FH Peavey & Company v. Whitman

146 N.W.2d 365, 82 S.D. 367, 1966 S.D. LEXIS 120
CourtSouth Dakota Supreme Court
DecidedNovember 16, 1966
DocketFile 10195
StatusPublished
Cited by9 cases

This text of 146 N.W.2d 365 (FH Peavey & Company v. Whitman) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FH Peavey & Company v. Whitman, 146 N.W.2d 365, 82 S.D. 367, 1966 S.D. LEXIS 120 (S.D. 1966).

Opinion

WINANS, Circuit Judge.

The plaintiff brings this suit to obtain a judgment against the defendants, E. J. Perry and Mary Elizabeth Perry, for the sum of $8,590.99, with interest from August 27, 1957, for various building materials and supplies furnished by plaintiff to the defendant, Whitman, at his instance and request, between the dates of Mays 14, 1956 and June 4, 1957, inclusive, for the construction of a dwelling for the defendants Perry, and to foreclose a mechanic's lien against said property after determining the priority of lien-holders.

Defendant Whitman is the general construction contractor of said dwelling. No personal judgment was sought against him as he had been adjudicated a bankrupt.

The mechanic's lien and its validity, which is the real subject matter of this suit, was filed on August 30, 1957 in the office of the Register of Deeds of Spink County, South Dakota. This is within 90 days after furnishing the item of material in the filed lien, claimed to be June 3, 1957.

The defendants Perry admitted certain of the items of supplies and materials in the construction of their dwelling, but contended that the dwelling was substantially completed prior to February 10, 1957 at which time they took possession of the premises and moved into the same, and that the dwelling was completed no later than on or about March 22, 1957; they also contended among numerous other defenses, that such items furnished by plaintiff subsequent to March 22, 1957 were not items supplied by plaintiff through defendant Whitman, pursuant to any contract between Whitman and Perry for the original construction of said dwelling but rather, such materials as were *369 furnished by plaintiff after March 22, 1957, were furnished pursuant to a new and separate contract and the mechanic's lien was not filed within 90 days after the furnishing of the last item of said building materials and supplies by plaintiff on the prior or original construction contract.

It appears from the record herein that defendants Perry employed an architect to prepare plans and specifications for construction of their home. Plaintiff's manager and defendant Whitman prepared a material list to determine cost of materials, and defendants Perry then contracted with Whitman to build the house according to such plans and specifications. The new home was occupied by the 10th day of February 1957 and was then substantially complete. In April of 1957 Perry discovered the asphalt shingles installed on the roof of their residence rippled from high winds and discussed this condition with the architect and defendant Whitman, the contractor. They advised that the shingles should be glued to the roof and that he should “hire somebody" to get it done. Subsequently and following this conversation, the glue and materials were purchased from plaintiff on May 31, 1957 and June 3, 1957, as hereafter related, for the purpose of gluing down the shingles and such work was thereafter performed.

At all times herein relevant, SDC 39.0708 provided: "The lien shall cease at the end of ninety days after doing the last of such work, or furnishing the last item of such skill, services, material, or machinery, unless within such period a statement of the claim therefor be filed with the register of deeds”.

The lien absolutely terminates unless such filing is made within the prescribed time. Botsford Lumber Co. v. Schriver, 49 S.D. 68, 206 N.W. 423.

The lien statement contained charges for material furnished for the Perry residence on May 31 and June 3, 1957, for adhesive used to • stop the shingles from rippling in the wind in the total amount of $47.87. The court found that these two items were furnished under a new and independent contract, and that the defendants Perry employed Ken Sjolentes, foreman for the *370 contractor, defendant Whitman, to do the work during his off hours, for which they paid extra to Whitman for the foreman's benefit. The court also found that it was not established that the invoice of materials claimed to have been furnished June 4, 1957 was used on the dwelling. The court also found that plaintiff furnished materials to said contractor Whitman for the construction of the Perry dwelling commencing May 14, 1956 continuously until March 22, 1957.

The judgment provided a lien in the amount of $47.87 with interest from August 27, 1957 and costs in the amount of $161.61, totaling $209.48, and provided for foreclosure against defendants' Perry dwelling property.

The plaintiff appeals this determination by the court. The assignments of error by plaintiff primarily involve the court's determination that plaintiff supplied materials to defendant Whitman for defendants Perry under two different contracts, one for the construction of the dwelling, from May 14, 1956 through March 22, 1957 and one for gluing down the shingles, from May 31, 1957 to and including June 3, 1957, and whether plaintiff is bound by the second contract under all the circumstances. There was no argument as to the shingle gluing being an extra for which additional charges were justified. As to the issue of whether there was a second contract entered into between defendants Perry and Ken Sjolentes to glue the shingles on the dwelling, this is a question for the trier of the fact. In this case it was the trial judge who made such determination. There is evidence in the record to support such finding and there is no preponderance of evidence against such finding: therefore, it will not be disturbed by this court. Botsford Lumber Co. v. Schriver, supra, and cases therein cited, 49 S.D. page 75(5), 206 N.W. 423. This court in the case of Ward v. Melby, 82 S.D. 132, 142 N.W.2d 526, at page 528 states the rule as follows: "Whether a party having the burden of proof on an issue has sustained it is determined by the trial court, Hilde v. Flood, 81 S.D. 25, 130 N.W.2d 100, as is the question whether the proof in a given case measures up to the required degree of persuasiveness. Brown v. Warner, 78 S.D. 647, 107 N.W.2d 1. In either situation we may disturb the trial court's findings only if the evidence preponderates against *371 its determination. A careful examination of the record herein convinces us we are unable to do so in this case. The record when viewed in a light favorable to the court's determinations furnishes ample support for its findings."

The trial court in this case accepted Dr. Perry's version of a second contract with a third person' dealing with the fastening of the shingles, and we are in no position to say that the trial judge was not at liberty to believe him.

Under the findings which the court made, the last item furnished under the building contract with defendant Whitman was on March 22, 1957; the other items in the lien statement were furnished pursuant to the second contract with Sjolentes on May 31 and June 3 of 1957. The last item of material on said lien statement under date of June 4, 1957 in the amount of 69 cents was not established as being used on the dwelling. It follows that the lien was not filed within the 90 day period from the date defendant Whitman completed his work on the house early in the spring.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Craig v. Swann (In Re Swann)
141 B.R. 678 (D. South Dakota, 1992)
Sioux Falls Construction Co. v. Bruns
420 N.W.2d 29 (South Dakota Supreme Court, 1988)
Wefel v. Harold J. Westin & Associates, Inc.
329 N.W.2d 624 (South Dakota Supreme Court, 1983)
Lytle v. Morgan
270 N.W.2d 359 (South Dakota Supreme Court, 1978)
McLaughlin Electric Supply v. American Empire Insurance Co.
269 N.W.2d 766 (South Dakota Supreme Court, 1978)
Potter v. Anderson
178 N.W.2d 743 (South Dakota Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W.2d 365, 82 S.D. 367, 1966 S.D. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fh-peavey-company-v-whitman-sd-1966.