Rivett Lumber & Coal Co. v. Linder

204 N.W. 77, 113 Neb. 567, 1925 Neb. LEXIS 152
CourtNebraska Supreme Court
DecidedMay 23, 1925
DocketNo. 23152
StatusPublished
Cited by7 cases

This text of 204 N.W. 77 (Rivett Lumber & Coal Co. v. Linder) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivett Lumber & Coal Co. v. Linder, 204 N.W. 77, 113 Neb. 567, 1925 Neb. LEXIS 152 (Neb. 1925).

Opinion

Evans, J.

' This is an action to foreclose a mechanics’ lien. There was a judgment for the plaintiff, from which the defendant Anton P. Linder (hereinafter called the owner) appeals. The defendant John J. Healy (hereinafter called the contractor) entered into a contract with the owner for the erection of three dwelling-houses on lots No. 10, No. 11, and No. 12, block 5, in Kirkwood addition to Omaha, and described in the evidence as Nineteenth and Manderson streets. At the time of entering into the contract the three lots had thereon three dwellings and a garage. One of the old buildings was on lot No. 10, and two were on lot No. 12. The garage was on lot No. 11. Two of the new dwellings were placed on lot No. 12 and one on lot No. 11. During the performance of the contract for the construction of the dwellings a garage was constructed by the contractor on [569]*569lot No. 10 and certain repairs made upon the old dwellings. The contract for the construction of the dwellings did not, in express terms, provide for the building of a garage. The contract, however, by its terms fixes the second payment thereunder, and provided for therein, as due upon completion of the garage; and, with the plans, which were in contemplation at the time the contract was made, is a sketch or outlined plan for a garage, and the specifications fix certain requirements as to it. The contract in no way affects or mentions the repairs made on the old dwelling-houses. The plaintiff furnished the material required for the construction of the three new dwelling-houses, the new garage, and for the repairs to the old dwelling-houses, and on January 7, 1920, filed a written statement under oath, in the office of the register of deeds of Douglas county, claiming a mechanics’ lien upon the three lots above described, and charges therein the material used in erecting the garage and in repairing the old dwellings. In that statement or mechanics’ lien it is set forth: “That said labor was performed and said materials were furnished in good faith for the purpose of erecting certain dwellings standing on the land hereinafter described.”

In plaintiff’s petition there is an allegation that the plaintiff and contractor, “who was agent of, and general contractor for,” the owner, on July 31, 1919, entered into a contract “to furnish and deliver to said defendant Anton P. Linder a quantity of lumber and building material for the erection of certain dwellings and other improvements upon said real estate.” In the statement and lien filed by the plaintiff, after certain items of material charged, is the word “garage.” There is no other mention of the garage in the petition of the plaintiff or the lien filed by it except as it might be included in the words “other improvements” mentioned above. All materials furnished for the erection of the dwellings, for the repair of the old dwellings, and for the erection of the garage, were charged to the contractor and are included in the items charged in the lien attempted to be foreclosed in this action. The defendant owner, Linder, [570]*570in his answer admits that certain materials were furnished by the plaintiff for the contractor for the construction of said dwelling-houses, and alleges that the plaintiff has been fully paid, and denies each and every other allegation. The evidence was taken before a referee, who reported the same to the court, together with his findings of fact and conclusions of law, which report found there was due to the plaintiff $2,428.41, with interest; that the plaintiff was entitled to a lien therefor upon the property described, and recommended the entry of a decree of foreclosure in its favor for that amount. The owner filed exceptions to the report, which were overruled, and the report was approved by the court. A motion for a new trial was filed and overruled, and judgment rendered upon the findings and report off the referee, and a decree of foreclosure conformable to the recommendations of the referee was entered in plaintiff’s favor. The owner appeals. The decree, so far as it affects the issues between the owner and the contractor, is not appealed from.

The owner challenges the plaintiff’s right to any lien because of its erroneous and unjust claims put upon record which are the result of gross carelessness or design, and which it knew, or by the exercise of reasonable and proper diligence it might have known, to be erroneous, and that a lien based on such a claim so made ought not to be enforced. The owner assigns as error that the material furnished the contractor was not furnished upon the credit of the buildings being erected by the appellant, but upon the general credit of the contractor; that the allowance of a lien for the entire balance of material of the bill charged for in a lump sum is improper; that the allowance of a lien for the full $2,428.41 upon the three buildings already owned by the appellant before the contract was entered into, as a part of the entire property covered by the lien, was error, because the material furnished for repairs was not furnished in pursuance of the contract for the erection of the three new buildings; and that no mechanics’ lien attaches if the materials for which the lien is credited do not enter into the improvements.

[571]*571The appellant strongly urges that, by reason of the numerous errors as to items charged therein and credits improperly omitted, the plaintiff is not entitled to any lien.

In Consolidated Stone Co. v. Union P. R. Co., 96 Neb. 521, it is held: “Where a claimant, either by gross carelessness or by design, puts upon record a statement which he knows, or which by the exercise of reasonable and proper diligence he might have known, to be erroneous and unjust, either by including items not furnished for the particular building or by failure to give credit for- payments made, the law will not aid him in enforcing his lien.” We have examined the record, and while it appears there are mistakes, some of which are the result of carelessness, we cannot say that the carelessness was gross or the mistakes wilful, and as both the referee and the district court find that there was no bad faith apparent, and that the mistakes are to be explained and accounted for by “the imperfections of human machinery,” this court would not be warranted in holding the entire lien unenforceable.

There is, however, a more serious question as to the evidence supporting the finding of the amount due the plaintiff and secured by the lien.

The statute, so far as material to this case, is as follows : ' “Any person who shall * * * furnish any material * * * for the construction, erection, improvement, reparation or removal of any house, * * * or building or appurtenance by virtue of a contract or agreement, expressed or implied, with the owner thereof or his agents, shall have a lien to secure the payment of the same upon such house * * * building or* appurtenance and the lot of land upon which the same shall stand.” Comp. St. 1922, sec. 3207.

“Any person or subcontractor who shall * * * furnish any material * * * for any of the purposes mentioned in the first section of this chapter, to the contractor or any subcontractor who shall desire to secure a lien upon any of the structures mentioned in said section, may file a sworn statement of the amount due him or them from such contractor or subcontractor for such * * * material, * * * [572]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stoltenberg v. Caffrey
141 N.W.2d 458 (Nebraska Supreme Court, 1966)
Jensen v. Manthe
95 N.W.2d 699 (Nebraska Supreme Court, 1959)
Patterson v. Spelts Lumber Co.
90 N.W.2d 283 (Nebraska Supreme Court, 1958)
Central Construction Co. v. Highsmith
50 N.W.2d 817 (Nebraska Supreme Court, 1952)
Ideal Cement Stone Co. v. Dohse
16 N.W.2d 151 (Nebraska Supreme Court, 1944)
Rivett Lumber & Coal Co. v. Linder
217 N.W. 946 (Nebraska Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
204 N.W. 77, 113 Neb. 567, 1925 Neb. LEXIS 152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivett-lumber-coal-co-v-linder-neb-1925.