Wefel v. Harold J. Westin & Associates, Inc.

329 N.W.2d 624, 1983 S.D. LEXIS 254
CourtSouth Dakota Supreme Court
DecidedJanuary 26, 1983
Docket13518
StatusPublished
Cited by20 cases

This text of 329 N.W.2d 624 (Wefel v. Harold J. Westin & Associates, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wefel v. Harold J. Westin & Associates, Inc., 329 N.W.2d 624, 1983 S.D. LEXIS 254 (S.D. 1983).

Opinions

MORGAN, Justice.

This appeal arises from the foreclosure of a mechanic’s lien filed by appellant Howard-Osmera & Associates, Inc. (Engineer), on property owned by the City of Rapid City (City) and leased to Medical and Dental Building, a partnership (Building Partnership). The trial court granted a directed verdict for appellees, City and Building Partnership. Engineer appeals and we reverse and remand.

On December 23, 1976, Building Partnership, upon leasing the subject property from City, contracted with Harold J. Westin Constructors, Inc. (Construction Manager) to construct a medical and dental clinic in Rapid City, South Dakota.1 On that same day, the architect for the construction, Harold J. Westin and Associates, Inc. (Architect), contracted with Engineer for mechanical and electrical design of the building. The contract called for two payments; 80% due upon completion of the construction documents and the remaining 20% upon completion of construction. The contract further provided that any additional work would be paid at fixed hourly rates.

Construction on the project began in the spring of 1977 and continued in stages as additional doctors decided to move into the building. In July 1977 Engineer submitted its invoice for the first 80% of its fixed fee. As late as March 1978 Engineer was designing new areas within the building for additional medical personnel. On October 19, 1978, Lawrence Howard and Al Osmera, the principals of Engineer, conducted an on-site inspection of the mechanical and electrical portions of the construction project and compiled a punch list of work to be completed. Subsequently, on October 24, 1978, Engineer submitted an invoice to Construction Manager for “final inspection” and an invoice to Architect for the remaining “20% due upon completion of the project.” On October 31, 1979, Architect issued to Construction Manager a certificate of completion stating that the work “involved in the project is now 100% complete ... except for those items mentioned in the attached punch lists.” Engineer did not receive a copy of the certificate of completion.

One of the items on the electrical punch list stated: “Connect up Humidifiers Priority # 1.” Although the humidifiers were in place, they were not electrically connected until approximately November 1, 1978. When the humidification system began operating, problems developed with condensation in the duct work resulting in water leakage. In August 1979 Rouse Mechanical, Inc., a subcontractor on the project, consulted with Engineer concerning the humidification system and the project. On October 4, 1979, Construction Manager consulted with Engineer concerning the problems with the humidification system. One month later, Construction Manager filed a petition for bankruptcy. Engineer filed a mechanic’s lien on December 17,1979, in the amount of $20,934, with interest. At the trial for foreclosure of the mechanic’s lien, the court granted Building Partnership’s motion for a directed verdict.2 Engineer appeals, alleging that lienable work was done within 120 days of filing the .mechanic’s lien.

Although the court granted a motion for a directed verdict, SDCL 15-6-[626]*62641(b)3 states that this is a motion for dismissal. Federal Rule of Civil Procedure 41(b) was amended in 1963 to provide that “the motion for dismissal at the close of the plaintiff’s evidence shall apply only to non-jury cases .... Hereafter the correct motion in jury-tried cases will be the motion for a directed verdict.” 5 Moore’s Federal Practice § 41.13 at 41-176. Since the instant case was tried to a court without a jury, the actual motion granted by the court was a motion for dismissal.

When a court dismisses an action, the court must make findings of fact and conclusions of law pursuant to SDCL 15-6-52(a). The court’s dismissal of the action operates as an adjudication upon the merits. SDCL 15-6-41(b). Since the dismissal operates as an adjudication upon the merits, on appeal this court reviews the findings of fact under the “clearly erroneous” standard. 5 Moore’s Federal Practice § 41.13[4] at 41-196 to 198. The conclusions of law are reviewed under the usual “in error as a matter of law.”

Initially, we must determine whether Engineer’s services are the type of services within the contemplation of our mechanic’s lien statutes. SDCL 44-9-1 specifically provides:

Whoever shall, at the request of the owner or the duly authorized agent or representative of the owner, or of any contractor or subcontractor, furnish skill, labor, services, including light, power, or water, equipment, or materials for the improvement, development, or operation of property as hereinafter specified, shall have a first lien thereon and the appurtenances thereto, ... for the price or value of the same, so furnished, subject to the further provisions of this chapter, as follows:
(1) For the erection, alteration, repair, or removal of any building, fixture, bridge, fence, or other structure ....

(Emphasis added.) The mechanic’s lien filed by Engineer is for skills and services performed by Engineer. Further, the record indicates that the services performed by Engineer were requested by contractors or subcontractors. Clearly, these services are within the scope of the mechanic’s lien statutes and are “lienable work.”

The remaining issue is whether the Engineer timely filed the mechanic’s lien. SDCL 44-9-15 states that:

The lien shall cease at the end of one hundred twenty days after doing the last of such work, or furnishing the last item of such skill, services, material, or machinery, unless within such period a statement of the claim therefor be filed with the register of deeds of the county in which the improved premises are situated, or of the county to which such county is attached for judicial purposes, or if the claim be under the provisions of subdivision (2) of § 44-9-1, with the secretary of state.

Accordingly, for the mechanic’s lien to include all of the services provided by Engineer on the contract, the work done in October 1979 would have to be part of the Engineer’s continuing obligation under the contract.

Several times this court has addressed whether supplies or services were part of a [627]*627continuing obligation under a contract.4 In several of these cases, we have held that the 120-day period cannot be extended by a return to the worksite. In Thorson v. Pfeifer, 82 S.D. 313, 145 N.W.2d 438 (1966), where a heating subcontractor returned voluntarily over three months after installation to inspect and winterize the unit, this court held that the 120-day filing period ran from installation and not the voluntary service call. Similarly, in Big Sioux Lumber Co. v. Miller, 57 S.D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoiten v. City of Canistota
1998 SD 44 (South Dakota Supreme Court, 1998)
Craig v. Swann (In Re Swann)
141 B.R. 678 (D. South Dakota, 1992)
Hammerquist v. Warburton
458 N.W.2d 773 (South Dakota Supreme Court, 1990)
Bryant v. Butte County
457 N.W.2d 467 (South Dakota Supreme Court, 1990)
Ethan Dairy Products v. Austin
448 N.W.2d 226 (South Dakota Supreme Court, 1989)
In Re the Driver's License Revocation of Malone
387 N.W.2d 547 (South Dakota Supreme Court, 1986)
Bublitz v. State Bank of Alcester
369 N.W.2d 137 (South Dakota Supreme Court, 1985)
Jankord v. Jankord
368 N.W.2d 571 (South Dakota Supreme Court, 1985)
Western Petroleum Co. v. First Bank Aberdeen (N.A.)
367 N.W.2d 773 (South Dakota Supreme Court, 1985)
Temple v. Temple
365 N.W.2d 561 (South Dakota Supreme Court, 1985)
Sepco, Inc. v. Valley State Bank (In Re Sepco, Inc.)
36 B.R. 279 (D. South Dakota, 1984)
Red Bear v. Cheyenne River Sioux Tribe
336 N.W.2d 370 (South Dakota Supreme Court, 1983)
Taylor Oil Co. v. Weisensee
334 N.W.2d 27 (South Dakota Supreme Court, 1983)
Sioux Valley Hospital Ass'n v. Bon Homme County
331 N.W.2d 78 (South Dakota Supreme Court, 1983)
Wefel v. Harold J. Westin & Associates, Inc.
329 N.W.2d 624 (South Dakota Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
329 N.W.2d 624, 1983 S.D. LEXIS 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wefel-v-harold-j-westin-associates-inc-sd-1983.