows that Covington sent registered form letters to all phase 1 subcontractors, requesting written assurance that they were ready and willing to perform phase 2. It is undisputed that Valley received such a letter and failed to provide a written response.

The testimony is conflicting whether Valley gave oral assurance of performance. The uncertainty arose from the fact that a price increase for phase 2 was discussed. Valley admits requesting an increase, but denies having conditioned further performance on its being granted. 2 On March 25, 1974, Covington informed Valley by letter that it had selected another subcontractor to perform, and on April 2, 1974, engaged Southwest Construction Co. for that purpose. Valley, in return, by certified letter dated April 3, 1974, advised Covington that it was willing to perform phase 2. That letter stated, in part:

Mr. Friel, president of Valley Plastering, Inc., informed vour representative, William Bryan, that his firm did intend to proceed with Phase Two, but demanded payment in full of all the monies due under Phase One. Therefore, the statements made by you in your March 25, *360 1974 letter are incorrect. Valley Plastering, Inc., does intend to do Phase Two but must insist on payment in full of the monies now due under Phase One, to-wit: the sum of $3,858.10.
We have been informed that you intend to use others to do work that Valley Plastering, Inc., contracted to do. If this occurs, then we intend to proceed against your firm for the damages suffered by Valley Plastering, Inc., in the amount of the profit which they would otherwise have realized had they been allowed to proceed with the second phase in the sum of $20,000.00.
Your prompt attention to these matters is encouraged and we will expect payment forthwith of the balance due under the old contract so that we may proceed to perform the second phase immediately.

A contractual anticipatory repudiation must be clear, positive, and unequivocal. See Kahle v. Kostiner, 85 Nev. 355, 455 P.2d 42 (1969). Whether specific conduct or language is sufficiently clear to constitute an anticipatory repudiation must be decided in light of the total factual context of the individual case. See Early v. Santa Clara Broadcasting Co., 27 Cal.Rptr. 212, 214 (Cal.App. 1963).

The court in this case chose to believe Valley’s version of the facts and in so doing found that an anticipatory repudiation did not occur. Such a finding was within the court’s discretion. Substantial evidence supports the finding, and it therefore must stand. Shell Oil Co. v. Ed Hoppe Realty Inc., 91 Nev. 576, 540 P.2d 107 (1975).

Finally, Covington contends that the court erred in awarding Valley a gross profit lost on phase 2 of the contract. It is urged that, in addition to the cost of labor and material, the court should have deducted some portion of the company's overhead: i.e., the officers’ salaries, depreciation, interest, office rent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Health Sys., LLC v. Murray
Nevada Supreme Court, 2023
Shaw v. Citimortgage, Inc.
201 F. Supp. 3d 1222 (D. Nevada, 2016)
Vegas South Partners v. Mandalay Place
Nevada Supreme Court, 2015
Wallace v. Smith
Nevada Supreme Court, 2014
Zhang v. Eighth Judicial District Court of State of Nevada
103 P.3d 20 (Nevada Supreme Court, 2004)
Zhang v. Dist. Ct.
103 P.3d 20 (Nevada Supreme Court, 2004)
INTERSTATE COMMERCIAL BLDG. SERV. v. Bank of Amer.
23 F. Supp. 2d 1166 (D. Nevada, 1998)
David Sloane, Inc. v. Stanley G. House & Associates, Inc.
532 A.2d 694 (Court of Appeals of Maryland, 1987)
Ritam Corp. v. Applied Concepts, Inc.
387 N.W.2d 619 (Court of Appeals of Iowa, 1986)
State Mortgage Co. v. Rieken Development, Inc.
664 P.2d 358 (Nevada Supreme Court, 1983)
Bronken's Good Time Co. v. J. W. Brown & Associates
661 P.2d 861 (Montana Supreme Court, 1983)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
566 P.2d 814, 93 Nev. 355, 1977 Nev. LEXIS 569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/covington-bros-v-valley-plastering-inc-nev-1977.