American Multi-Cinema, Inc. v. Southroads, L.L.C.

115 F. Supp. 2d 1257, 2000 U.S. Dist. LEXIS 19109, 2000 WL 1468450
CourtDistrict Court, D. Kansas
DecidedJuly 28, 2000
Docket99-2019-JWL
StatusPublished

This text of 115 F. Supp. 2d 1257 (American Multi-Cinema, Inc. v. Southroads, L.L.C.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Multi-Cinema, Inc. v. Southroads, L.L.C., 115 F. Supp. 2d 1257, 2000 U.S. Dist. LEXIS 19109, 2000 WL 1468450 (D. Kan. 2000).

Opinion

MEMORANDUM AND ORDER

LUNGSTRUM, District Judge.

This suit arises out of a retail lease agreement between plaintiff, as tenant, and defendant, as landlord. 1 Plaintiff alleges that defendant breached the lease, and certain amendments thereto, by failing to deliver timely physical possession of the leased premises to plaintiff and by failing to complete timely various tasks associated with the shopping center of which plaintiff was one tenant. Plaintiff seeks liquidated damages pursuant to a stipulated damages provision in the lease. Defendant, on the other hand, contends that the stipulated damages provision is an unenforceable penalty. This matter is presently before the court on defendant’s motion for summary judgment (doc. # 95).

As set forth in more detail below, the choice of which state’s law to apply to this case could very well determine which party ultimately prevails at trial. Nonetheless, because material factual disputes exist concerning the place of the contract’s formation, the court does not decide the choice-of-law issue at this stage of the proceeding. Even assuming, however, that Oklahoma law applies to this case, as defendant suggests, the court concludes that the evidence, viewed in the light most favorable to plaintiff, requires a trial on plaintiffs claims. Put briefly, the court has no difficulty concluding that defendant has not met its burden on summary judgment to show that the uncontroverted facts demonstrate that plaintiffs potential damages from defendant’s breach of the lease were not extremely difficult to ascertain at the time of contracting. Similarly, the court has little difficulty concluding that defendant falls short of meeting its summary judgment burden to show that the uncontroverted facts fail to demonstrate that the stipulated sum was reasonably proportionate to plaintiffs probable actual harm suffered .prior to the time plaintiff opened for business. The more difficult decision is whether defendant has satisfied its summary judgment burden to demonstrate that the uncontroverted facts fail to show that the stipulated sum was reasonably proportionate to plaintiffs probable actual harm suffered for the period of time after plaintiff opened for business.' Nonetheless, the court concludes that, while a closer call, defendant has failed to meet this burden. Thus," defendant’s motion for summary judgment is denied.

I. Facts

The following facts are either uncontro-verted or related in the light most favorable to plaintiff, the nohmoving party. In December 1995, plaintiff and Yale 41 Associates Limited Partnership executed a re *1260 tail lease agreement whereby Yale 41 was the landlord and plaintiff was a tenant in a new shopping center located in Tulsa, Oklahoma. Yale 41’s rights and responsibilities under the lease were subsequently assigned to defendant and the shopping center, at some point thereafter, was named the Southroads shopping center.

The lease agreement, including a September 1996 amendment thereto, required defendant to provide to plaintiff by November 15, 1996 a pad site with utilities on which plaintiff would construct a “mega-plex” movie theater — the Southroads 20. This November 15, 1996 deadline is referred to in the lease and by the parties in their papers as the “turnover date.” The lease agreement and the September 1996 amendment further provided that defendant was to complete by May 30, 1997 a variety of tasks associated with the South-roads shopping center, including the construction of all common facilities and access facilities. This May 80, 1997 deadline is referred to in the lease and by the parties in their papers as the “completion date.” According to plaintiffs evidence, plaintiff intended to open its megaplex theater during the summer of 1997.

According to plaintiff, defendant breached the lease agreement and the September 1996 amendment thereto by failing to provide a certified pad site in a timely fashion and by failing to complete the various tasks associated with the completion of the Southroads shopping center. Plaintiffs evidence indicates that the pad site was not provided until March 11,1997 and that, as a result, the Southroads 20 did not open for business until November 21, 1997. Plaintiffs evidence further indicates that defendant did not complete the tasks related to the completion date until July 31, 1998 and that, as a result, the Southroads 20 continued to suffer in a variety of ways and, in fact, may continue to suffer today.

Specifically, plaintiff asserts that, as a result of defendant’s breach of the turnover date, it was not able to open its theater during the summer of 1997 as scheduled and, thus, it lost income. Plaintiff further asserts that, as a result of defendant’s breach of the completion date, it was forced to build its theater in the midst of major ongoing construction, thereby increasing its construction costs due to work coordination problems; that it lost customers who, had they been able to shop at a completed center, would have learned about the anticipated opening of the Southroads 20; and that, once the theater opened, it lost customers who either had negative experiences at the Southroads 20 in large part because of the unfinished nature of the center or who simply elected not to go to the Southroads 20 because they could not combine a trip to the movies with a shopping trip.

Pursuant to article 5 of the lease, if defendant failed to meet either the turnover date or the completion date, then plaintiff was entitled to “receive an amount equal to four days of free Annual Fixed Rent for each day of delay” between the completion date or the turnover date and the date on which defendant fully performed its obligations (i.e., providing a certified pad site and/or completing the tasks associated with the Southroads shopping center). This provision for stipulated damages is referred to by the parties as the 4 to 1 provision. Pursuant to the stipulated damages provision, plaintiff seeks stipulated damages relating to the turnover date for the period from November 15, 1996 through March 11, 1997. 2 With respect to the completion date, plaintiff seeks stipulated damages from May 30, 1997 through July 31, 1998. 3

II. Summary Judgment Standard

Summary judgment is appropriate if the moving party demonstrates that there is “no genuine issue as to any material fact” and that it is “entitled to a judgment as a *1261 matter of law.” Fed.R.Civ.P. 56(c). In applying this standard, the court views the evidence and all reasonable inferences therefrom in the light most favorable to the nonmoving party. Adler v. Wal-Mart Stores, Inc., 144 F.3d 664, 670 (10th Cir.1998) (citing Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986)). A fact is “material” if, under the applicable substantive law, it is “essential to the proper disposition of the claim.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Adler v. Wal-Mart Stores, Inc.
144 F.3d 664 (Tenth Circuit, 1998)
Bancoklahoma Mortgage Corp. v. Capital Title Co.
194 F.3d 1089 (Tenth Circuit, 1999)
Rodriguez v. Learjet, Inc.
946 P.2d 1010 (Court of Appeals of Kansas, 1997)
Knapp v. Ottinger
1951 OK 329 (Supreme Court of Oklahoma, 1951)
Fretwell v. Protection Alarm Co.
1988 OK 84 (Supreme Court of Oklahoma, 1988)
Freeling v. Wood
1961 OK 113 (Supreme Court of Oklahoma, 1961)
B & B Lines, Inc. v. Ryan Freight Lines, Inc.
601 P.2d 1207 (Court of Civil Appeals of Oklahoma, 1979)
Waggoner v. Johnston
1965 OK 192 (Supreme Court of Oklahoma, 1965)
Simms v. Metropolitan Life Insurance
685 P.2d 321 (Court of Appeals of Kansas, 1984)
Sun Ridge Investors, Ltd. v. Parker
1998 OK 22 (Supreme Court of Oklahoma, 1998)
Massey v. Love
478 P.2d 948 (Supreme Court of Oklahoma, 1971)
Manufacturers Casualty Insurance v. Sho-Me Power Corp.
157 F. Supp. 681 (W.D. Missouri, 1957)
Wasserman's Inc. v. Township of Middletown
645 A.2d 100 (Supreme Court of New Jersey, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 2d 1257, 2000 U.S. Dist. LEXIS 19109, 2000 WL 1468450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-multi-cinema-inc-v-southroads-llc-ksd-2000.