Hoiten v. City of Canistota

1998 SD 44, 579 N.W.2d 12, 1998 S.D. LEXIS 43
CourtSouth Dakota Supreme Court
DecidedMay 13, 1998
DocketNone
StatusPublished
Cited by6 cases

This text of 1998 SD 44 (Hoiten v. City of Canistota) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoiten v. City of Canistota, 1998 SD 44, 579 N.W.2d 12, 1998 S.D. LEXIS 43 (S.D. 1998).

Opinion

AMUNDSON, Justice.

[¶ 1.] Contractor sued city of Canistota (City) to recover money claimed to be due for services rendered at the city landfill. At the conclusion of the contractor’s case during the trial to the court, City’s motion for a directed verdict was granted based on the failure to comply with the competitive bidding requirements of the State of South Dakota. Contractor appeals, asserting there was a valid contract pursuant to an existing bid that was subsequently verbally modified. We affirm.

FACTS

[¶2.] Merle Hoiten, Jr. (Hoiten) and his father are equal partners in Hoiten Construction Company (Hoiten Construction). Hoiten has been involved in the earth-moving business for over twenty years and has been a business partner with his father for fifteen years. In his business, Hoiten has performed work under contracts with municipalities and townships and has been involved in the bidding process for those contracts. He also admitted to knowing that those government contracts are required to be in writing under state law.

[¶ 3.] In 1993, the city council of Canistota accepted Hoiten Construction’s bid of *14 $6,122.46 to complete an earth moving and leveling project at the city landfill. The project involved digging a hole, pushing debris into the hole, and covering the site -with eighteen inches of dirt from the hole. Hoiten was familiar with the site because he had previously performed other similar work at the site. However, due to the extremely wet weather conditions, Hoiten and City agreed not to proceed with the project in 1993.

[¶ 4.] In 1994, Hoiten inspected the site to determine if the ground had dried out sufficiently to start the job. His inspection revealed there had been a significant amount of debris placed on the site after his original bid was accepted. Thereafter, Hoiten and City discussed the additional work that would now be involved in completing the project. After these discussions, City agreed to pay an additional $2,500 to Hoiten for the job, bringing the total contract to approximately $8,600.

[¶ 5.] Hoiten commenced work at the site on June 24, 1994. On June 27, Hoiten attempted to begin digging a hole at the dump site, but again the ground was too wet to dig properly. Hoiten then contacted the mayor of Canistota, since the project was impossible to complete as Hoiten had intended. The mayor directed him to see the city council member in charge of the landfill, Bill Nichols.

[¶ 6.] Hoiten and Nichols had a conversation about what should be done at the landfill in light of the wet conditions. The content of Hoiten’s conversation with Nichols is a disputed matter, however. Hoiten’s version of events was that he and Nichols discussed a plan to take dirt from an old railroad bed down the road and cover the dump site. Hoiten contends that, because it was impossible to gauge what it would cost to implement this new job plan, he and Nichols agreed on a rate of $80 an hour for each machine that Hoiten would use to accomplish the task. Hoiten claims that he asked Nichols if the rest of the city council would be required to vote on the new plan, but Nichols stated he was in charge of the landfill and that this new agreement did not need the approval of the rest of the council.

[¶ 7.] After work had begun on the new plan, Hoiten claims to have informed Nichols that the cost of the project was mounting. Then Hoiten contends Nichols told him to continue the project and assured him that City would “float a loan” to take care of the costs, if needed.

[¶ 8.] Additionally, Hoiten claims that Nichols told him to put a twenty-four-inch overlay of dirt on the dump site, instead of the eighteen inches that was required by the original contract with City. Hoiten contends the increased amount of dirt overlay was to allay Nichols’ concerns about compliance with state environmental regulations. This increase in the amount of dirt that was to cover the dump site was estimated to have taken an extra three to four days of work.

[¶ 9.] When Hoiten finished his work at the landfill, the cost of the project had risen to over $34,000. Nichols testified that he did not agree to an hourly rate for Hoiten’s work, nor did he tell Hoiten to increase the dirt overlay to twenty-four inches. Nichols also denies telling Hoiten that he could incur expenses beyond the $8,600 originally agreed upon. Nichols did make a motion at a city council meeting that Hoiten’s bill be paid in its entirety, but it failed for lack of a second. The city council has since refused to pay Hoiten Construction more than the $8,600 which they had previously approved. Additional facts will be noted when relevant.

[¶ 10.] Hoiten brought this action to recover the balance of the amount he contends is due. At the close of Hoiten’s case-in-chief, the trial court granted City’s motion for a directed verdict. The trial court held as a matter of law that the alleged amendment to the contract was null and void because it did not comply with South Dakota’s competitive bidding laws, was not reduced to writing, and was not approved by a governing body at a duly assembled meeting.

[¶ 11.] Hoiten appeals the grant of the directed verdict, and raises the following issue for review:

Whether Hoiten is foreclosed from being paid for services he provided to the city of Canistota because of alleged failures in complying with the competitive bidding requirements of the state of South Dakota?

*15 STANDARD OF REVIEW

[¶ 12.] This case was tried to the circuit court without a jury. Therefore, City’s motion was in reality a motion for dismissal under SDCL 15-6-41(b), rather than a motion for directed verdict. Sioux Valley Hosp. Ass’n v. Bon Homme County, 331 N.W.2d 78, 78 (S.D.1983) (citing Wefel v. Westin, 329 N.W.2d 624 (S.D.1983)). SDCL 15-6-41(b) states, in pertinent part, as follows:

After the plaintiff, in an action tried by the court without a jury, has completed the presentation of his evidence, the defendant, without waiving his right to offer evidence in the event the motion is not granted, may move for a dismissal on the ground that upon the facts and the law the plaintiff has shown no right to relief. The court as trier of the facts may then determine them and render judgment against the plaintiff.... [A] dismissal under this section ... operates as an adjudication upon the merits.

“Since the dismissal operates as an adjudication upon the merits, on appeal this court reviews the findings of fact under the ‘clearly erroneous’ standard.” Sioux Valley Hosp. Ass’n, 331 N.W.2d at 78 (citation omitted). “This Court interprets statutes under a de novo standard of review without deference to the decision of the trial court.” In re Estate of Jetter, 1997 SD 125, ¶ 10, 570 N.W.2d 26, 28 (citation omitted).

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bozied v. City of Brookings
2001 SD 150 (South Dakota Supreme Court, 2001)
C & W Enterprises, Inc. v. City of Sioux Falls
2001 SD 132 (South Dakota Supreme Court, 2001)
City of Aberdeen v. Rich
2001 SD 55 (South Dakota Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
1998 SD 44, 579 N.W.2d 12, 1998 S.D. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoiten-v-city-of-canistota-sd-1998.