Graber, Inc. v. W&Z Contracting Construction, LLC

CourtDistrict Court, E.D. Missouri
DecidedDecember 15, 2021
Docket4:19-cv-00067
StatusUnknown

This text of Graber, Inc. v. W&Z Contracting Construction, LLC (Graber, Inc. v. W&Z Contracting Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graber, Inc. v. W&Z Contracting Construction, LLC, (E.D. Mo. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

GRABER, INC., ) ) Plaintiff, ) ) v. ) ) W&Z CONTRACTING ) CONSTRUCTION, LLC, et al., ) ) Defendants; ) _________________________________ ) No. 4:19 CV 67 CDP ) W&Z CONTRACTING ) CONSTRUCTION, LLC, ) ) Counterclaim Plaintiff, ) ) v. ) ) GRABER, INC., ) ) Counterclaim Defendant. )

MEMORANDUM AND ORDER

Plaintiff Graber, Inc., a construction contractor, seeks summary judgment against defendant W&Z Contracting Construction LLC on both W&Z’s amended counterclaim against Graber, Inc. and on Graber, Inc.’s affirmative claims against W&Z, who is in default for failure to defend. Graber, Inc. alleges that it hired W&Z as a subcontractor on a project and that W&Z breached the contract by charging more than the contracted flat fee. Graber, Inc. also alleges that W&Z injured its economic interests by serving on the property owner a notice of mechanic’s lien that falsely claimed that Graber, Inc. owed W&Z more than

$112,000 under the contract. Graber, Inc.’s problem, however, is that the evidence of record does not show that W&Z served a notice or filed a mechanic’s lien alleging nonpayment by Graber, Inc. What the evidence does show is that W&Z

never submitted invoices to Graber, Inc., and that W&Z served a notice on the property owner and filed a mechanic’s lien stating that another subcontractor, MidAmerican Construction Management, had failed to pay it for labor and materials under its contract with MidAmerican.

W&Z’s separate contract with MidAmerican and its alleged breach is the subject of W&Z’s amended counterclaim. I will grant Graber, Inc.’s motion for summary judgment on W&Z’s

amended counterclaim because the evidence shows that Graber, Inc. was not a party to nor did it receive any benefit from the MidAmerican contract W&Z claims was breached. I will deny Graber, Inc.’s motion for summary judgment on its own claims of breach of contract and injurious falsehood raised against W&Z in the

complaint, as the evidence does not show that Graber, Inc. is entitled to judgment as a matter of law on these claims. Because the evidence actually contradicts what Graber, Inc. would have to present to prove all of the claims in its complaint –

given the undisputed fact that the lien and invoices were not directed to and did not reference Graber, Inc. but instead involved a non-party to this case – I will also direct Graber, Inc. to show cause why summary judgment should not be granted

against it on all claims in its complaint. Background In May 2018, Graber, Inc. entered into a written contract with defendant

W&Z whereby W&Z, through its sole member, defendant Wilmer Urbina Gutierrez, agreed to perform certain work in relation to a construction project in exchange for a lump-sum amount of $30,000. In this diversity action against W&Z and Gutierrez, Graber, Inc. alleges that W&Z breached the contract by charging

$82,330 more than what it agreed to accept for the scope of work outlined in the contract (Count I); that W&Z and Gutierrez injured Graber, Inc.’s economic interests by serving upon the Project Owner a Notice to Owner of Claim of

Mechanic’s Lien containing false information that Graber, Inc. failed to pay W&Z for its work, thereby causing the Project Owner to stop payments to and cancel its contracts with Graber, Inc. (Count II)1; and that W&Z and Gutierrez tortiously interfered with Graber, Inc.’s contracts with the Project Owner by serving the

Notice to Owner that contained false information (Count III). The contract at issue, the Notice to Owner, and the Mechanic’s Lien are attached as exhibits to

1 Graber, Inc. admits that the complaint errantly denoted this claim as “Count III” and avers that it should be considered “Count II.” (See ECF 94 at p. 14, n.5.) I will therefore refer to this claim as Count II in this memorandum. Graber, Inc.’s complaint and are considered a part of the complaint for all purposes. Fed. R. Civ. P. 10(c).

Graber, Inc. now moves for summary judgment against W&Z on Counts I and II of its complaint, asserting that it is entitled to $359,699.11 in damages and attorneys’ fees on these claims.2 Graber, Inc. also moves for summary judgment

on W&Z’s amended counterclaim in which W&Z alleges that Graber, Inc. breached a separate Third Tier Subcontract and, further, seeks recovery from Graber, Inc. under the theory of quantum meruit. The Third Tier Subcontract is attached as an exhibit to the Amended Counterclaim (ECF 21-1). W&Z has not

responded to Graber, Inc.’s motion for summary judgment, and the time to do so has passed. For the reasons that follow, Graber, Inc. is not entitled to judgment as a

matter of law on its claims of breach of contract and injurious falsehood against W&Z. I will therefore deny its motion for summary judgment to the extent it is directed to Counts I and II of its complaint against W&Z. I will, however, grant its motion for summary judgment to the extent it is directed to W&Z’s amended

counterclaim. W&Z has been unrepresented in this action since March 2021 and has given

2 Graber, Inc.’s motion for summary judgment does not address its claim of tortious interference with contract raised in Count III of the complaint, nor does it address any of its claims to the extent they are raised against defendant Gutierriez. no indication that it intends to retain counsel for any further proceedings in the case. Because an LLC cannot proceed pro se, I will direct the clerk of court to

enter default against W&Z under Rule 55(a), Federal Rules of Civil Procedure, for failure to defend. But as will be evident by the discussion below, liability is not deemed established simply because of W&Z’s default. See 10A, Wright & Miller,

Fed. Prac. & Proc. Civ. § 2688.1 (4th ed. 2021) (Court’s Entry of a Default Judgment—Effect of Default on Proof Requirements). Indeed, to the contrary, the admissible evidence before the Court appears to show that Graber, Inc. cannot recover against either W&Z or Gutierrez on any of its claims raised in its

complaint. I will therefore order Graber, Inc. to show cause why I should not enter summary judgment against it under Rule 56(f)(3), Federal Rules of Civil Procedure.

Summary Judgment Standard Summary judgment must be granted when the pleadings and proffer of evidence demonstrate that no genuine issue of material fact exists and that the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a);

Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986); Torgerson v. City of Rochester, 643 F.3d 1031, 1042 (8th Cir. 2011) (en banc). I must view the evidence in the light most favorable to the nonmoving party and accord it the

benefit of all reasonable inferences. Scott v. Harris, 550 U.S. 372, 379 (2007). Initially, the moving party must demonstrate the absence of an issue for trial. Celotex, 477 U.S. at 323. Once a motion is properly made and supported, the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Marshall v. Baggett
616 F.3d 849 (Eighth Circuit, 2010)
Conseco Life Insurance v. Williams
620 F.3d 902 (Eighth Circuit, 2010)
Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Shaver v. Independent Stave Company
350 F.3d 716 (Eighth Circuit, 2003)
Jon R. Tollefson v. DeAnn Marie Pladson
508 F. App'x 593 (Eighth Circuit, 2013)
Murray v. Lene
595 F.3d 868 (Eighth Circuit, 2010)
JB Contracting, Inc. v. Bierman
147 S.W.3d 814 (Missouri Court of Appeals, 2004)
KC Excavating & Grading Inc. v. Crane Construction Co.
141 S.W.3d 401 (Missouri Court of Appeals, 2004)
Keveney v. Missouri Military Academy
304 S.W.3d 98 (Supreme Court of Missouri, 2010)
Miller v. Kasden (In Re Kasden)
209 B.R. 236 (Eighth Circuit, 1997)
Kahn v. Prahl
414 S.W.2d 269 (Supreme Court of Missouri, 1967)
Woods v. Wills
400 F. Supp. 2d 1145 (E.D. Missouri, 2005)
MECO Systems, Inc. v. Dancing Bear Entertainment, Inc.
42 S.W.3d 794 (Missouri Court of Appeals, 2001)
Wandersee v. BP Products North America, Inc.
263 S.W.3d 623 (Supreme Court of Missouri, 2008)
Pearson v. AVO General Services, LLC
520 S.W.3d 496 (Missouri Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Graber, Inc. v. W&Z Contracting Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graber-inc-v-wz-contracting-construction-llc-moed-2021.