Forney v. Missouri Bridge & Concrete, Inc.

112 S.W.3d 471, 2003 Mo. App. LEXIS 1298, 2003 WL 21960334
CourtMissouri Court of Appeals
DecidedAugust 19, 2003
DocketWD 61792
StatusPublished
Cited by11 cases

This text of 112 S.W.3d 471 (Forney v. Missouri Bridge & Concrete, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forney v. Missouri Bridge & Concrete, Inc., 112 S.W.3d 471, 2003 Mo. App. LEXIS 1298, 2003 WL 21960334 (Mo. Ct. App. 2003).

Opinion

ROBERT G. ULRICH, Judge.

Jay Forney appeals the judgment of the trial court awarding him $18,306.82 in damages on his breach of contract action against Missouri Bridge and Concrete. He claims that the trial court erred in awarding him $13,306.82 and in denying his motion for new trial on the issue of damages because the award, the amount owed for retainage, misapplied the law in that the proper measure of damages was the balance of the contract. The judgment of the trial court is affirmed.

Facts

Jay Forney is the sole proprietor of Forney Excavating Company, which is also known as Forney Construction (Forney). Missouri Bridge and Concrete, Inc. (Missouri Bridge) is a Missouri corporation in the business of bridge construction. On April 23, 1999, Missouri Bridge entered into a contract with the Missouri Highway and Transportation Department for the construction of the Nodaway County bridge replacement. On April 25, 1999, Missouri Bridge and Forney entered into a subcontract whereby Forney agreed to perform Class A excavation and eompact-ing embankment on the Nodaway County bridge job in exchange for payment in the amount of $438,988.71. The subcontract provided that if Forney was unable to complete the project, Missouri Bridge could take over and complete the project or furnish the necessary materials and employees to remedy Forney’s noncompliance at the expense of Forney. It also provided that Forney may rent the equipment or hire the employees of Missouri Bridge to perform part of the subcontract for an agreed upon price.

The Nodaway County bridge job was a larger project than Forney normally performed requiring it to purchase additional equipment and hire additional employees. Forney began work on the job on May 10, 1999. For the first couple of months, For-ney performed the work under the subcontract and received scheduled payments. During that time, Missouri Bridge never informed Forney that the character or timeliness of its performance of the subcontract was inadequate. By early August 1999, without any notice to Forney that it was failing to comply with the subcontract, Missouri Bridge moved its own men and equipment onto the job and began part of the excavation and compacting work covered by the subcontract. Soon after, Missouri Bridge presented Forney with invoices billing it for the hours that its men and equipment worked on the project. Forney refused to pay the invoices, and Missouri Bridge deducted the invoice amounts from its scheduled payments to Forney. Forney received payments from Missouri Bridge totaling $252,829.62.

In December 2000, Mr. Forney filed his breach of contract action against Missouri Bridge seeking the sum of $186,159.09, the balance of the contract. 1 Following a trial *474 to the bench, the trial court entered its findings of fact, conclusions of law, and judgment finding that Missouri Bridge, breached the subcontract with Mr. Forney by making it impossible for Mr. Forney to substantially comply with its terms. The trial court also found that the proper measure of damages was the contract price less the amount it would have cost the subcontractor to perform the contract and that no probative evidence was produced regarding the expenses of the completion of the contract. The trial court, therefore, awarded Mr. Forney $13,306.82, the amount owed to Mr. Forney as retainage. This appeal by Mr. Forney followed.

Point I

In his first point on appeal, Mr. Forney claims that the trial court erred in awarding him damages in the amount of $13,306.82. He asserts that the award, the amount owed for retainage, misapplied the law in that the proper measure of damages was the balance of the contract because the contract was for labor only and no evidence was presented that his overhead expenses were saved by the non-completion of the contract.

In a court-tried case, the judgment of the trial court will be sustained unless no substantial evidence supports it, it is against the weight of the evidence, or it erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976); Gee v. Payne, 939 S.W.2d 383, 385 (Mo.App. W.D.1997). “The proper measure of damages is a question of law for determination by the trial court.” Gee, 939 S.W.2d at 385. The particular facts and circumstances of a case dictate which measure of damages is appropriate. Id. Generally, in a breach of contract case, the goal in awarding damages is to put the non-breaching party in as good a position as it would have been in if the contract had been performed. Id.

The proper measure of damages in a case where an owner breaches a construction contract by preventing the contractor from performing the work is the contract price less the amount it would have cost the contractor to perform the contract. Juengel Constr. Co. v. Mt. Etna, Inc., 622 S.W.2d 510, 514 (Mo.App. E.D.1981). “This amount, which constitutes lost profits, must be shown with reasonable certainty by proof of facts from which anticipated profits can rationally be estimated.” Id. Overhead expenses are included in the contractor’s total cost saved by nonperformance and, thus, deducted from the contract price only where the owner/defendant proves that such expenses were actually saved by the breach. Id. at 515. In the absence of proof that the contractor/plaintiff saved overhead expenses as a result of the owner’s breach of contract, overhead expenses are included in the lost profits damages award. Id. “The rationale supporting this conclusion is that if the contract had not been breached, fixed business expenses would have been paid from profits remaining after payment of costs directly related to performance of the contract.” Id.

Forney failed to introduce evidence from which its lost profits could be ascertained with reasonable certainty. Specifically, Forney failed to present evidence of the costs to complete the subcontract; whether the costs were direct costs associated with performance of the subcontract or fixed overhead expenses. Forney argues that the entire amount of the subcontract constituted profit and overhead expenses. It contends that because Missouri Bridge failed to prove that its overhead *475 expenses were saved by the breach, such expenses should have been included in the lost profits damages award. Thus, it contends it was entitled to $192,003.17, the remaining balance of the contract.

While some of Forney’s expenses may have constituted overhead expenses, such as payments on its equipment and insurance, certain costs were directly associated with the subcontract such as fuel and labor costs. The evidence in this case showed that Missouri Bridge completed part of the excavation work under the subcontract. Because Forney did not complete the work, it did not incur the expenses directly associated with that part of the work. To award Forney damages that included compensation for expenses that were actually avoided as a result of the breach would create a windfall.

Forney relies on the case,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker Team Properties, LLC v. Matt Wenta
Missouri Court of Appeals, 2020
Union Electric Company D/B/A Ameren Missouri v. A.P. Read Homes, LLC
485 S.W.3d 773 (Missouri Court of Appeals, 2016)
Handy v. Handy
338 S.W.3d 852 (Missouri Court of Appeals, 2011)
Arrow Financial Services, LLC v. Collier
323 S.W.3d 827 (Missouri Court of Appeals, 2010)
U.S. Neurosurgical, Inc. v. Midwest Division-RMC, LLC
303 S.W.3d 660 (Missouri Court of Appeals, 2010)
Eiman Bros. Roofing Systems, Inc. v. CNS International Ministries, Inc.
158 S.W.3d 920 (Missouri Court of Appeals, 2005)
Ameristar Jet Charter, Inc. v. Dodson International Parts, Inc.
155 S.W.3d 50 (Supreme Court of Missouri, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
112 S.W.3d 471, 2003 Mo. App. LEXIS 1298, 2003 WL 21960334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forney-v-missouri-bridge-concrete-inc-moctapp-2003.