KC Excavating & Grading Inc. v. Crane Construction Co.

141 S.W.3d 401, 2004 Mo. App. LEXIS 948, 2004 WL 1439671
CourtMissouri Court of Appeals
DecidedJune 29, 2004
DocketWD 62271
StatusPublished
Cited by14 cases

This text of 141 S.W.3d 401 (KC Excavating & Grading Inc. v. Crane Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KC Excavating & Grading Inc. v. Crane Construction Co., 141 S.W.3d 401, 2004 Mo. App. LEXIS 948, 2004 WL 1439671 (Mo. Ct. App. 2004).

Opinion

PAUL M. SPINDEN, Presiding Judge.

In this construction dispute, a subcontractor, KC Excavating and Grading, Inc., charged the general contractor, Crane Construction Company, with breach of contract after Crane fired it before it had completed excavation of a commercial building site in Warrensburg owned by the trusts of William H. Koch and Phyllis L. Koch. The dispute arose in 1997 when KC Excavating decided that contract documents did not specify the scope of the work properly and Crane concluded that KC Excavating was not working quickly enough.

Apparently because KC Excavating had not signed Crane’s proposed written contract, the parties operated on the basis of an oral contract. During October 1997, KC Excavating notified Crane that, to satisfy the project’s plans and specifications, it would have to excavate more dirt than contract documents indicated. Crane, however, was concerned that KC Excavating was not working quickly enough to keep construction on schedule. Crane told KC Excavating that Crane would consider it to have breached their contract materially if it did not provide written assurances immediately that it would perform its work on time. KC Excavating did not provide the assurances.

On October 14, 1997, amidst continuing disagreement over the amount of excavation required, Crane told KC Excavating not to continue working until the dispute had been resolved. The firms did not resolve the dispute, and, during the following week, Crane terminated its contract with KC Excavating and obtained a replacement subcontractor to complete excavation.

By that time, KC Excavating had excavated 35,000 cubic yards of dirt in addition to what was specified in the contract documents. It spread most of the extra dirt over the property at Crane’s direction and stockpiled the remainder for removal. Crane did not pay it for the additional work or other extra work that Crane had requested. Crane also did not pay for a portion of the work indicated in the project’s plans and specifications that KC Excavating contracted to complete for the sum stated in its amended bid.

KC Excavating filed a mechanic’s lien on the property and filed this lawsuit to enforce the lien, to collect damages from Crane for breach of contract, and to collect in quantum meruit from all defendants the reasonable value of its services not covered by contract. The circuit court issued judgment for KC Excavating for $220,435.86, plus costs of the action, on each count. The defendants appeal.

Because this was a court-tried case, the standard set forth in Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976), governs our review: We must affirm the judgment unless it is not supported by substantial evidence, is against the weight of evidence, erroneously declares the law, or erroneously applies the law. Because the circuit court did not make findings of fact, we deem it to have resolved factual disputes in *405 accord with its judgment. Weaks v. Rupp, 966 S.W.2d 387, 392 (Mo.App.1998).

In its first point, Crane argues that the circuit court erred in ruling that it had breached its contract with KC Excavating because KC Excavating was the party who had failed to perform its contractual obligations and thereby relieved it of its obligation to perform. Crane argues that KC Excavating breached the contract by walking off the job, by not attending to burn pits, by leaving the job site early each afternoon during construction, and by taking more than a day to aerate the soil after rains. We find no merit to the claim.

First, the record contains sufficient evidence to support the circuit court’s apparent conclusion that KC Excavating did not walk off the job. KC Excavating’s president Gary Wyatt testified that his company stopped working because Crane’s representative told him not to do any more work until the firms had resolved their dispute concerning additional excavation. He said that KC Excavating did not complete the work because Crane terminated the contract before it could do the work. Faced with conflicting evidence, the circuit court had the discretion to determine witness credibility and to accept all, none, or some portion of the witnesses’ testimony. Leonard v. Leonard, 112 S.W.3d 30, 32 (Mo.App.2003).

Second, even had KC Excavating acted as Crane alleged and even had those acts violated the contract, the acts did not bar KC Excavating from recovering under the contract. A central issue in resolving a claim of breach of contract is materiality of the alleged breach. That Crane was dissatisfied with KC Excavating’s work or even that KC Excavating had breached the contract did not excuse Crane’s performance unless KC Excavating’s breach was material. Health Related Services, Inc. v. Golden Plains Convalescent Center, Inc., 806 S.W.2d 102, 105 (Mo.App.1991). A party cannot claim the benefit of a contract that it was the first to breach, but this rule applies only when the breach is material. Classic Kitchens and Interiors v. Johnson, 110 S.W.3d 412, 417 (Mo.App.2003). We find nothing in this record supporting Crane’s contentions that KC Excavating was obligated to be on the job site during certain hours, attend to its burn pits, or aerate the soil on any particular schedule. It may have been, but Crane did not establish at trial that KC Excavating had those obligations, but, of more significance, even had KC Excavating been required to do these things, Crane did not establish that KC Excavating’s not doing them was material.

This leaves Crane’s argument that KC Excavating was not entitled to recover additional sums under the contract. Crane first argues that the contract was a lump-sum contract, paying KC Excavating $98,297 for all the work necessary, and that it could not recover additional sums even had it encountered additional work. It further argues that KC Excavating was required to obtain a change order for extra work. 1

The parties’ contract apparently was oral and was supported by written contract documents, including KC Exeavating’s bid, *406 the plans and specifications, and Crane’s letter of acceptance. Crane submitted a formal, written contract to KC Excavating for signing, but KC Excavating did not sign it. KC Excavating asserts that it never received it. In any event, neither party contends in this appeal that the parties executed a signed, written contract governing their business deal. Instead, they tried the case on the basis that their agreement was reflected in various other documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CHRISTOPHER J. GARDNER v. CATHY J. GARDNER
Missouri Court of Appeals, 2024
Superior Edge, Inc. v. Monsanto Co.
44 F. Supp. 3d 890 (D. Minnesota, 2014)
APAC-Missouri, Inc. v. Boyer
420 S.W.3d 651 (Missouri Court of Appeals, 2013)
City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115 (Missouri Court of Appeals, 2013)
Clean the Uniform Co. St. Louis v. Magic Touch Cleaning, Inc.
300 S.W.3d 602 (Missouri Court of Appeals, 2009)
Fire Sprinklers, Inc. v. Icon Contracting, Inc.
279 S.W.3d 230 (Missouri Court of Appeals, 2009)
Guidry v. Charter Communications, Inc.
269 S.W.3d 520 (Missouri Court of Appeals, 2008)
Hadley v. Burton
265 S.W.3d 361 (Missouri Court of Appeals, 2008)
Porter v. Director of Revenue
168 S.W.3d 147 (Missouri Court of Appeals, 2005)
A & L Underground, Inc. v. Leigh Construction, Inc.
162 S.W.3d 509 (Missouri Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
141 S.W.3d 401, 2004 Mo. App. LEXIS 948, 2004 WL 1439671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kc-excavating-grading-inc-v-crane-construction-co-moctapp-2004.