Dave Gustafson & Co. v. State

156 N.W.2d 185, 83 S.D. 160, 1968 S.D. LEXIS 84
CourtSouth Dakota Supreme Court
DecidedFebruary 13, 1968
DocketFile 10409
StatusPublished
Cited by33 cases

This text of 156 N.W.2d 185 (Dave Gustafson & Co. v. State) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dave Gustafson & Co. v. State, 156 N.W.2d 185, 83 S.D. 160, 1968 S.D. LEXIS 84 (S.D. 1968).

Opinion

HANSON, Presiding Judge.

*162 In this action by a contractor against the State of South Dakota and its Highway Commission the single question is whether a provision in a state highway construction contract is one for liquidated damages, as the trial court found, or is a penalty.

On October 5, 1963 plaintiff, Dave Gustafson & Company, entered into a contract with the State Highway Commission for the construction of the subbase, base and bituminous surfacing of a new public highway between Wessington Springs and Woonsocket. Plaintiff performed a total dollar amount of work in the amount of $530,724.14. Upon completion the new highway replaced the pre-existing portion of State Trunk Highway No. 34 between the two towns. During construction the old portion of Highway 34 remained open for travel by the public in substantially the same manner as it had been for the past five years. After the new highway was completed the old portion of the road was also left open for use as a public highway.

Plaintiff failed to complete the new highway on the date fixed. There was a delay of 67 working days for which there was no extension of time requested or granted. Therefore the state withheld $14,070.00 as liquidated damages from the amount due plaintiff computed according to the contract scale of daily damage for delay in construction. As this project totaled $530,-742.14, the per diem daily damage was $210. This daily damage multiplied by the 67 day delay equals the sum withheld. According to an interrogatory answered by the state any damage, loss, or expense incurred by reason of the delay was "unknown". This did not necessarily mean there were no damages.

The pertinent contract provision reads:

"8.9 FAILURE TO COMPLETE THE WORK ON TIME:— Time is an essential element of the contract and it is important that the work be pressed vigorously to completion. [1] The cost to the Department of the administration of the contract including engineering, inspection, and supervision, will be increased as the time occupied in the work is lengthened. [2] The public is subject to detriment and inconvenience when full use cannot be made of an incomplete project.
*163 "Should the Contractor fail to complete the work within the time agreed upon in the contract or within such extra time as may have been allowed by increases in the contract or by formally approved extensions granted by the Department there shall be deducted from any monies or amount due or that may become due the Contractor, the sum set forth in the schedule shown in Section 8.10 herein, for each and every weather working day, that the work shall remain uncompleted. [3] This sum shall be considered and treated not as penalty but as fixed, agreed liquidated damage due the State from the Contractor by reason of inconvenience to the public, added cost of Engineering and supervision, and other items which have caused an expenditure of public funds resulting from his failure to complete the work within the time specified in the contract."

Section 8.10 provides the following graduated scale of per diem liquadated damages:

From more than To and including
0 25.000 42
25.000 50.000 70
50.000 100,000 105
100,000 500,000 140
500,000 1,000,000 210
1,000,000 2,000,000 280
2,000,000 420"

An unexcused delay in performing a contract after the time fixed for performance constitutes a breach of contract for which damages are recoverable. The measure of damages, except as otherwise provided by statute, is the amount which

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cerny v. Andrews
2025 Ohio 2864 (Ohio Court of Appeals, 2025)
Hawken School v. Machado
2024 Ohio 1060 (Ohio Court of Appeals, 2024)
Stark Ambulatory Surgical Ctr., L.L.C. v. CS Anesthesia, L.L.C.
2022 Ohio 3305 (Ohio Court of Appeals, 2022)
Drake Townhomes, L.L.C. v. Woodberry
2017 Ohio 6968 (Ohio Court of Appeals, 2017)
Oldendick v. Crocker
2016 Ohio 5621 (Ohio Court of Appeals, 2016)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)
Overholt Crop Insurance Service Co. v. Travis
941 F.2d 1361 (Eighth Circuit, 1991)
Jessen v. Jessen
810 P.2d 987 (Wyoming Supreme Court, 1991)
Taos Construction Co. v. Penzel Construction Co.
750 S.W.2d 522 (Missouri Court of Appeals, 1988)
City of Fargo v. Case Development Co.
401 N.W.2d 529 (North Dakota Supreme Court, 1987)
Prentice v. Classen
355 N.W.2d 352 (South Dakota Supreme Court, 1984)
Marcam Mortgage Corp. v. Black
686 P.2d 575 (Wyoming Supreme Court, 1984)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Walter Motor Truck Co. v. State Ex Rel. Department of Transportation
292 N.W.2d 321 (South Dakota Supreme Court, 1980)
Fortune Bridge Co. v. Department of Transportation
250 S.E.2d 401 (Supreme Court of Georgia, 1978)
Bottineau Public School District No. 1 v. Zimmer
231 N.W.2d 178 (North Dakota Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
156 N.W.2d 185, 83 S.D. 160, 1968 S.D. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dave-gustafson-co-v-state-sd-1968.