Potter v. Anderson

178 N.W.2d 743, 85 S.D. 142, 1970 S.D. LEXIS 102
South Dakota Supreme Court·Decided July 21, 1970·No. File 10700·Published·Cited by 19 cases

Opinion

BIEGELMEIER, Judge.

Plaintiff Rex Potter, a contractor, and defendant executed an agreement whereby plaintiff agreed to construct a house in the country on lands owned by defendant for $34,000 in accord with plans and specifications prepared by a company which specialized in that service. The plans (blue prints) were used, but the contract stated some changes and the 15 pages of specifications were then rewritten to reflect these written changes. Potter brought an action against defendant for the balance he claimed due on the contract and a second cause of action for damages for failure of defendant to convey his former home to plaintiff. Defendant’s answer was a general denial, claims of failure of plaintiff to perform the contract, listing numerous defects and a counterclaim. Three firms commenced a separate action against defendant to foreclose liens claimed by them for labor and materials furnished in the building. Upon reaching trial the parties to both these actions stipulated to consolidate the two cases for trial by the court. The trial court’s Findings and Judgment awarded Potter the balance found due on the contract plus some extras, less damages allowed for some of the defects; it also decreed liens for all three lien claimants in varying amounts.

I.

One set of Findings of Fact,. Conclusions of Law and a Judgment were entered. The titles of these papers, as all thereafter filed in the trial court and the one Notice of Appeal to this court, were titled with the names of the parties *145 to both actions. The propriety of the latter is much in doubt. 36 A.L.R.2d 823. As the court commented on a different phase of appellate procedure in Morrison & Skaug v. Connery, 54 S.D. 329, 223 N.W. 210, “It is not only confusing but perilous.” In a similar situation two actions, one for forcible entry and detainer and the other for specific performance of a contract involving the same property but with the parties reversed, were consolidated for trial and tried to the court. Two copies of the set of Findings, Conclusions and Judgment were entered, each having both titles as did the one Notice of Appeal which was served and filed. On motion the appeal was dismissed by order without an opinion. Himrich v. Helm, and Helm v. Himrich, No. 10340. However, no objection was made here, 36 A.L.R.2d 849; consequently, the merits have been considered.

II.

For clarity contractor Potter will sometimes be designated in the opinion as contractor or plaintiff as he was in what the parties referred to as the main action, and defendant as such or as owner.

The contract contained the usual provisions that the contractor furnish all labor, materials, etc. to construct the house, the work to be performed by qualified and skilled craftsmen in good and workmanlike manner, and that he assumed responsibility for all subcontractors employed by him but not for that of, or the delays caused by, subcontractors employed by the owner. Plaintiff’s complaint alleged he had performed his contract and defendant argues that having alleged performance, he cannot prove waiver or excuse. Defendant also asserts that the findings plaintiff substantially performed his contract are against the evidence.

We believe the first point is merged in the second and if plaintiff substantially performed the contract he may recover on it. Defendant does not otherwise contend nor could he, as his brief states “plaintiff * * * cannot recover unless he shows substantial performance”; ergo, if plaintiff shows substantial performance he may recover. That is the *146 teaching of our cases from Aldrich v. Wilmarth, 3 S.D. 523, 54 N.W. 811, through Dixon v. Nelson, 79 S.D. 44, 107 N.W.2d 505, which defendant cites and from which he quotes. See also 13 Am.Jur.2d, Building, Etc. Contracts, § 43. What is substantial performance in a given situation is sometimes a question of fact, Hulst v. Benevolent Hall Ass’n, 9 S.D. 144, 68 N.W. 200, yet as phrased by Justice Cardozo in Jacob v. Kent, 230 N.Y. 239, 129 N.E. 889, 23 A.L.R. 1429, “The question is one of degree, to be answered, if there is doubt;, by the triers of the facts * * * and, if the inferences are certain, by the judges of the law”. In the latter circumstances, it is a matter of law. *

Further, in considering whether the Findings of Fact are supported by the evidence, we must accept that version, including the inferences which can be fairly drawn therefrom, which is favorable to the trial court’s action. Because his participation in the trial reveals to him many things that are helpful and sometimes essential in deciding fact issues, it is presumed the findings are correct. Hence, we are not free to disturb them unless satisfied that they are contrary to a clear preponderance of the evidence. Dolan v. Hudson, 83 S.D. 144, 156 N.W.2d 78. As in Dolan, the trial court by consent of and in presence of counsel viewed the house and while it is not evidence, it fortifies the findings. We assume this view was of some value in assisting the judge to determine the issues of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Potter v. Anderson, 178 N.W.2d 743, 85 S.D. 142, 1970 S.D. LEXIS 102 (S.D. 1970).

178 N.W.2d 743 (Potter v. Anderson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Zarecky v. Thompson
2001 SD 121 (South Dakota Supreme Court, 2001)
Ducheneaux v. Miller
488 N.W.2d 902 (South Dakota Supreme Court, 1992)
Mash v. Cutler
488 N.W.2d 642 (South Dakota Supreme Court, 1992)
Maryhouse, Inc. v. Hamilton
473 N.W.2d 472 (South Dakota Supreme Court, 1991)
Farmers Union Coop Ass'n v. Schladweiler Bros., Inc.
448 N.W.2d 650 (South Dakota Supreme Court, 1989)
Rosebud Sioux Tribe v. A & P Steel, Inc.
874 F.2d 550 (Eighth Circuit, 1989)
Ambrose v. Biggs
509 N.E.2d 614 (Appellate Court of Illinois, 1987)
Marshall v. Karl F. Schultz, Inc.
438 So. 2d 533 (District Court of Appeal of Florida, 1983)
Wefel v. Harold J. Westin & Associates, Inc.
329 N.W.2d 624 (South Dakota Supreme Court, 1983)
Skoglund v. Staab
312 N.W.2d 29 (South Dakota Supreme Court, 1981)
Chisum v. Behrens
283 N.W.2d 235 (South Dakota Supreme Court, 1979)
Terminal Grain Corp. v. Rozell
272 N.W.2d 800 (South Dakota Supreme Court, 1978)
Cunningham v. Yankton Clinic, P. A.
262 N.W.2d 508 (South Dakota Supreme Court, 1978)
Colby v. Costello
232 N.W.2d 81 (South Dakota Supreme Court, 1975)
MURPHY v. McCLINTOCK
Montana Supreme Court, 1972