Fire Sprinklers, Inc. v. Icon Contracting, Inc.

279 S.W.3d 230, 2009 Mo. App. LEXIS 342, 2009 WL 679507
CourtMissouri Court of Appeals
DecidedMarch 17, 2009
DocketED 91426
StatusPublished
Cited by11 cases

This text of 279 S.W.3d 230 (Fire Sprinklers, Inc. v. Icon Contracting, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fire Sprinklers, Inc. v. Icon Contracting, Inc., 279 S.W.3d 230, 2009 Mo. App. LEXIS 342, 2009 WL 679507 (Mo. Ct. App. 2009).

Opinion

SHERRI B. SULLIVAN, J.

Introduction

Fire Sprinklers, Inc. (FSI) appeals from the trial court’s judgment in favor of Icon Contracting, Inc. (Icon) for $58,668 on Icon’s counterclaim against FSI for breach of contract. We affirm as modified.

Factual and Procedural Background

U.S. Paint (USP) utilizes, stores, and distributes flammable liquids. In June 2003, Icon entered into an a Subcontract Agreement (Agreement) with FSI pursuant to which FSI agreed to design and install a foam fire protection system for the USP facility in St. Louis. The Agreement declared that time was of the essence and that if FSI failed to commence work as requested or to continue work with adequate manpower or equipment, Icon could terminate the Agreement with 24 hours’ written notice. In the event of such termination, FSI was responsible for reimbursing Icon for the additional costs Icon expended to perform the work.

In the Agreement, FSI agreed to comply with “all codes, statutes, rules and regulations governing the work.” Upon being notified of defects in its work, FSI agreed to remedy the defects within 10 days and, if it failed to do so, Icon was entitled to remedy the defects at FSI’s expense. The Agreement provided that if Icon prevailed in an action arising out of the Agreement, Icon was entitled to recover its reasonable attorney’s fees and costs and expenses incurred in the action.

The fire suppression system plan required approval by the St. Louis Fire Department (Fire Department or the Department) prior to installation. The approval process required (1) submission of a permit application, (2) review of FSI’s design by the Department, (3) upon approval of the design, issuance of a permit by the Department, and (4) upon final inspection and approval of the installed system (the “acceptance test”) by the Department, the “closing out” of the permit.

*232 In July 2003, FSI submitted its design and permit application to the Fire Marshal for review of the plans for compliance with fire codes and standards. In October 2003, the Fire Marshal began reviewing the plans. The Fire Marshal became skeptical about the nature of the materials stored at the facility and put the plans on hold because FSI’s plans reflected the facility stored Class IB liquids while USP had previously represented to the Marshal, albeit incorrectly, that the facility stored a more flammable class of liquids. FSI immediately began efforts to persuade the Fire Marshal that USP was a Class IB facility. FSI eventually succeeded by obtaining a hazard analysis from USP’s insurer. In May 2004, the Fire Marshal began reviewing the plan once again.

In October 2004, the Fire Department completed its review and in November 2004, the Department issued the permit. FSI, however, had begun installing the system prior to obtaining the permit, most likely with the knowledge and approval of Icon and USP.

In December 2004, the Fire Department attended an acceptance test of the system. At that time, the fire pump appeared to pass its flow test but the system as a whole failed due to a lack of documentation showing that the system’s foam component had passed an earlier testing. Sometime after the initial acceptance test, the Fire Department learned that the pump installed and tested was a 1500 gallons per minute (GPM) pump instead of a 1250 GPM pump as represented by FSI. The size of the pump affects other parts of the system, including whether or not an additional water supply is necessary to supply the pump.

The trial court found FSI’s misrepresentation to the Fire Department regarding the flow size of the pump was knowing and intentional, and compounded the existing credibility problems the companies had with the Fire Department. Upon learning of FSI’s misrepresentation, the Fire Marshal proceeded with the approval process very slowly and found additional shortcomings with the fire suppression system.

On February 3, 2005, Icon notified FSI of its dissatisfaction with the incomplete work and lack of approval by the Fire Department, and put FSI on notice that it intended to have FSI’s work reviewed by another company. At that time, FSI had still failed to instill the dual water supply needed for the larger pump as FSI had represented to the Fire Department it would do.

As of March 1, 2005, the system had not passed the Fire Department’s acceptance test. Icon notified FSI by letter that Icon was terminating the Agreement and that the costs it encountered to complete FSI’s work would be at FSI’s expense. On March 14, 2005, FSI filed a mechanic’s lien against the USP property.

In March 2005, Icon hired TVA Fire and Life Safety, Inc. (TVA) to evaluate FSI’s work. Icon also hired Guardian Fire Protection (Guardian) to evaluate the water supply issue and to perform a fire pump test on the USP system. Guardian found that the pump did not have an adequate water supply to meet the flow requirements of the pump. Guardian reported this finding to the Fire Department and the Department concurred that the water supply was inadequate. Icon hired Guardian to install a 6-inch water supply main to supplement the water supply to the pump.

On March 16, 2006, FSI filed an amended petition for mechanic’s lien against USP’s property and a claim in quantum meruit. On November 6, 2006, Icon filed its Amended Answer and Set-off and Counterclaim for Breach of Contract.

*233 On January 25, 2008, the trial court entered its final judgment and order. The court found that FSI materially breached the Agreement by intentionally misrepresenting to the Fire Department the size of the pump installed and by faffing to timely install a new water supply line to the pump. The court found Icon’s termination of the Agreement was justified and that Icon had proved its breach of contract counterclaim by the greater weight of the credible evidence.

The court found that due to FSI’s material breach of the Agreement, Icon had no legal or contractual obligation to pay FSI $46,588 in contract retainage. The court noted that as a result of Icon’s contribution to the overall situation, not all of the additional work to complete the project could be charged to FSI alone and that Icon must bear some responsibility for the additional costs. The court found that Icon’s damages from FSI’s breach of contract were the $42,165 Icon paid to Guardian to install a second water main to adequately supply water to the pump; $850.00 Icon paid to Guardian to conduct an additional pump test; and $1,575 Icon to paid TVA for engineering consultation services. The court granted FSI a set-off of $5,800 for the additional engineering costs incurred by FSI in correcting the flammable liquids classification issues. The court found in favor of USP and against FSI on the mechanic’s lien and awarded Icon $4,878 for the bond costs it incurred to indemnify USP with respect to the lien. The court also awarded Icon $15,000 for reasonable attorney’s fees incurred in connection with the action. In sum, the court entered judgment in favor of Icon for $58,668.

Point on Appeal

On appeal, Appellant argues that the trial court erred in both discharging Icon’s balance owed under the Agreement and affirmatively awarding damages against FSI for Icon’s cost to complete FSI’s work, as it impermissibly yielded Icon a double recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lapponese v. Carts of Colorado, Inc.
422 S.W.3d 396 (Missouri Court of Appeals, 2013)
Anglin Family Investments v. Hobbs
375 S.W.3d 244 (Missouri Court of Appeals, 2012)
Asamoah-Boadu v. State, Office of Administration
328 S.W.3d 790 (Missouri Court of Appeals, 2010)
Greenstreet v. Fairchild
313 S.W.3d 163 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W.3d 230, 2009 Mo. App. LEXIS 342, 2009 WL 679507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fire-sprinklers-inc-v-icon-contracting-inc-moctapp-2009.