Werner v. Ashcraft Bloomquist, Inc.

10 S.W.3d 575, 2000 Mo. App. LEXIS 122, 2000 WL 51821
CourtMissouri Court of Appeals
DecidedJanuary 25, 2000
DocketED 75617
StatusPublished
Cited by9 cases

This text of 10 S.W.3d 575 (Werner v. Ashcraft Bloomquist, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Werner v. Ashcraft Bloomquist, Inc., 10 S.W.3d 575, 2000 Mo. App. LEXIS 122, 2000 WL 51821 (Mo. Ct. App. 2000).

Opinion

WILLIAM H. CRANDALL, Jr., Presiding Judge.

Defendant, Ashcraft Bloomquist, Inc. (hereinafter ABI), appeals from the judgment of the trial court, entered in a court-tried case, in favor of plaintiff, Richard C. Werner, d/b/a Neon City Sign and Electric Company (hereinafter Werner), in a breach of contract action. We affirm.

ABI entered into a contract with the owner of Fenton Plaza, Diversified Developers Realty Corp. (hereinafter Diversified), whereby it agreed to be the general contractor on a remodeling project for the shopping center. ABI entered into a subcontract with Werner to “remove and reinstall all store front signage with union labor” for a total price of $26,700.00. The contract was for labor only; no materials were included. Pursuant to the contract, Werner removed the signs and was paid $13,260.00 for that work.

Thereafter, Diversified determined that it wanted new signs and in accordance with its contract with ABI entered a change order to delete the reinstallation of the signs from its contract with ABI. ABI informed Werner that it was discontinuing its contract with him. Werner brought this action for, inter alia, breach of contract. The trial court found that ABI had breached the contract and awarded damages to Werner in the amount of $13,-400.00.

Our standard of review in a court-tried case is enunciated in Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976).

In its first point on appeal, ABI challenges the trial court’s finding that it breached its contract with Werner for the *577 reason that the doctrines of impossibility of performance and/or commercial frustration excused its performance. ABI argues that because “Diversified exercised its right to enter a change order and removed all remaining signage work from ABI’s contract,” it “no longer had the right or ability to allow Werner to perform that work” under the contract at issue.

The doctrine of impossibility of performance excuses a party to a contract from performance when an Act of God, the law, or the other party renders performance impossible. Grannemann v. Columbia Ins. Group, 931 S.W.2d 502, 506 (Mo.App. W.D.1996). If a party desires to be excused from performance in the event of contingencies arising after the formation of a contract, it is that party’s duty to provide therefore in the contract. Stein v. Bruce, 366 S.W.2d 732, 734 (Mo.App.1963).

The change order by Diversified is not the type of unexpected event warranting consideration of the application of the impossibility of performance doctrine. See, e.g., West Los Angeles Institute for Cancer Research v. Mayer, 366 F.2d 220 (9th Cir.1966) (change in the law in the form of a revenue ruling); Lake Development Enterprises, Inc. v. Kojetinsky, 410 S.W.2d 361 (Mo.App.1966) (Act of God in the form of freezing temperatures); Stein v. Bruce, 366 S.W.2d at 732 (death of a party). Furthermore, ABI made no provision for the termination of its obligation under its contract with Werner in the event Diversified entered a change order regarding the removal or reinstallation of the signs. See, e.g., Sanfillippo v. Oehler, 869 S.W.2d 159 (Mo.App.E.D.1993) (because the non-competition agreement did not provide for termination of his obligation upon the death of the dentist from whom he purchased the assets of a dental practice, dentist-purchaser was not excused from paying under the non-compete agreement).

In addition, the ultimate question is whether or not the nature of the contract and the surrounding circumstances show that the risk of the subsequent events, whether or not foreseen, was assumed by the promisor. West Los Angeles Institute for Cancer Research, 366 F.2d at 225. In the case before us, it appears from the nature of ABI’s contract with Werner and from the surrounding circumstances that ABI assumed the risk of a change order by Diversified after it contracted with Werner. As between ABI and Werner, ABI was in the better position to anticipate the frustrating event of a change order. ABI’s failure to make provision for that contingency in its contract with Wer-ner indicated its assumption of the risk that a change order might occur which could impair its contract with Werner.

ABI alternatively argues commercial frustration as a basis for discharging its performance under its contract with Werner. Under the doctrine of commercial frustration, if the happening of an event not foreseen by the parties and not caused by or under the control of either party has destroyed or nearly destroyed either the value of the performance or the object or purpose of the contract, then the parties are excused from further performance. Howard v. Nicholson, 556 S.W.2d 477, 482 (Mo.App.1977). The doctrine of commercial frustration is close to but distinct from the doctrine of impossibility of performance. Id. Both concern the effect of supervening circumstances upon the rights and duties of the parties; but in cases of commercial frustration, performance remains possible but the expected value of performance in the party seeking to be excused has been destroyed by the fortuitous event which supervenes to cause an actual but not literal failure of consideration. Id.

If the event was reasonably foreseeable, however, the parties should have provided for its occurrence in the contract and the absence of such provision indicates an assumption of risk by the promisor. Id. Courts consider the relation of the parties, the terms of the contract, and the circumstances surrounding the formation *578 of the contract in determining whether the supervening event was reasonably foreseeable. Id.

The doctrine of commercial frustration is not applicable in this case. It was foreseeable to ABI at the time ABI entered into its contract with Werner that Diversified might enter a change order to the original contract with ABI that could impair performance under ABI’s contract with Werner. In Conlon Group, Inc. v. City of St. Louis, 980 S.W.2d 37, 40-41 (Mo.App. E.D.1998), cert. denied, — U.S. -, 119 S.Ct. 1786, 143 L.Ed.2d 814 (1999), this court declined to find commercial frustration where the structural problems in a 100-year-old building were foreseeable. This court concluded that the purpose of the agreement with the city’s redevelopment authority remained intact, despite the increased costs of redevelopment project. Id. In Shop ‘N Save Warehouse Foods, Inc. v. Soffer,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clean the Uniform Co. St. Louis v. Magic Touch Cleaning, Inc.
300 S.W.3d 602 (Missouri Court of Appeals, 2009)
Richardson v. Richardson
218 S.W.3d 426 (Supreme Court of Missouri, 2007)
Minor v. Rush
216 S.W.3d 210 (Missouri Court of Appeals, 2007)
Forney v. Missouri Bridge & Concrete, Inc.
112 S.W.3d 471 (Missouri Court of Appeals, 2003)
Adbar, L.C. v. New Beginnings C-Star
103 S.W.3d 799 (Missouri Court of Appeals, 2003)
Liquidation of Professional Medical Insurance Co. v. Lakin
88 S.W.3d 471 (Missouri Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
10 S.W.3d 575, 2000 Mo. App. LEXIS 122, 2000 WL 51821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/werner-v-ashcraft-bloomquist-inc-moctapp-2000.