Taos Construction Co. v. Penzel Construction Co.

750 S.W.2d 522, 1988 Mo. App. LEXIS 263, 1988 WL 26321
CourtMissouri Court of Appeals
DecidedMarch 29, 1988
Docket53221
StatusPublished
Cited by10 cases

This text of 750 S.W.2d 522 (Taos Construction Co. v. Penzel Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taos Construction Co. v. Penzel Construction Co., 750 S.W.2d 522, 1988 Mo. App. LEXIS 263, 1988 WL 26321 (Mo. Ct. App. 1988).

Opinion

REINHARD, Presiding Judge.

Both parties appeal from a judgment of the trial court in favor of defendant Penzel Construction Company on plaintiff Taos Construction Company’s breach of contract claim and in favor of Taos on Penzel’s counterclaim. The appeals are consolidated for our review; we affirm.

Penzel was the prime contractor for a Missouri Highway and Transportation Commission project that involved the construction of four bridges on Highway 106 in Shannon County for a total contract price of about $1.25 million. The contract allowed Penzel 120 working days in which to complete the project and contained a liquidated damages provision that permitted the Commission to deduct $200 from the amount due Penzel for every day the project remained uncompleted after expiration of the 120-working-day period.

The contract contained specifications for permanent soil erosion control. Taos, one of several subcontractors on the project, was responsible for fertilizing, seeding, and mulching approximately 12 acres of ground surrounding the construction sites for a total price of about $13,900. In the subcontract Taos agreed “to commence work *524 within 10 days following notification by Penzel,” and acknowledged it had “thoroughly examined all contract documents as provided for this project, including the form of agreement between Penzel and [the Commission],” and that the contract and specifications agreed upon by Penzel and the Commission “are part of this subcontract and shall be made available for inspection by the Subcontractor upon his request.” The subcontract contained the following liquidated damages clause:

The contract between Penzel and [the Commission] provides for liquidated damages. In the event Subcontractor has caused or contributed to cause in any way any part of any assessment of liquidated damages against Penzel, then in addition to all other remedies provided and available to Penzel, Subcontractor shall be liable to Penzel for the full amount of such penalty as shall be assessed by [the Commission] in the form of such liquidated damages plus 10% of said figure, together with reasonable attorney fees and costs, in the event it becomes necessary to use an attorney for purposes of collection, whether or not suit is brought. Penzel shall further have the right to withhold from any monies due Subcontractor hereunder all or a proportionate share of any liquidated damages assessed by [the Commission] against Penzel.

Operations on the project commenced July 11, 1988, and the 120-working-day period to complete the project expired August 15, 1984. On August 16, the Commission began assessing liquidated damages against Penzel at the daily rate of $200. Two of the four bridges were open to traffic by August 16; the remaining two were open to traffic about August 31. Prior to August 16, Taos had seeded the ground surrounding two of the bridges, an area comprising about five acres of the project. Penzel admits Taos did not cause any delays during this phase of its work and it did not cause Penzel to exceed the 120-day limit. Penzel’s field superintendent stated his opinion that delays during the 120-day contract period were caused primarily by the grading subcontractor and the weather.

Penzel notified Taos on August 24 to return to the job site to begin seeding the seven acres adjacent to the remaining two bridges. A Penzel engineer who was the project coordinator testified he informed Taos on August 24 that “the job was in liquidated damages....” The engineer said the 3V2 acres around one of the two remaining bridges were ready for seeding on September 6; grading of the 3¾⅛ acre area around the other bridge was completed on September 18. He said the remaining seven acres could have been seeded in “four or five days ... that would be a reasonable time,” and he stated that “it’s not an uncommon practice for the seeder and the grading man to finish the same day or certainly within a day or so of one another.” The Penzel field superintendent, who was at the job site daily, testified that all but one of the seven remaining acres could have been seeded before September 18; the final acre was a half-day job.

There was evidence in the form of the Commission’s Weekly Report of Working Days, prepared by the Commission’s resident engineer, about the number of working days available to Taos before September 21 to perform the seeding. According to the Weekly Report of Working Days, Taos did not begin seeding until October 4 and worked October 5 and November 7, 8, 9, 13, 14, 15, and 16. On those days, Taos applied 75 percent of the seed and fertilizer required to complete its work. On November 19, the Commission accepted the job subject to the remaining overseeding. 1 Taos performed the overseeding on December 4 and 13 and the Commission accepted the project unconditionally on December 13. The Weekly Report of Working Days indicated that, from the week ending September 27 until completion December 13, the major operation on the project was “seeding” and no work other than seeding was performed after September 21. The *525 Commission’s resident engineer continued to file the weekly report until the December 13 acceptance of the project.

The Commission assessed Penzel 71 days of liquidated damages for a total of $14,-200. Penzel assessed the grading contractor for 25 days of damages, a total of $5,000, for the period August 16 through September 20. Penzel assigned to Taos all damage days after September 20, a total of 46, and withheld $9,200 from payment to Taos. There was evidence that Penzel suffered additional damages in excess of $900 as a result of Taos’s tardy performance.

Taos filed a petition for a declaratory judgment against Penzel and the Commission in Cole County where the court dismissed the action against the Commission for lack of privity and then dismissed against Penzel for improper venue. Taos did not appeal the dismissal of the Commission. Taos then filed a first amended petition in Cape Girardeau County against Pen-zel alone seeking a declaratory judgment in Count I and asserting a breach of contract claim in Count II. Penzel brought a counterclaim for rental on a piece of its equipment that Taos used in performing the subcontract. Upon motion of Penzel, the court dismissed the declaratory judgment count because “the plaintiff has an adequate remedy at law, i.e., Count II.”

Count II was tried without a jury. The court found that the 10-day notice provision in the subcontract referred to “working days” and that Taos should have resumed seeding on September 10. Among its other findings, the court found as follows:

8. After September 10, 1984, and before September 21,1984, there were two separate bridge sites available for plaintiff to perform its work on, each consisting of approximately 3⅛⅛ acres.
9. That the reasonable time necessary to seed, fertilize and mulch an area such as remained after September 10, 1984, would be between 4 and 5 days.
10. After September 10,1984, the following working days were available during which plaintiff could have performed its seed and mulch work on the job site: September 12, 13, 14, 17, 18, 19 and 20.
11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Arcese v. Daniel Schmitt & Company
504 S.W.3d 772 (Missouri Court of Appeals, 2016)
Valentine's, Inc. v. Ngo
251 S.W.3d 352 (Missouri Court of Appeals, 2008)
Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc.
171 S.W.3d 81 (Missouri Court of Appeals, 2005)
American Multi-Cinema, Inc. v. Southroads, L.L.C
119 F. Supp. 2d 1190 (D. Kansas, 2000)
Hawkins v. Foster
897 S.W.2d 80 (Missouri Court of Appeals, 1995)
Paragon Group, Inc. v. Ampleman
878 S.W.2d 878 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
750 S.W.2d 522, 1988 Mo. App. LEXIS 263, 1988 WL 26321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taos-construction-co-v-penzel-construction-co-moctapp-1988.