Cladianos v. Friedhoff

240 P.2d 208, 69 Nev. 41, 1952 Nev. LEXIS 54
CourtNevada Supreme Court
DecidedJanuary 31, 1952
DocketNo 3664
StatusPublished
Cited by32 cases

This text of 240 P.2d 208 (Cladianos v. Friedhoff) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cladianos v. Friedhoff, 240 P.2d 208, 69 Nev. 41, 1952 Nev. LEXIS 54 (Neb. 1952).

Opinion

*43 OPINION

By the Court,

Merrill, J.:

This is an action brought by the respondent, Friedhoff, as plaintiff asking damages for breach of contract. The contract involved was one for the performance of personal services by Friedhoff to appellant, Cladianos. The trial court, hearing the case without a jury, found for Friedhoff and granted judgment in the sum of $7,500 (plus the additional sum of $176.11 which is not in dispute) . This appeal is from that judgment and from the court’s subsequent order denying motion for new trial. The parties will be referred to by name.

The questions raised upon this appeal are whether, as contended by Cladianos, a tender of performance by Friedhoff was necessary under the circumstances; and whether the measure of damages should not be confined to quantum meruit for the services actually performed by Friedhoff.

Friedhoff is a duly licensed contractor engaged in business in the city of Reno. Cladianos is- the owner and operator of El Rancho Motel in that city. On or about February 10, 1946, the parties entered into a contract whereby Cladianos employed Friedhoff to render services in a supervisory capacity for the construction of a 20-unit addition to the motel. Friedhoff was to be compensated in an amount equal to 10 percent of the total cost of construction.

Friedhoff entered into performance of the contract on or about April 1,1946, laid out the work to be performed in accordance with architect’s plans provided to him by Cladianos, engaged cement, carpentry, brick, plumbing, electrical and other subcontractors and entered into agreements with them as to the time of performance and their charges. Work proceeded in this manner from April 1, 1946, to May 15, 1946, under Friedhoff’s supervision.

On the last-mentioned date the parties were notified by the Civilian Production Administration, a federal *44 agency, that the construction was in violation of orders of that agency and must be discontinued. Pursuant to that notice, construction was discontinued on that date.

On August 10, 1946, Cladianos notified Friedhoff that authority had been received from the agency to proceed with construction. Construction thereupon continued under Friedhoff’s supervision until February 4, 1947, at which time Cladianos notified Friedhoff that he had again been ordered to discontinue construction.

Effective July 1,1947, the Civilian Production Administration was abolished and all controls on construction were lifted. On July 10, 1947, Cladianos proceeded with construction of the motel addition. He did not notify Friedhoff of his action in this regard, however, and from that date until completion of the structure, work continued without Friedhoff’s supervisory services. The total cost of the construction as finally completed was $78,433.60.

While Friedhoff was not notified that construction was recommencing on July 10, 1947, he subsequently learned of that fact by personal observation in driving past the site of construction and from conversations had with certain subcontractors. He also learned from those conversations that Cladianos had advised the subcontractors that Friedhoff was no longer in charge of the job. Friedhoff never thereafter discussed the matter with Cladianos or made formal tender of his services.

In the trial court Cladianos contended that the contract by its terms was subject to termination at any time and that it had been expressly so terminated by him prior to July 10, 1947. This contention was denied by Friedhoff and the trial court by its findings decided this factual issue in Friedhoff’s favor. No assignment of error is made in this regard and we therefore must accept the terms of the contract as alleged by Friedhoff and found by the trial court: to cover the whole of the construction with compensation computed upon the total cost thereof.

*45 Cladianos contends that, notwithstanding the existence of the agreement and its scope as determined below, Friedhoff is not entitled to rely on such contract and that his recovery should be limited to quantum meruit for the services actually performed by him prior to discontinuance of work on February 4, 1947. Two arguments are advanced in support of this contention:

First: That to entitle him to rely on breach of the contract, Friedhoff must have tendered his services to Cladianos, thus giving actual notice that he was ready, able and willing to proceed with his side of the agreement. The nature of this-“tender” is set forth in 12 Am.Jur. 891 (Contracts, sec. 334), as follows:

“The word ‘tender’ as used in such connection does not mean the same kind of offer as when it is used in reference to the payment or offer to pay an ordinary debt due in money, where the money is offered to a creditor who is entitled to receive it, nothing further remains to be done, and the transaction is completed and ended; but it means only a readiness and willingness accompanied with an ability on the part of one of the parties to do the acts which the agreement requires him to perform, provided the other will concurrently do the things which he is required by it to do, and a notice by the former to the latter of such readiness. Such readiness, ability, and notice are sufficient evidence of, and indeed imply, an offer or tender in the sense in which those terms are used in reference to mutual and concurrent agreements. It is not an absolute, unconditional offer to do or transfer anything at all events, but it is, in its nature, conditional only, and dependent on, and to be performed only in case of, the readiness of the other party to perform his part of the agreement.”

The law is clear, however, that any affirmative tender of performance is excused when performance has in effect been prevented by the other party to the contract. See: 3 Williston on Contracts (Rev.Ed.) 1952 (sec. *46 677), 2325 (sec. 832); 17 C.J.S. 986, (Contracts, sec. 481); 12 Am.Jur. 889, (Contracts, sec. 333).

As is stated by Mr. Williston (supra, sec. 677) : “It is a principle of fundamental justice that if a promisor is himself the- cause of the failure of performance, either of an obligation due him or of a condition upon which his own liability depends, he cannot take advantage of the failure.”

In this respect it is stated in Lake Shore & M. S. Ry. Co. v. Richards, 152 Ill. 59, 38 N.E. 773, 779, 30 L.R.A. 33, that the term “prevented from performing” does not mean:

“* * * that there must be physical prevention, but that any acts, conduct, or declarations of the party, evincing a clear intention to repudiate the contract, and to treat it as no longer binding, is a legal prevention of performance by the other party.” 38 N.E. at 779.
“* * * It seems clear both upon principle and by authority, that where one party to an executory contract refuses to treat it as subsisting and binding upon him, or, by his act and conduct, shows that he has renounced it, and no longer considers himself bound by it, there is, in legal effect, a prevention of performance by the other party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BANK OF AMERICA, N.A. VS. THOMAS JESSUP, LLC SER. VII
2019 NV 7 (Nevada Supreme Court, 2019)
Bank of Am., N.A. v. Thomas Jessup, LLC
435 P.3d 1217 (Nevada Supreme Court, 2019)
Wallace v. Smith
Nevada Supreme Court, 2014
Summa Corp. v. Richardson
596 P.2d 208 (Nevada Supreme Court, 1979)
Eaton v. J. H. Inc.
581 P.2d 14 (Nevada Supreme Court, 1978)
Enloe v. Blain
577 P.2d 60 (Nevada Supreme Court, 1978)
Covington Bros. v. Valley Plastering, Inc.
566 P.2d 814 (Nevada Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
240 P.2d 208, 69 Nev. 41, 1952 Nev. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cladianos-v-friedhoff-nev-1952.