Corrigan Co. Mechanical Contractors, Inc. v. Fleischer

423 S.W.2d 209, 1967 Mo. App. LEXIS 549
CourtMissouri Court of Appeals
DecidedDecember 19, 1967
Docket32620
StatusPublished
Cited by7 cases

This text of 423 S.W.2d 209 (Corrigan Co. Mechanical Contractors, Inc. v. Fleischer) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corrigan Co. Mechanical Contractors, Inc. v. Fleischer, 423 S.W.2d 209, 1967 Mo. App. LEXIS 549 (Mo. Ct. App. 1967).

Opinion

BRADY, Commissioner.

Judgment in this jury-waived action was rendered in favor of plaintiff and against defendants on plaintiff’s petition and in favor of plaintiff and against defendants on defendants’ counterclaim. Plaintiff is a corporation and will be herein referred to by its designation in the trial court. Defendants are partners doing business as “Fleischer-Seeger Construction Company” and will be referred to as “Fleischer-Seeger” or as defendants. Defendants have perfected their appeal to this court.

The pleadings will help delineate the issues here involved. Plaintiff entered into a contract with defendants under the terms of which it agreed to furnish labor and materials, and do certain work in connection with defendants’ contract to construct a power plant at Chamois, Missouri. Plaintiff had been paid for such work except for $4,900.00 which defendants refused to pay to plaintiff. In the instant case plaintiff seeks to recover this $4,900.00 with interest and costs. Defendants’ answer was in the form of a general denial and they also filed a counterclaim in the nature of a setoff alleging there was due them from plaintiff the sum of $4,900.00 for services, material, labor, etc., necessary to complete work which they had performed as plaintiff’s subcontractor in connection with the conversion of three boiler furnaces at the Carr Square Village project, a job for which plaintiff was prime contractor for the St. Louis Housing Authority. Defendants prayed judgment on their counterclaim for $4,900.00 with interest and costs and that in the event recovery was had by plaintiff on its petition defendants’ judgment on its counterclaim be set off. Plaintiff’s answer to the counterclaim admitted the performance of the work on the St. Louis project by defendants and the demand and refusal to pay the $4,900.00. The answer also set up the defense the contract under which both plaintiff and defendants were working on the Carr Square Village project contained certain completion dates and provided for penalties for failure to comply with such dates; that knowing of such penalties defendants failed to reasonably carry on the work which they undertook to do and so unreasonably and belatedly carried on such work as to cause breaches of said contract with respect to the completion dates; that as a direct and proximate result of defendants’ activities penalties accrued under the contract which after all allowances resulted in a reasonable and proper charge by the St. Louis Housing Authority against plaintiff in the amount of $4,900.00; that this sum was retained and not paid to plaintiff by the Housing Authority under the contract; and that plaintiff was damag *211 ed by the failure of defendant to reasonably do its work in accordance with the contract by that amount. In their reply defendants denied they failed to reasonably carry on the work or cause a breach of the contract; stated that any penalties assessed against plaintiff were improper and arbitrary; denied that they orally or in writing agreed and assumed to pay for any penalties; and stated that any delays were caused by conditions over which they had no control.

The parties filed a stipulation prior to the trial by which they agreed the amount of $4,900.00 was due the plaintiff under the contract sued on in the petition; that defendants agreed to do the work on the St. Louis Housing Authority project and “to complete in accordance with the Plans and Specifications * * * ” the work involved in connection with the installation of these boilers; that defendants did the work mentioned; “That subject to its admissibility and competency, it is agreed that a multitude of delays ensued with respect to the finishing of the conversion of the coal fired boilers * * * ”; and that the contract provides for certain completion dates and for liquidated damages in specified amounts in the event these dates were not met. The dates for completion and the amounts provided as liquidated damages as stipulated are the same as stated in the contract which was an exhibit and which will be set out more fully later herein. It was further stipulated extensions were applied for and some of them granted without charge by the Housing Authority which under the contract charged plaintiff a total of $4,900.00 as liquidated damages on account of delay; that plaintiff has paid defendants all amounts due excepting this sum; and that “ * * * the dispute in this law suit concerns whether or not defendants, under the law and the facts, owe plaintiff $4900.00 on account of said alleged delay and the charge made against plaintiff by the St. Louis Housing Authority, * *

The specifications for the Carr Square Village project were admitted into evidence over defendants’ objection. There are many provisions of this contract which would need to be stated in this opinion in order to rule upon all the allegations of error raised by defendants. However, it is our view that defendants’ allegation of error with respect to the damages constituting a penalty is determinative of this appeal and we will confine our résumé of the contract and other pertinent evidence to that bearing upon this issue. In so doing it is apparent that we assume arguendo plaintiff’s strongest case; i. e., it is correct as to the admissibility of Exhibit “B”. Our ruling upon that point is then unnecessary to the disposition of this appeal and renders superfluous a summarization of the voluminous provisions of this exhibit which constitute the contract between plaintiff and the Housing Authority and which plaintiff contends also bind the defendants.

The evidence showed that prior to the 15th day of July, 1958, the Housing Authority requested bids for the purpose of converting three (3) furnaces in the Carr Square Village project from coal firing furnaces to combination oil and gas fired burners. The defendants as subcontractors submitted their bid for $30,800.00 for a portion of the work to the plaintiff as prime contractor. The bids were opened on July 15, 1958, and plaintiff was advised it was the successful bidder on that same day. However, plaintiff did not sign its contract with the Housing Authority until August 13th. The Housing Authority sent plaintiff a “Notice to Proceed” on August 27, 1958, the terms of which directed plaintiff to commence work on September 2, 1958. On August 28, 1958, plaintiff wrote the Housing Authority requesting extension of contract completion time stating the bid was submitted to the Housing Authority on July 15, 1958, but due to “delays beyond our control, we did not receive notice to proceed until August 28, 1958”, and, “We do not believe it is possible to have the two (2) boilers in operation by October 15, *212

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strouse v. Starbuck
987 S.W.2d 827 (Missouri Court of Appeals, 1999)
Luna v. Smith
861 S.W.2d 775 (Missouri Court of Appeals, 1993)
Standard Improvement Co. v. DiGiovanni
768 S.W.2d 190 (Missouri Court of Appeals, 1989)
Taos Construction Co. v. Penzel Construction Co.
750 S.W.2d 522 (Missouri Court of Appeals, 1988)
Grand Bissell Towers, Inc. v. Joan Gagnon Enterprises, Inc.
657 S.W.2d 378 (Missouri Court of Appeals, 1983)
Highland Inns Corp. v. American Landmark Corp.
650 S.W.2d 667 (Missouri Court of Appeals, 1983)
Berger v. McBride & Son Builders, Inc.
447 S.W.2d 18 (Missouri Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
423 S.W.2d 209, 1967 Mo. App. LEXIS 549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corrigan-co-mechanical-contractors-inc-v-fleischer-moctapp-1967.