Jensen v. Manthe

95 N.W.2d 699, 168 Neb. 361, 1959 Neb. LEXIS 36
CourtNebraska Supreme Court
DecidedApril 3, 1959
Docket34552
StatusPublished
Cited by11 cases

This text of 95 N.W.2d 699 (Jensen v. Manthe) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jensen v. Manthe, 95 N.W.2d 699, 168 Neb. 361, 1959 Neb. LEXIS 36 (Neb. 1959).

Opinion

Carter, J.

Plaintiff brought this action to foreclose a mechanic’s lien in the amount of $821.89. The defendants alleged that plaintiff entered into an oral contract to construct a house on the property here involved; asserted that the amount had been fully paid; and asserted that plaintiff therefore had no basis for a lien. The defendants, by cross-petition, alleged that plaintiff failed to complete the' house in accordance with his contract and that they were compelled to expend $1,137.20 to complete if; and prayed for a judgment in that amount. The trial court found for the plaintiff and against the defendants and directed *362 a foreclosure of the mechanic’s lien in the amount of $528.08 with interest at 6 percent from August 14, 1957. The defendants have appealed.

In September 1955, the defendants desired to build a new house on the real estate described in the petition. They found a rough drawing of a house in a book of house plans which appeared to meet their desires. They took the drawing to plaintiff to determine the cost of constructing such a house. Plaintiff estimated that it would cost $15,000. Plaintiff informed defendants that an accurate estimate could not be made until detailed plans had been prepared. The parties agreed to have plans prepared, which was done. Thereafter plaintiff submitted the plans to subcontractors and obtained bids from them. He then approached the defendants and offered to contract for the building of the house for $15,000. The defendants declined to enter into such a contract because they could not afford to put that much money into the house. Negotiations were then commenced to reduce the cost of the house.

Plaintiff submitted a written estimate based on the following: Excavation, $100; cement work, $1,200; material, $4,800; plumbing and heating, $2,200; painting labor, $585; paint, $300; floor covering, $1,280; electrical work and fixtures, $378; and labor, $3,600; a total of $14,443. The plaintiff indicated that an additional charge of $225 for labor on the fireplace should be added. Plaintiff stated that after calling the lumber dealer and obtaining a 5 percent discount on the lumber, and the defendants agreeing to do the inside painting, the defendants said to go ahead with the construction. Plaintiff testified that he told defendants the figures were an estimate only and that it would not vary more than 10 percent either way.

The defendants testified that the negotiations between the parties occurred generally as testified to by the plaintiff. Their evidence, however, is to the effect that after securing the 5 percent discount on the lumber, *363 and the defendants agreeing to do the inside painting, the plaintiff agreed to build the house for $14,200.

Whether or not there was a meeting of the minds of the parties on a firm contract to construct the house for $14,200 constitutes the primary issue in the case. The evidence of the parties on that point is in direct conflict.

There is evidence in the record, however, which indicates what the parties intended. The manner in which the parties interpreted the agreement before the dispute arose is ordinarily a safe guide in determining the true nature of the contract.

Plans were prepared as a guide to the construction of the house. Specifications as to materials to be used or the type of appliances to be installed were never provided. We think it would be unusual for a builder to enter into the construction of a house under a firm contract at such an amount without complete plans and specifications. The evidence shows that the defendants paid subcontractors direct. The plaintiff testified that this was because the defendants desired to select the subcontractors and secure those who would give them discounts on the cost. Defendants testified that they paid subcontractors to relieve plaintiff of the necessity of borrowing money at the bank, a matter which was of no concern to them if the house was being built under a firm contract. Ordinarily, direct payment of subcontractors by the owner is evidence that no firm contract was agreed upon. See Timmons v. Nelsen, 159 Neb. 193, 66 N. W. 2d 406. There is evidence that plaintiff went to the defendants and told them they could save on materials and labor by using cement stone instead of tile in the foundation. They approved, stating that they desired to save money wherever they could. The plaintiff suggested using cement stones instead of brick in the fireplace for the same reasons and defendants approved the savings. These instances are clearly incon *364 sistent with defendants’ contentions that a firm contract was made.

The defendants contend, on the other hand, that they paid subcontractors only on the approval of - the plaintiff. It seems to us, however, that plaintiff as the builder, was obliged to approve such payments as a protection to the owner, whether or not he was working under a firm contract or on a time and material cost basis. The record shows also that all of the inside painting was not done by the defendants and that there was no discussion as to the effect of this on the amount of the alleged firm contract. There was no discussion as to the effect upon the alleged firm contract of savings made with subcontractors other than those the plaintiff had procured during the preliminary negotiations.

The trial court saw and heard the witnesses as they testified. It had a better opportunity to appraise the credibility of the witnesses than does this court. The trial court resolved the conflicting evidence in favor of the plaintiff. While this court tries appeals in equity de novo, we must necessarily consider the findings of the trial judge on matters that are in irreconcilable conflict. Wilkie v. Banse, 166 Neb. 138, 88 N. W. 2d 181; Marston v. Drobny, 166 Neb. 747, 90 N. W. 2d 408. For the reasons stated, the record supports a finding that there was no firm contract to construct the house for $14,200 which resulted from a definite offer and unconditional acceptance by the parties. The agreement was for the construction of the house on a “time and materials” cost basis as plaintiff contended.

The evidence shows that plaintiff received a discount of 5 percent on the materials purchased from the lumber dealer which amounted to $293.01. The defendants are entitled to credit for the amount of this discount. Grothe v. Erickson, 157 Neb. 248, 59 N. W. 2d 368. It is the general rule that the profits made and advantages gained by a builder in the execution of work on a cost basis belong to the owner, in the absence of an agreement *365 to the contrary. 2 Am. Jur., Agency, § 268, p. 215.

The defendants contend that they are entitled to credit for overcharges made by plaintiff for the labor employed to construct the house. This contention is based on the wages paid to employees Gard, Bickford, Bruening, Laue, and Forsburg. The evidence shows that Gard worked 125 hours and was paid $1.75 per hour. The defendants were charged $2 per hour for the work performed by Gard. Similar increased charges were made on the wages paid the other employees named, the total amount of the added charges being $491.15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Basin Electric Power Cooperative
248 F.3d 781 (Eighth Circuit, 2001)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
KNOELL CONST. CO., INC. v. Hanson
287 N.W.2d 435 (Nebraska Supreme Court, 1980)
Brandt v. Mayer
246 N.W.2d 203 (Nebraska Supreme Court, 1976)
HD Fager Oil Co., Inc. v. VAINCE
224 N.W.2d 372 (Nebraska Supreme Court, 1974)
LaPuzza v. Prom Town House Motor Inn, Inc.
217 N.W.2d 472 (Nebraska Supreme Court, 1974)
Conditioned Air Corp. v. Rock Island Motor Transit Co.
114 N.W.2d 304 (Supreme Court of Iowa, 1962)
State Ex Rel. Nebraska State Bar Ass'n v. Jensen
105 N.W.2d 459 (Nebraska Supreme Court, 1960)
Bailey v. Karnopp
104 N.W.2d 417 (Nebraska Supreme Court, 1960)
Dunbier v. Rafert
103 N.W.2d 814 (Nebraska Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.W.2d 699, 168 Neb. 361, 1959 Neb. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jensen-v-manthe-neb-1959.