FOX CREEK CONSTRUCTION, INC., Plaintiff-Respondent v. OPIE'S LANDSCAPING, LLC

CourtMissouri Court of Appeals
DecidedJuly 30, 2019
DocketSD35668
StatusPublished

This text of FOX CREEK CONSTRUCTION, INC., Plaintiff-Respondent v. OPIE'S LANDSCAPING, LLC (FOX CREEK CONSTRUCTION, INC., Plaintiff-Respondent v. OPIE'S LANDSCAPING, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FOX CREEK CONSTRUCTION, INC., Plaintiff-Respondent v. OPIE'S LANDSCAPING, LLC, (Mo. Ct. App. 2019).

Opinion

FOX CREEK CONSTRUCTION, INC., ) ) Plaintiff-Respondent, ) ) v. ) No. SD35668 ) OPIE’S LANDSCAPING, LLC, ) Filed: July 30, 2019 ) Defendant-Appellant. )

APPEAL FROM THE CIRCUIT COURT OF CHRISTIAN COUNTY

Honorable Jennifer Growcock

TRANSFERRED TO THE SUPREME COURT PER RULE 83.02

Opie’s Landscaping, LLC (“Opie”), appeals the bench-trial judgment that ordered

it to pay $40,250 to Fox Creek Construction, Inc. (“Contractor”). In three points, Opie

claims the trial court erred by applying the wrong measure of damages to Contractor’s

breach of contract claim. Because Opie has failed to meet its burden of demonstrating

reversible error, we affirm; however, we transfer this case to our Supreme Court after

opinion pursuant to Rule 83.02. 1

1 All rule references are to Missouri Court Rules (2019).

1 Governing Principles of Review

“In appeals from a court-tried civil case, the trial court’s judgment will be

affirmed unless there is no substantial evidence to support it, it is against the weight of

the evidence, or it erroneously declares or applies the law.” White v. Director of

Revenue, 321 S.W.3d 298, 307-08 (Mo. banc 2010) (citing Murphy v. Carron, 536

S.W.2d 30, 32 (Mo. banc 1976)). We begin with a presumption that the judgment is

correct, and the appellant has the burden of proving it erroneous. Flooring Sys, Inc. v.

Staat Constr. Co., 100 S.W.3d 835, 837 (Mo. App. E.D. 2003).

The Evidence 2

Contractor was engaged by Mike and Annette Ensley (“Homeowners”) to do

some major remodeling of their home. Contractor’s arrangement with Homeowners was

a “cost-plus” contract that required Homeowners to pay Contractor the actual cost of the

work plus 15% of that total cost as Contractor’s profit. One portion of the remodeling

job involved the construction of a waterfall outside of Mrs. Ensley’s library window.

Contractor sub-contracted with Opie to build the waterfall. Although Opie admitted that

it had an oral contract with Contractor, Opie’s brief fails to identify the terms of that

contract.

Although Contractor had not previously used Opie to build a water feature,

“[Opie had] hired a new guy from Wickman’s Garden, Logan, who was specially in –

specialized in water features, and [Opie] was going to get into the water features – putting

in water features with Logan and that Logan could do the job.” Opie gave Contractor an

estimate of $35,000 to build the waterfall. It took Logan approximately one month to

2 Unless otherwise necessary for context, we recite the relevant evidence and the inferences therefrom in the light most favorable to the trial court’s decision. Heubel v. VSV, LLC, 567 S.W.3d 276, 278 n.2 (Mo. App. S.D. 2019).

2 build the waterfall, and once it was completed, Contractor paid Opie the full $35,000

estimated price.

Shortly thereafter, Homeowners returned from a vacation and began experiencing

problems with the waterfall. The first problem was that the waterfall was in the wrong

location. To address the problem, Opie added a second, smaller waterfall that could be

seen from the library.

The next problem arose when Homeowners discovered water “flying” down their

driveway. That led to a discovery that the waterfall leaked – so much so that the pumps

could not pump enough water to keep the waterfall flowing. Two months after the

waterfall was completed, the leak was so bad that Homeowners’ well pump was running

24 hours per day, resulting in large electric bills for June, July, and August. The rocks in

the waterfall were not level and would move around. The liner was also “sticking

outside” and “looked shoddy.” Opie said 3 it had the wrong pumps, the wrong floats, and

the reservoir was too small, but all of those deficiencies would be fixed. Despite those

admissions, Opie continued to claim that the water loss was due solely to natural

evaporation.

Frustrated with the lack of progress, Homeowners contacted Cliff Fitzwater (“Mr.

Fitzwater”), owner of Fitzwater Design, who had extensive experience with water

features. Mr. Fitzwater looked at the waterfall in approximately June 2016. He

described the problems with the waterfall as: (1) a lot of liner showing; (2) the water

falling over natural rock; (3) a water hose was running continuously; and (4) the reservoir

size seemed small. Mr. Fitzwater advised Homeowners to contact Opie to fix the

3 Although Logan was the person actually building the waterfall, it appears that Homeowners would go to Contractor about the problems that kept arising. Contractor would then communicate with Opie, and Opie in turn went to Logan. Opie eventually fired Logan from the job.

3 problems. The only way Mr. Fitzwater would have fixed the waterfall would be to

rebuild it such that it did not fall over the natural rock, a job that would require removing

the existing water feature and building a new one. He estimated the cost of removal and

reconstruction to be approximately “35- to 40-thousand.”

In September 2016, after six months of continuing problems with the waterfall,

Homeowners told Opie to remove it. Opie did so, and Homeowners never paid

Contractor the $35,000 plus 15% profit that Contractor would have received from

Homeowners if the waterfall had functioned correctly.

Contractor made a demand upon Opie to repay Contractor the $35,000 it had paid

for the waterfall, plus the additional 15% profit. When that demand went unmet,

Contractor filed the instant breach-of-contract suit, which prayed for damages in the

amount of $40,250 (the $35,000 paid to Opie, plus Contractor’s 15% lost profit).

The trial court entered its $40,250 judgment in favor of Contractor based upon the

following undisputed evidence:

• Contractor contracted with Homeowners to install a water feature for $35,000 plus 15% profit;

• Contractor subcontracted with Opie to install the water feature for a cost of $35,000.

• Contractor paid $35,000 to Opie upon the installation of the water feature;

• After six months of Opie’s failed attempts to repair the water feature, Homeowners demanded that Opie remove it, which it did;

• Homeowners did not pay Contractor the $35,000 plus 15% profit because Homeowners were not provided with a functioning water feature;

• Opie retained the $35,000 plus all materials used in constructing the water feature; and

4 • Mr. Fitzwater testified that it would cost at least $35,000 to reconstruct a functioning water feature.

This appeal timely followed.

Analysis

For ease of analysis, we address points 1, 2 and 3 together because Opie

complains about the same set of facts in three different ways: first, that the damage

award was a misapplication of law; second, that substantial evidence does not support the

damage award; and, third, that the damage award is against the weight of the evidence.

Point 1 claims the trial court erred in awarding Contractor $40,250 in damages because

such an award constituted a misapplication of the law 4 in that, “under Missouri law, the

proper measure of damages for substantial but defective completion of a construction

contract is the cost of repair[.]” Point 2 claims the trial court erred in awarding

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stom v. St. Clair Corp.
153 S.W.3d 360 (Missouri Court of Appeals, 2005)
Cornejo v. Crawford County
153 S.W.3d 898 (Missouri Court of Appeals, 2005)
Flooring Systems, Inc. v. Staat Construction Co.
100 S.W.3d 835 (Missouri Court of Appeals, 2003)
State Ex Rel. Union Electric Co. v. Barnes
893 S.W.2d 804 (Supreme Court of Missouri, 1995)
Bonney v. Environmental Engineering, Inc.
224 S.W.3d 109 (Missouri Court of Appeals, 2007)
Murphy v. Carron
536 S.W.2d 30 (Supreme Court of Missouri, 1976)
Forney v. Missouri Bridge & Concrete, Inc.
112 S.W.3d 471 (Missouri Court of Appeals, 2003)
Gillham v. LaRue
136 S.W.3d 852 (Missouri Court of Appeals, 2004)
White v. Director of Revenue
321 S.W.3d 298 (Supreme Court of Missouri, 2010)
Fire Sprinklers, Inc. v. Icon Contracting, Inc.
279 S.W.3d 230 (Missouri Court of Appeals, 2009)
Gee v. Payne
939 S.W.2d 383 (Missouri Court of Appeals, 1997)
DOUGLAS WHITE v. R.L. PERSONS CONSTRUCTION, INC., Defendant-Respondent.
503 S.W.3d 339 (Missouri Court of Appeals, 2016)
Kansas City Power & Light Co. v. Bibb & Associates, Inc.
197 S.W.3d 147 (Missouri Court of Appeals, 2006)
Kelley v. Widener Concrete Construction, LLC
401 S.W.3d 531 (Missouri Court of Appeals, 2013)
Brown v. Brown
423 S.W.3d 784 (Supreme Court of Missouri, 2014)
Gabriel v. Saint Joseph, LLC
425 S.W.3d 133 (Missouri Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
FOX CREEK CONSTRUCTION, INC., Plaintiff-Respondent v. OPIE'S LANDSCAPING, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-creek-construction-inc-plaintiff-respondent-v-opies-landscaping-moctapp-2019.