Graber, Inc. v. W&Z Contracting Construction, LLC

CourtDistrict Court, E.D. Missouri
DecidedMarch 24, 2022
Docket4:19-cv-00067
StatusUnknown

This text of Graber, Inc. v. W&Z Contracting Construction, LLC (Graber, Inc. v. W&Z Contracting Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graber, Inc. v. W&Z Contracting Construction, LLC, (E.D. Mo. 2022).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

GRABER, INC., ) ) Plaintiff, ) ) v. ) ) W&Z CONTRACTING ) CONSTRUCTION, LLC, et al., ) ) Defendants; ) _________________________________ ) No. 4:19 CV 67 CDP ) W&Z CONTRACTING ) CONSTRUCTION, LLC, ) ) Counterclaim Plaintiff, ) ) v. ) ) GRABER, INC., ) ) Counterclaim Defendant. )

MEMORANDUM AND ORDER

This matter is before the Court for consideration of summary judgment pursuant to Rule 56(f)(3), Federal Rules of Civil Procedure. Because plaintiff Graber, Inc. has presented no evidence demonstrating that it may obtain relief on the factual allegations and legal theories raised in its complaint, I will enter summary judgment against it under Rule 56(f)(3) and dismiss its complaint in its entirety with prejudice. Background1 After being granted additional time to do so, plaintiff Graber, Inc. filed a

motion for summary judgment in May 20212 asserting it was entitled to judgment as a matter of law on Counts I and II of its three-count complaint against defendant W&Z Contracting Construction, LLC. Graber, Inc. did not seek summary

judgment on Count III of its complaint or against the other defendant it sued in this case, Wilmer Urbina Guttieriez. On December 15, 2021, I denied Graber, Inc.’s motion to the extent it was directed to Counts I and II of its complaint3 and, upon consideration of the admissible evidence presented, I ordered Graber, Inc. to show

cause why summary judgment should not be granted against it on all of its claims pursuant to Rule 56(f)(3), which permits the Court to consider summary judgment on its own after identifying material facts that may not be genuinely in dispute.

(See ECF 96.) Graber, Inc. responded to the show cause order on February 7, 2022. Upon review of Graber, Inc.’s complaint, the admissible evidence before the Court, and Graber, Inc.’s additional briefing, I will enter summary judgment

1 The circumstances giving rise to this litigation and the procedural history leading up to its present status are thoroughly set out in my Memorandum and Order entered December 15, 2021 (see ECF 96) and will not be repeated here except where necessary for purposes of discussion. 2 Under the operative Case Management Order, any motions for summary judgment were due to be filed not later than July 23, 2020. (ECF 70.)

3 I granted the motion to the extent it was directed to W&Z’s amended counterclaim. pursuant to Rule 56(f)(3) against Graber, Inc. on all claims raised in its complaint as to both defendants, and I will dismiss the complaint with prejudice.

Counts I and II Against Defendant W&Z Graber, Inc. filed its complaint in this action on January 16, 2019, alleging that on May 11, 2018, it entered into a written Labor Subcontract Agreement

(“Agreement”) with defendant W&Z whereby W&Z, through its sole member, defendant Gutierrez, agreed to perform certain work in relation to a construction project in exchange for a lump-sum payment of $30,000. The complaint further alleges that on July 2, 2018, W&Z served on the Project Owner a Notice to Owner

of Claim of Mechanic’s Lien (“Notice to Owner” or “Notice”) asserting a claim of $112,330 for its work on the project. The complaint alleges that as a result of the Notice to Owner, the Project Owner withheld monetary payments to Graber, Inc.

and discharged it from the Project. Finally, the complaint alleges that W&Z filed a Mechanic’s Lien in the amount of $112,330 on October 1, 2018, claiming that it was to be paid on a time-and-materials basis. Attached to the complaint are the Agreement, the Notice to Owner, and the Mechanic’s Lien. There are no other

substantive attachments to the complaint. Based on these factual allegations, Count I of Graber, Inc.’s complaint asserts a breach-of-contract claim contending that W&Z breached the terms of the

Labor Subcontract Agreement “by charging $82,330 more than it agreed to accept in its Scope of Work.” (ECF 1 at ¶ 32.) Although inartfully pled, Graber, Inc. contends that W&Z’s claim for $112,330 in the Mechanic’s Lien constituted the

overcharge. (See id. at ¶ 31.) Count II asserts a claim of injurious falsehood, contending that W&Z knowingly made false statements in the Notice to Owner by: 1) falsely conveying that it had submitted invoices to Graber, Inc. that totaled

$112,330, which contradicted the lump-sum payment term of the Agreement; and 2) falsely implying that Graber, Inc. had failed to pay W&Z for its work performed on the Project. Count II asserts that these false statements caused the Project Owner to believe that Graber, Inc. had failed to pay W&Z for work performed,

resulting in the Project Owner stopping payments to and canceling its contracts with Graber, Inc., thereby causing pecuniary loss to Graber, Inc. (Id. at ¶¶ 37-47.) As discussed in my December 15 Memorandum and Order, no evidence

before the Court on Graber, Inc.’s motion for summary judgment showed that W&Z charged Graber, Inc. $112,330 for its work or that W&Z sought to recover $112,330 under the Labor Subcontract Agreement. Moreover, the admissible evidence showed that W&Z claimed in the Notice to Owner and Mechanic’s Lien

that it was owed $112,330 pursuant to a separate Third Tier Subcontract (“Subcontract”) with another entity, MidAmerican Construction Management, and not pursuant to the Agreement with Graber, Inc. Therefore, because the evidence

showed that W&Z neither sought $112,330 from Graber, Inc. under the Agreement nor asserted that Graber, Inc. owed it $112,330 under the Agreement, I denied Graber, Inc.’s motion for summary judgment as to Count I of its complaint. (ECF

96 at pp. 15-17.) As further discussed in the Memorandum and Order, the admissible evidence submitted on Graber, Inc.’s motion for summary judgment showed that

neither the Notice to Owner nor the Mechanic’s Lien contained the false statements that Graber, Inc. attributed to W&Z. Instead, the undisputed evidence showed that the Notice and Mechanic’s Lien asserted that only MidAmerican owed monies to W&Z under W&Z’s separate contract with MidAmerican. There was no

assertion that Graber, Inc. owed W&Z monies; nor was there any conveyance that W&Z submitted invoices totaling $112,330 to Graber, Inc. that went unpaid. Accordingly, because the Notice’s allegation of unpaid accounts was directed to

only MidAmerican and not to Graber, Inc., the Notice did not contain the purported false statements that Graber, Inc. asserted in its complaint, and thus there was no evidence that Graber, Inc.’s pecuniary losses were caused by the purported false statements. I therefore denied Graber, Inc.’s motion as to Count II of its

complaint. (ECF 96 at pp. 17-19.) In determining Graber, Inc.’s motion for summary judgment, I reviewed the entirety of Graber, Inc.’s complaint against the backdrop of admissible evidence on

the motion. From my review, it appeared that Graber, Inc. could not recover as a matter of law on any of its claims. I therefore invited Graber, Inc. to show cause why summary judgment should not be entered against it on all of the claims raised

in its complaint. In response, Graber, Inc. again addressed only Counts I and II of its complaint and only as to defendant W&Z.4 In its response, Graber, Inc. admittedly raises a new legal theory that it did not raise in its earlier motion for summary judgment,5 that is, that the Notice to

Owner and the Mechanic’s Lien could not have been based on W&Z’s Third Tier Subcontract with MidAmerican because that Subcontract was invalid per se. Specifically, Graber, Inc. now contends that the Subcontract between W&Z and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kneibert Clinic, LLC v. Smith
610 F.3d 1019 (Eighth Circuit, 2010)
Satcher v. UNIVERSITY OF ARK. AT PINE BLUFF BD.
558 F.3d 731 (Eighth Circuit, 2009)
Lovelle Banks v. John Deere and Company
829 F.3d 661 (Eighth Circuit, 2016)
Hanover Insurance v. Cameron Country Mutual Insurance
730 F. Supp. 998 (E.D. Missouri, 1990)
Downing v. Riceland Foods, Inc.
298 F.R.D. 587 (E.D. Missouri, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Graber, Inc. v. W&Z Contracting Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graber-inc-v-wz-contracting-construction-llc-moed-2022.