Ideal Cement Stone Co. v. Dohse

16 N.W.2d 151, 145 Neb. 246, 1944 Neb. LEXIS 134
CourtNebraska Supreme Court
DecidedOctober 20, 1944
DocketNo. 31796
StatusPublished
Cited by2 cases

This text of 16 N.W.2d 151 (Ideal Cement Stone Co. v. Dohse) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ideal Cement Stone Co. v. Dohse, 16 N.W.2d 151, 145 Neb. 246, 1944 Neb. LEXIS 134 (Neb. 1944).

Opinion

Messmore, J.

This is an action to foreclose a mechanic’s lien under the provision of article 1, ch. 52, Comp. St. 1929.

Plaintiff’s petition alleges that on or about April 15, 1941, defendant Fred J. Dohse employed A. S. McGimsey, a contractor, for the purpose of constructing a dwelling and garage on defendants’ premises; that between April 15, 1941, and June 14, 194.1, both inclusive, the plaintiff sold certain materials to McGimsey and delivered the same on the defendants’ premises for the purpose ábove stated; that McGimsey promised and agreed to pay plaintiff the fair and reasonable value of the materials so furnished. Plaintiff filed a mechanics’ lien August 13, 1941, claiming $296.91, with interest at 6 per cent per annum from June 14, 1941, and one dollar for filing.

The defendants’ answer alleges:' Shortly before April 15, 1941; defendant Fred J. Dohse entered into a contract with McGimsey to furnish the materials and perform the labor for the basement walls and chimney of the dwelling for the agreed price of $325. The materials listed in exhibit A, attached to plaintiff’s petition, as being delivered on or about the dates of April 15, 1941, and May 2 of the same year, were furnished to the contractor under said contract. Thereafter, or shortly before June 14, 1941, the same defendant entered into a second contract, independent of the first, with McGimsey, to furnish 'the materials and perform the labor for a cement basement floor-in the house and in a garage attached thereto. The materials listed as being delivered June 14, 1941, were furnished Mc-Gimsey under the second contract. Before defendants had notice of plaintiff’s lien or its filing, the contractor was paid all the amounts due him under both contracts. Being advised of the plaintiff’s lien, shortly before December 31, 1941, defendant Fred J. Dohse informed plaintiff that its lien had not been filed in the statutory time as to the first [248]*248contract, and offered to pay and tendered into court the amount of $70 for materials furnished under the second contract. The plaintiff’s reply alleges that the material furnished was at all times furnished under a continuous running account, constituting one account, and plaintiff was not informed and did not know that there was more than one contract existing between defendants and their contractor and had no notice of any kind or character that separate contracts were being entered into between the defendants and their contractor.

The trial court decreed that the plaintiff’s claim for a lien on materials furnished on or before May 6, 1941, be dismissed, rendered judgment against defendants on items delivered June 14, 1941, in the sum of $70, plus $8.60, costs accruing- to and including February 5, 1942, taxed 'all costs subsequent to such date to the plaintiff, and decreed that the plaintiff had no lien, claim or demand of any kind or description against the defendants or their property. From this decree and the overruling of a motion for a new trial, plaintiff appeals, assigning as error that the decision was contrary to the evidence and the law. The record discloses:

Defendant Fred J. Dohse started the excavation of the basement for a house, with garage attached, to be constructed on his premises. In the forepart of April, 1941, he entered into an oral agreement with A. S. McGimsey to furnish the material and perform the work necessary to put in the footing, the walls of the garage, the chimney and the porch pillars. About the same time McGimsey contacted A. V. Johnson, vice-president of the plaintiff company, and told him that Fred J. Dohse was going to build a house and that he, McGimsey, was going to- build the foundation and do the work for him. Thereafter, McGimsey, as the contractor, ordered out material, the first delivery being made on the Dohse property April 15, 1941. About the 10th or 12th of June, 1941, Fred J. Dohse entered into another oral agreement with McGimsey, by which the latter should furnish the material and do the work in constructing the basement floor in the house and the garage [249]*249and two steps leading from the basement to the garage. Prior to the awarding of the latter contract, a bid was submitted by another contractor and rejected. The contract price for the first contract was $325, and for the second $118. The plaintiff’s account shows materials .ordered out from and after April 15, 1941, to May 2 of the same year, and thereafter on June 14, 1941. Defendant Fred J. Dohse did the excavating, all of the rough carpenter work, the cement work on the sidewalks and driveway, and the cement steps from the porch to the sidewalk and painted the house with a prime coat.

Payments were made pursuant to the contracts in the following manner: April 19, 1941, in the amount of $75; May 5, 1941, $175; May 10, 1941, $50; total, $300, leaving a balance of $25 withheld by defendant Fred J. Dohse on the first contract, for the reason that McGimsey had not completed the job under the first contract. There remained to be finished off the sills for the basement windows and the pillars for the porch. Further payments were made: On June 21, 1941, the sum of $50 for cement work; June 26, 1941, $50 for cement work; August 2, 1941, in full for labor and material, cement work, $43. The work provided for in the first contract was not entirely completed when the work under the second contract was commenced. The job under the first contract was completed with the material furnished from April 15 to and including May 2, 1941, and the material furnished June 14 was used exclusively under the second contract. There remained on the premises a certain quantity of screened sand and cement which, plaintiff contends, were used in the work covered by the second contract by a finisher smoothing off the cement floors. The finisher did not testify as to where these materials came from. The materials, as shown by plaintiff’s account from April 16 to May 2, 1941, inclusive, were of the value of $231.33, and the materials obtained on June 14, 1941, of the. value of $65.58.

Plaintiff’s evidence is to the effect that in furnishing materials, and, until after filing its mechanic’s lien, it had no [250]*250knowledge that the materials were being used in the performance of two separate contracts between Dohse and his contractor, but believed the same were being furnished for one continuous job. The vice-president of the plaintiff testified that he understood the materials were for the construction of a house, treated the orders as one job, and furnished the materials accordingly. Further, it is asserted, the receipt (exhibit 4) for the payment made under date of June 21, 1941, referred to, does not contain any separation of the items under the two contracts, but merely recites that said payment was made for cement work.

The plaintiff contends that a running account for materials furnished for the same improvement is deemed one entire transaction for the purpose of a mechanics’ lien; therefore, the materialman has the statutory period from the date of the last item in which to file his lien for the entire account, citing 36 Am. Jur. 96, sec. 138, in which it is said: “The time for filing a mechanic’s lien begins to run from the time the last item of the account is furnished, when the entire account is a continuous and connected transaction or running account, such an account being deemed an entire contract.” In conformity with the above contention and rule, we consider the Nebraska cases cited by the plaintiff on the subject.

In Ballou v. Black, 17 Neb. 389, 23 N. W. 3, there was only one contract involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FH Peavey & Company v. Whitman
146 N.W.2d 365 (South Dakota Supreme Court, 1966)
Malicki v. Holiday Hills, Inc.
174 N.E.2d 915 (Appellate Court of Illinois, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.W.2d 151, 145 Neb. 246, 1944 Neb. LEXIS 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ideal-cement-stone-co-v-dohse-neb-1944.